Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC327-4347 | 36 - Volunteers | By December 2023, the Rural Fire Service should: develop a strategy to ensure that local brigade volunteers are adequate in numbers and appropriately trained to operate fleet appliances in the RFS Districts where they are required. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4306 | 6 - Insurance and legal liability | NSW Reconstruction Authority: That, to provide rapid and effective recovery from floods (and other disasters) and to provide maximum mitigation of the impacts of future floods (and other disasters), Government establish a permanent state-wide agency, the NSW Reconstruction Authority (NSWRA) dedicated to disaster recovery, reconstruction and preparedness. The NSWRA should: |
REC324-4315 | 36 - Volunteers | The Community First Responders Program: That, to better coordinate community efforts to save life and property during a disaster, Government create a ‘Community First Responders Program’, funding appropriate community equipment and training, particularly in high-risk catchments along the east coast of NSW. This training would be delivered by combat and/or other appropriate government agencies. This program could support and empower community led initiatives such as disaster response, evacuation centres and the provision of services such as psychological first aid. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4223 | 5 - Hazard reduction burns | The Inspector-General Emergency Management recommends the Department of Environment and Science implements the proposed treatments for fire identified in the Queensland Parks and Wildlife Service K’gari Compliance Strategy. |
REC322-4248 | 5 - Hazard reduction burns | The Inspector-General Emergency Management recommends the prescribed burn program for K’gari be developed by the Department of Environment and Science, in collaboration with the Locality Specific Fire Management Group and the Butchulla people, based on the principles of the National Position on Prescribed Burning. This program should incorporate a process for monitoring and evaluation of outcomes and integration of evolving fire management practices. |
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4202 | 10 - Infrastructure | We recommend that DELWP investigates incentives and advises government on options to accelerate burying and insulating the remaining high-voltage bare-wire powerlines in the 33 highest risk areas. |
REC321-4201 | 10 - Infrastructure | We recommend that DELWP improves the Powerline Bushfire Safety Program's transparency by publicly reporting on activities, costs and risk-reduction outcomes. |
REC321-4217 | 5 - Hazard reduction burns | We recommend that DELWP in partnership with Country Fire Authority and Fire Rescue Victoria develops, implements and publicly reports on a holistic suite of performance metrics to demonstrate: - the impact that planned burning has on public and private land on bushfire risk - the impact that planned burning has on public and private land on ecosystem resilience - the impact that non-burn fuel management activities have on public and private land on bushfire risk - the impact that its activities at local and regional levels have on bushfire risk - the cost-effectiveness of its fuel management activities on public and private land. |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4197 | 36 - Volunteers | Relief and recovery capability: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department develop and resource an ongoing strategy to coordinate spontaneous volunteers that can be activated before, during or after emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4185 | 15 - Inter-service cooperation | The Inspector-General for Emergency Management recommends that Emergency Management Victoria works with the emergency management sector and relevant emergency management entities in New South Wales and South Australia to identify and address key cross border operational and resource management issues. This engagement should aim to enhance interoperability and maximise the capability and capacity of agencies to work together during emergencies along Victoria’s borders. |
REC318-4184 | 15 - Inter-service cooperation | The Inspector-General for Emergency Management recommends that Emergency Management Victoria collaborate with the emergency management sector to develop a capacity model that considers current and future: |
REC318-4179 | 15 - Inter-service cooperation | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in accepting that emergency management is a ‘shared responsibility’ - collaborate with the emergency management sector and community to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4075 | 6 - Insurance and legal liability | The Australian Government should afford appropriate legal protections from civil and criminal liability to Australian Defence Force members when conducting activities under an authorisation to prepare for, respond to and recover from natural disasters. |
REC317-4070 | 10 - Infrastructure | Australian, state and territory governments should expedite the delivery of a Public Safety Mobile Broadband capability. |
REC317-4124 | 6 - Insurance and legal liability | In reviewing the Disaster Recovery Funding Arrangements, Australian, state and territory governments should examine the small disaster criterion, and financial thresholds generally. |
REC317-4081 | 18 - Access to fire ground | State and territory governments should provide information to the public on the closure and opening of roads. Information should be provided in real-time, or in advance based on predictions, where possible. |
REC317-4083 | 10 - Infrastructure | The Australian Government should work with state and territory governments and critical infrastructure operators to improve information flows during and in response to natural disasters: |
REC317-4113 | 6 - Insurance and legal liability | The insurance industry, as represented by the Insurance Council of Australia, working with state and territory governments and other relevant stakeholders, should produce and communicate to consumers clear guidance on individual-level natural hazard risk mitigation actions insurers will recognise in setting insurance premiums. |
REC317-4080 | 18 - Access to fire ground | State and territory governments should include road closure and opening information on all roads within their borders on public apps. |
REC317-4082 | 10 - Infrastructure | The Australian Government, working with state and territory governments and critical infrastructure operators, should lead a process to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4043 | 15 - Inter-service cooperation | NDIA be engaged in regard to information sharing in emergencies as part of the above actions. |
REC316-4034 | 15 - Inter-service cooperation | Efforts be increased to build trust, confidence and a common operating picture across PCS and RFS and seek mechanisms that identifies RFS and PCS as equitable partners in delivery of fire management across the territory. |
REC316-4019 | 15 - Inter-service cooperation | In collaboration with other jurisdictions the ACT share the learnings for this bushfire event and work to officially embedded values officers and RRATs as key elements of bushfire response. |
REC316-4017 | 15 - Inter-service cooperation | The working group (Rec 1) should include relevant stakeholders deciding collectively what the declaration might mean for such things as sub and supporting plans and the relevant community messages and calls to action. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3826 | 10 - Infrastructure | That, in order to maximise the protection of critical infrastructure in a bush fire, Australian governments revise the regulatory framework for the provision to government authorities of information about all critical infrastructure (public and private) including a possible change to compel the owners of critical assets to provide all needed metadata, updated annually, for appropriate planning, preparation and response for bush fire. This would include information about location, ownership, access, details of service the infrastructure supports, and fire treatments of building and surrounding zones. |
REC315-3806 | 15 - Inter-service cooperation | That the NSW RFS work with AFAC to analyse the impact of changing fire seasons on inter- jurisdictional resource sharing agreements, both domestic and international, and determine any flow-on effects for NSW fire fighting personnel capacity. |
REC315-3863 | 15 - Inter-service cooperation | That, in order to provide real-time information on evacuation doorknocking during emergency events, Government explore a shared data gateway for NSW agencies based on the NSW State Emergency Service Collector app and a common mapping and analytics platform. |
REC315-3856 | 10 - Infrastructure | That, in order to improve response times to Triple Zero calls, the NSW RFS implements the integrated dispatch system before the 2020-21 fire season commences. |
REC315-3817 | 5 - Hazard reduction burns | That Government, noting that hazard reduction targeted in proximity to assets is on balance more likely to provide help than hinder, should: |
REC315-3851 | 10 - Infrastructure | That, to ensure mobile generators are sourced and distributed on a priority basis during natural disasters, the EUSFAC work with the NSW Telco Authority, relevant NSW government agencies and commercial stakeholders to develop a mobile asset deployment strategy. The strategy should reduce duplication in purchasing, maintaining and housing mobile generators and improve agility in deployment. |
REC315-3835 | 15 - Inter-service cooperation | That, in order to ensure the safety of local landholders on firegrounds, the NSW RFS emphasises the importance of local landholders using protective clothing while fire fighting as part of the RFS’ ‘Farm Fire Unit Integration’ priority for 2020-21. |
REC315-3816 | 5 - Hazard reduction burns | That Government re-commit to the current, regionally based approach to planning and coordinating hazard reduction activities across all tenures through Bush Fire Management Committees but ensure that it is actually being implemented at a high-level of quality across NSW. Getting it to a high-level of quality requires: |
REC315-3827 | 10 - Infrastructure | That, in order to minimise communication outages and extend basic communication coverage during bush fires, the NSW Government work directly, or together with other Australian governments and/or their relevant power and telecommunications regulatory, policy and market bodies, to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
REC314-3264 | 6 - Insurance and legal liability | Consider removing stamp duty from home insurance to encourage a wider section of the community to take out insurance. South Australian government agencies should share their risk modelling data with the Insurance Council of Australia. |
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2475 | 15 - Inter-service cooperation | Greater emphasis be placed on pre-planned and pre-determined arrangements between the Australian Defence Force and State and local agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
REC308-2463 | 6 - Insurance and legal liability | Principles, applicable to all tourist budgets, covering liabilities for costs and shelter in the event of evacuation should be developed and promulgated as part of tourism marketing. |
Rec-ID | Code | Recommendation |
---|---|---|
REC302-2400 | 15 - Inter-service cooperation | Until a single call centre is developed, continue deployments of a senior RFS officer to Fire and Rescue NSW ComCen on a 24/7 day basis. This arrangement should determine the quickest most suitable resource and who is ‘in charge’ of an incident |
REC302-2396 | 15 - Inter-service cooperation | The Commissioners of Fire and Rescue NSW (FRNSW) and the RFS issue an instruction to FRNSW ComCen that while AVL capability is being made available to the RFS vehicle fleet, no offers of assistance by one agency to the other in combatting a fire is rejected or delayed if what is being offered is appropriate |
REC302-2394 | 15 - Inter-service cooperation | Take immediate steps to eliminate fire boundaries for call and dispatch purposes to create an agnostic approach to the threat of fires from both a departmental and organisational perspective |
REC302-2393 | 15 - Inter-service cooperation | In recognising the success of the work of both the volunteer based Rural Fire Service and the full time Fire and Rescue NSW (FRNSW) members in joint operations – both agencies should be represented at major briefings or press conferences to reinforce successful integrated collaborative efforts rather than individual agency achievements |
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2384 | 36 - Volunteers | TFS should pursue the creation of a cadre of volunteer remote area firefighters. In doing so the TFS should not consider itself limited to upskilling of current volunteer brigade members, but should carry out a cost benefit analysis of creating one or more remote area firefighting units based in urban areas, in order to tap into the potential of those members of the urban-based Tasmanian community who may have advanced knowledge and skills relating to navigation and survival in wilderness areas. |
REC301-2383 | 15 - Inter-service cooperation | Tasmanian Fire Service (TFS), Tasmanian Parks and Wildlife Service (PWS) and Sustainable Timber Tasmania (STT) initiate a discussion among their Australasian peers about good practice around managing new fire starts in remote terrain, to include issues around identification, predictive analysis, risk management and suppression activities. The outcome should be a document which allows for benchmarking to accepted good practice across Australasia, from which Tasmanian fire agencies can develop protocols against which the management of future events can be tested. |
REC301-2388 | 15 - Inter-service cooperation | TFS, PWS and STT should establish a State Air Desk, to be staffed by specialist staff year-round, with responsibility for managing both preparatory and contractual issues out of season as well as aircraft management when fires or other emergency events are occurring. |
REC301-2386 | 15 - Inter-service cooperation | TFS, PWS and STT should work with government and each other to continue to pursue a whole-of-state fuel management and burning program that encompasses all land tenures, meets the range of outcomes required by the state (township protection, risk reduction and landscape-scale burns) and is inclusive of private landholders and local communities as well as all fire agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1345 | 36 - Volunteers | That issues of animal welfare be given a higher practical priority in the planned burning process on the ground, including: |
REC299-1342 | 6 - Insurance and legal liability | That fire managers responsible for planned burns be |
REC299-1347 | 5 - Hazard reduction burns | In order to manage a reduced time window available to undertake the current types of planned burns, alternative methods, including the indigenous mosaic ‘cool’ burns, should be examined and trialled as they may extend the period in which planned burns can be undertaken while reducing overall risk and fuel loads. |
REC299-1341 | 5 - Hazard reduction burns | That in conjunction with a risk‑based approach, a minimum hectare target is also maintained that can be measured and compared. This minimum target should not be below the 5% target established by the Victorian Bushfire Royal Commission. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1305 | 18 - Access to fire ground | That the annexure to the State Emergency Management Plan, ‘Traffic management during emergencies’, be updated to include: responsibilities and processes for road closures; and, Department of Planning, Transport and Infrastructure requirements in regards to provision of road closure information, notification of changes in road closure status and publishing of that information. |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1234 | 5 - Hazard reduction burns | The Department of Parks and Wildlife to plan for the highest priority hazard reduction burning effort around settlements and critical assets in the South West and Perth Hills. The annual objective is to treat a total of 60,000 hectares of priority hazard reduction per annum, comprising 20,000 hectares per annum of Land Management Zone A and 40,000 hectares per year of Land Management Zone B. |
REC291-1242 | 15 - Inter-service cooperation | The Departments of Fire and Emergency Services and Parks and Wildlife to investigate and adopt an emergency services resource management system that will enable the registration, tasking, tracking, management and coordination of emergency management personnel, vehicles, plant and aircraft. |
REC291-1246 | 18 - Access to fire ground | The State Emergency Management Committee to review the policy for traffic management at emergency incidents so it reflects national ‘best practice’. This includes the production and issuing of an aide-memoire to guide traffic management, emergency and incident management personnel. |
REC291-1237 | 5 - Hazard reduction burns | The Department of Fire and Emergency Services, utilising the Office of Bushfire Risk Management, to develop a simplified and fast track hazard reduction burn (and other fuel mitigation techniques) planning and approval process to ensure the timely conduct of township and asset protection burns by Bush Fire Brigades and individual property owners. The process is to be agile and adaptable for the range of stakeholders which may participate in low risk, small scale, low complexity burn planning and approvals. |
REC291-1245 | 18 - Access to fire ground | The Department of Fire and Emergency Services to issue a photo identification card to DFES members, members of Bush Fire Brigades, volunteer emergency services, Incident Management Teams, forestry industry brigade members and Networked Government Emergency Agency members. DFES also to consider temporary windscreen signage to identify vehicles carrying such personnel. |
REC291-1235 | 5 - Hazard reduction burns | The Department of Parks and Wildlife to continue emphasis on landscape hazard reduction burning with the annual objective of treating 140,000 hectares per annum in Land Management Zone C. In combination with Recommendation 2 (above) the strategic objective will be that a fuel age of less than six years will be maintained across 45% of the landscape on State Forest, National Parks and other Parks and Wildlife managed lands in the South West and Perth Hills. This will address the current backlog (created from under achievements of the recent two decades of burn programs) by the end of the 2020-2021 burning season (i.e. within the next 5 years). |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1210 | 15 - Inter-service cooperation | Co‐designed arrangements that support a unified response to fire |
REC290-1209 | 15 - Inter-service cooperation | Coordinated and targeted mitigation of fire risk |
Rec-ID | Code | Recommendation |
---|---|---|
REC288-1195 | 5 - Hazard reduction burns | The Committee finds that on the evidence presented, that the Fuel Reduction Burn Program should be maintained and have its budget directly funded to ensure that the program continues and does not hinder other services or programs. |
REC288-1199 | 36 - Volunteers | The Committee finds that on the evidence presented, that volunteer firefighters are at risk of being undervalued and underrated and that the Government should use best endeavours to ensure the full acknowledgement and recognition of these services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC287-1179 | 15 - Inter-service cooperation | The Tasmanian fire agencies develop a joint multi-agency Fire Preparedness Matrix to guide decision-making in response to severe fire weather conditions or capacity issues. |
REC287-1180 | 15 - Inter-service cooperation | The Tasmanian fire agencies consider the development of fire operational guidelines to avoid long-term environmental impacts such as: • • • strategies and tactics that will minimise the impact of fire management activities conditions under which earthmoving equipment and fire chemicals may be used information on seasonal conditions and the times of year when various strategies and tactics should be applied, and fuel management strategies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-2078 | 15 - Inter-service cooperation | Review interagency information sharing arrangements. |
REC286-2020 | 6 - Insurance and legal liability | Improve insurance affordability. |
REC286-2014 | 15 - Inter-service cooperation | Integrate non-government entities into emergency response and recovery arrangements. |
REC286-2016 | 6 - Insurance and legal liability | Review legal liability of participants in prevention and mitigation preparedness, response and recovery activities. |
REC286-1441 | 5 - Hazard reduction burns | Continue the Fuel Reduction Program. |
REC286-1479 | 6 - Insurance and legal liability | Ensure appropriate levels of insurance of public assets from flood risks. |
REC286-2084 | 10 - Infrastructure | Establish emergency services ICT redundancy arrangements for damage loss of communications infrastructure. |
REC286-2077 | 6 - Insurance and legal liability | Improve working relationship with the insurance industry to access impact information. |
REC286-2031 | 10 - Infrastructure | Improve information about electricity demand during heatwaves. |
REC286-1467 | 15 - Inter-service cooperation | Review the allocation of responsibilities for earthquake risk management. |
REC286-2076 | 36 - Volunteers | Review volunteering arrangements to improve recruitment and retention. |
REC286-2047 | 6 - Insurance and legal liability | Raise public awareness of the limitations of general insurance relating to landslide. |
REC286-1465 | 15 - Inter-service cooperation | Improve the coordination and delivery of the National seismic monitoring program. |
Rec-ID | Code | Recommendation |
---|---|---|
REC285-2521 | 36 - Volunteers | The report recommends that Ambulance Tasmania investigate whether higher proportions of volunteers were impacting on mobilisation times in the North. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
Rec-ID | Code | Recommendation |
---|---|---|
REC280-1375 | 5 - Hazard reduction burns | That the NSW Government commit to and fund a long term program of prescribed burning based on the recommendation of the 2009 Victorian Bushfires Royal Commission of an annual rolling target of a minimum of five per cent of public land per year, and that the NSW Government commit to extending the funding for the National Parks and Wildlife Service five year hazard reduction program past 2016. |
REC280-1378 | 5 - Hazard reduction burns | That the NSW Rural Fire Service: -improve accountability in relation to the implementation of bush fire risk management plans as a means of delivering more hazard reduction. |
REC280-1402 | 6 - Insurance and legal liability | That the Ministry for Police and Emergency Services and NSW Treasury: |
REC280-1393 | 36 - Volunteers | That the NSW Rural Fire Service formally recognise the Volunteer Fire Fighters Association as a legitimate advocacy organisation representing volunteer bush fire fighters, and duly consult with it on policy and operational matters. |
REC280-1377 | 5 - Hazard reduction burns | That the NSW Rural Fire Service, in collaboration with the NSW National Parks and Wildlife Service, review and improve the system of bush fire management zones to ensure that greater priority is given to hazard reduction on land classified within land management zones. |
REC280-1401 | 6 - Insurance and legal liability | That the NSW Government take all reasonable steps to expedite the process of establishing any legal liability for the losses incurred by property owners as a result of the Wambelong fire, and in the event that it is found liable, expedite the process of paying compensation claims. |
REC280-1392 | 36 - Volunteers | That the NSW Rural Fire Service, in order to ensure greater respect for volunteer fire fighters’ knowledge and experience in the management of fires: |
REC280-1376 | 5 - Hazard reduction burns | That the NSW National Parks and Wildlife Service establish a regime of frequent mosaic burning within the Warrumbungle National Park, where conditions permit, to be monitored and evaluated via a formal fully funded research program. This program should then inform the Service’s approach to the wider national park estate. |
REC280-1400 | 6 - Insurance and legal liability | That the Office of State Revenue investigate mechanisms to enhance the affordability of insurance for properties and assets in fire affected areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC279-1230 | 36 - Volunteers | Volunteer Retention: By April 2015, develop strategies and resources to improve volunteer retention, including: a) induction and development of leaders b) health checks for units to identify and address areas for improvement c) pathways for volunteers to take on greater responsibility d) consultation and communication e) recognition for volunteers and their employers |
REC279-1228 | 36 - Volunteers | Volunteer Workforce Plan: By December 2014, develop a volunteer workforce plan to focus resources for recruitment and retention on areas of greatest need. The plan should be based on regional capability plans that assess in a consistent way: a) how many volunteers they have and need b) the gaps and risks around volunteer numbers, skills and training |
REC279-1227 | 36 - Volunteers | Improve Analysis and Reporting: By December 2014, improve analysis and reporting on management information about volunteers, including: a) numbers, contribution, skills, profile, availability and turnover b) reasons for joining and leaving c) gaps in data completeness and quality This should enable SES to demonstrate an improvement in the completeness and accuracy of management information by April 2015 |
Rec-ID | Code | Recommendation |
---|---|---|
REC276-1176 | 36 - Volunteers | Within 12 months, improve its processes for collecting and maintaining volunteer membership, availability and training records. To do this it will need to work with local information. governments to improve the accuracy of LG volunteer membership |
REC276-1175 | 36 - Volunteers | Continue to implement the major change projects it has in place, including Professional Pathways, and review them to assess if they will address all the key findings in this report. In particular, within six months DFES should set priorities and Sustainability Strategy. begin implementing the Emergency Services Volunteer Workforce |
REC276-1177 | 36 - Volunteers | Within 12 months, develop volunteer specific policies and procedures, including fatigue management, consistent with the Guidelines for Successful Partnerships between Public Sector Agencies and Volunteers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC274-1404 | 15 - Inter-service cooperation | That the Department of Health & Human Services and the Department of Justice & Regulation, in consultation with their portfolio emergency service agencies that have response time measures, determine relevant targets for these. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1132 | 15 - Inter-service cooperation | Noting the implementation of Common Incident Command and Control System (CICCS) in SA that fire and emergency services together with police (including through AFAC and ANZPAA), continue to liaise regarding the development of a national incident management. |
REC273-1131 | 15 - Inter-service cooperation | That the Emergency Management Australia’s ‘Arrangements for Interstate Assistance (Fire and Emergency Services)’ be applied to all future requests for assistance by the SACFS, SAMFS and SASES. |
REC273-1142 | 18 - Access to fire ground | That SACFS consider the Traffic Management Procedures and guiding principles adopted in Tasmania as a model that could be implemented within SA. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1525 | 6 - Insurance and legal liability | The Department of Energy and Water Supply, in conjunction with SunWater, seek clarification of the dam owners’ legal obligation to comply with Emergency Action Plans and, if required, investigate how a more flexible approach may be adopted. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1149 | 15 - Inter-service cooperation | PES External Surge Program The success of the PES External Surge Program and the willingness of participants to deploy at short notice to support the recovery effort is commendable, as is the readiness of their supervisors to release them from their duties to enable deployment. The Program, supported by an appropriate training program, is one that should be sustained as part of the whole of Government recovery readiness effort. |
REC267-1154 | 36 - Volunteers | Coordination of Volunteer Support |
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1106 | 15 - Inter-service cooperation | In addition to regular meetings of the DFES/DPaW Interagency Bushfire Management Committee, the two organisations should use joint exercises to identify agreed firefighting approaches for common or likely scenarios. |
REC265-1122 | 18 - Access to fire ground | DFES, in consultation with bushfire volunteers should develop a procedure for the controlled entry and exit of volunteers to the fire ground |
REC265-1105 | 15 - Inter-service cooperation | The Executive Teams of both DFES and DPaW should meet quarterly to review and agree joint improvements relating to issues of interoperability, complementarity and the alignment of firefighting doctrine. The establishment of a unified command in joint State Operations Centre, Regional Operations Centre and Incident Management Teams should be pursued as an overarching goal. |
REC265-1121 | 18 - Access to fire ground | A Restricted Access Permit system for the entry/ re-entry of residents, based on the one developed for the Parkerville Stoneville Mt Helena Bushfire should be finalised. |
REC265-1111 | 15 - Inter-service cooperation | All agencies engaged in bushfire response should develop expeditious procedures for the mobilisation of resources in support of other agencies. See discussion in Section 7.1. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
REC264-1073 | 15 - Inter-service cooperation | The State establish, for any future incident, integrated incident management teams with GDF Suez and other Victorian essential industry providers, to: • essential industry providers; and require that emergency services personnel work with GDF Suez and other appropriate • implement the Australasian Inter-service Incident Management System. |
Rec-ID | Code | Recommendation |
---|---|---|
REC263-1094 | 36 - Volunteers | CFA and VICSES should: evaluate volunteer support systems and processes |
REC263-1093 | 36 - Volunteers | VICSES should: review and improve data quality around volunteer numbers and skills |
REC263-1095 | 15 - Inter-service cooperation | CFA and VICSES should: explore further opportunities to collaborate with each other. |
REC263-1091 | 36 - Volunteers | CFA and VICSES should: develop recruitment and retention strategies to guide these activities centrally, regionally and at the district, brigade and unit level, so that approaches are consistent with the organisations’ strategic goals |
REC263-1090 | 36 - Volunteers | CFA and VICSES should: improve their central and regional oversight of volunteer workforce management by strategically using the available information, such as volunteer demographic data, Brigade Operational Skills Profiles and ERAS-e profiles, and developing new information, such as risk assessment, to increase their awareness of: x x actual and required volunteer numbers the gaps and risks around volunteer capability and capacity |
REC263-1098 | 36 - Volunteers | VicSES should: improve ERAS-e profiles to reflect volunteer activity and availability |
REC263-1096 | 36 - Volunteers | CFA should: develop exit surveys and associated management reports based on meaningful analysis as a way to better inform it about the reasons that volunteers leave |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1490 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority critically reviews: |
REC262-1482 | 15 - Inter-service cooperation | That Emergency Management Victoria be responsible for facilitating the interoperability of all organisations involved in emergency response, including the Emergency Services Telecommunications Authority and Ambulance Victoria. |
REC262-1489 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority reclassifies its State Emergency Communications Centres as critical national infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1495 | 5 - Hazard reduction burns | That the NSW Rural Fire Service: |
REC261-1518 | 6 - Insurance and legal liability | That the NSW Government take all reasonable steps to expedite the process of establishing any legal liability for the losses incurred by property owners as a result of the Wambelong fire, and in the event that it is found liable, expedite the process of paying compensation claims. |
REC261-1493 | 5 - Hazard reduction burns | That the NSW National Parks and Wildlife Service establish a regime of frequent mosaic burning within the Warrumbungle National Park, where conditions permit, to be monitored and evaluated via a formal fully funded research program. This program should then inform the Service’s approach to the wider national park estate. |
REC261-1517 | 6 - Insurance and legal liability | That the Office of State Revenue investigate mechanisms to enhance the affordability of insurance for properties and assets in fire affected areas. |
REC261-1500 | 10 - Infrastructure | That the NSW Government improve the protection of media and telecommunications towers around New South Wales by: |
REC261-1510 | 36 - Volunteers | That the NSW Rural Fire Service formally recognise the Volunteer Fire Fighters Association as a legitimate advocacy organisation representing volunteer bush fire fighters, and duly consult with it on policy and operational matters. |
REC261-1519 | 6 - Insurance and legal liability | That the Ministry for Police and Emergency Services and NSW Treasury: |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1070 | 5 - Hazard reduction burns | The NPWS conduct a review of its prescribed burns program to ensure, as far as reasonably practicable, that all necessary managerial approvals for a prescribed burn are provided as promptly as possible. |
REC260-1061 | 18 - Access to fire ground | That the National Parks and Wildlife Service, in consultation with the relevant local Council(s), devise a policy that enables the John Renshaw Parkway to be closed at either end of the Warrumbungle National Park during a bush fire in such a way that its closure would not impede access by emergency services vehicles into the park. |
REC260-1063 | 5 - Hazard reduction burns | That the National Parks and Wildlife Service consider reviewing its guidelines and protocols in respect of hazard reduction planning and burning-off operations in the light of the evidence from experts witnesses in these proceedings that the incidence of, and intensity of, major fires is increasing and in the light of expert evidence given in these proceedings concerning the dangers of vorticity-driven lateral spread. |
REC260-1067 | 15 - Inter-service cooperation | That as part of the adoption of such a posture in ‘severe’ or worse fire conditions, the National Parks and Wildlife Service consider alerting, at an early stage, all relevant persons and organisations, such as shire councils, heavy plant operators, the local RFS captains, Fire & Rescue NSW and other emergency services, that it is doing so, and that their assistance may be required at short notice. |
Rec-ID | Code | Recommendation |
---|---|---|
REC259-1047 | 6 - Insurance and legal liability | That the insurance industry be asked to include in its “Code of Practice” the need to consult policy holders in bushfire prone areas on the issue of Bushfire Attack Level (BAL). This will ensure, to some extent, that policy holders insure their properties to a level commensurate with building costs under a variety of building standards and requirements.(For checking with RFS). |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2557 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority reassesses the penalties in the Civil Aviation Safety Regulations. |
REC258-2550 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority introduces grading of Non-Compliance Notices on a scale of seriousness. |
REC258-2544 | 6 - Insurance and legal liability | The Australian Transport Safety Bureau transfers information from Mandatory Occurrence Reports to the Civil Aviation Safety Authority, without redaction or de-identification. |
REC258-2543 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority reintroduces a ‘use of discretion’ procedure that gives operators or individuals the opportunity to discuss and, if necessary, remedy a perceived breach prior to CASA taking any formal action. This procedure is to be followed in all cases, except where CASA identifies a Serious and Imminent Risk to Air Safety. |
REC258-2559 | 15 - Inter-service cooperation | The Civil Aviation Safety Authority’s Director of Aviation Safety meet with industry sector leaders to jointly develop a plan for renewing a collaborative and effective Standards Consultative Committee. |
REC258-2540 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority continues to provide appropriate indemnity to all industry personnel with delegations of authority. |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1547 | 15 - Inter-service cooperation | The Marrangaroo Training Area Regional Environmental Officer confer with the local Rural Fire Service at least annually and determine a hazard reduction regime capable of implementation. It is furter recommended all ranges be reviewed in relation to the same issue, that is, that personnel involved in the management of each range under Defence control be directed to confer with local firefighting authorities on at least an annual basis to assess hazard reduction responses to be pursued for that range in subsequent years. |
REC257-1545 | 15 - Inter-service cooperation | Range Control Officer Marrangaroo Training Area liase with the local Rural Fire Service units to develop a map indicating the areas of the range likely to contain unexploded ordnance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1572 | 6 - Insurance and legal liability | Insurers should provide additional standardised information to households regarding their insurance policies, the natural hazards they face and indicative costs of rebuilding after a natural disaster. This work should be led by the Insurance Council of Australia developing guidelines, within one year, to ensure consistency in the provision and presentation of this information across insurers. |
REC256-1564 | 6 - Insurance and legal liability | State and territory governments, local governments and insurers should explore opportunities for collaboration and partnerships. Partnerships, for example, could be formed through the Insurance Council of Australia and state-based local government associations (or regional organisations of councils). Consideration could be given to the Trusted Information Sharing Network model. Partnerships could involve: |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1586 | 15 - Inter-service cooperation | Future coordination/support/control of integrated emergency management across all agencies in Albany needs to be merged and located in a single joint facility. This issue needs to be reviewed statewide. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0885 | 18 - Access to fire ground | That arrangements are made for and appropriate pre-planning occurs to effectively implement the policy on road closures and traffic management. |
REC247-0948 | 15 - Inter-service cooperation | That the Department of Justice conduct an independent review to develop a suitable model for integrated and interoperable emergency management arrangements in Tasmania. |
REC247-0904 | 10 - Infrastructure | That the Department of Infrastructure Energy and Resources consult Aurora Energy on the use of wooden poles for overhead infrastructure with a view to mitigating the risk in bushfires. |
REC247-0884 | 18 - Access to fire ground | That Tasmania Police reviews its Emergency Traffic Management Points policy; and develops a multi-agency policy in the emergency management plans for road closures and traffic management, including clarity in decision making, coordination and sufficient operational flexibility. |
REC247-0854 | 15 - Inter-service cooperation | That in multi-agency response and recovery operations, arrangements be made so it is unambiguous who is in charge of these operations. |
REC247-0939 | 5 - Hazard reduction burns | That Tasmania Fire Service conducts a review of the fire permit system in the Fire Service Act 1979, and implements change to improve the efficiency and effectiveness of the system by: • considering whether it is appropriate to authorise persons or organisations to conduct fuel reduction burning during a permit period • providing a better match between the period, area and fire risk • maintaining a timely and efficient process for issuing permits • naming the period in a way that draws attention to bushfire risk • establishing a reporting and accountability process. |
REC247-0906 | 18 - Access to fire ground | That emergency management plans recognise the need to provide priority access to areas of emergency operations for critical infrastructure providers. |
REC247-0895 | 6 - Insurance and legal liability | That action be taken as a priority to resolve any legal issues on mutual assistance arrangement for fire services. |
REC247-0938 | 5 - Hazard reduction burns | That Tasmania Fire Service or another suitable agency provides information to the community which shows, in simple form, the legislation applicable to approvals for lighting fires on private property and the various relationships between that legislation. |
REC247-0899 | 18 - Access to fire ground | That appropriate plans are made to mobilise resources quickly to re-open roads affected by emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC246-0789 | 6 - Insurance and legal liability | TFS seek legal opinion on the Bushfire CRC Research Report on legal liability implications of the Prepare, Stay and Defend or Leave Early policy to confirm the advice, consider the implications and implement those that are appropriate. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2621 | 36 - Volunteers | Greater attention needs to be given to the recruitment and retention of volunteers in alignment with the National Emergency Management Volunteer Action Plan. |
REC244-2616 | 6 - Insurance and legal liability | That once the review of the Emergency Management Act has been finalised, any reference to the liability of councils should be mirrored in both the EM Act and the F&ES Act. |
Rec-ID | Code | Recommendation |
---|---|---|
REC243-0842 | 36 - Volunteers | That the Government work with the volunteer community safety and emergency service providers to organise a comprehensive advertising campaign to promote the community and personal benefits of volunteering in the sector. |
REC243-0841 | 36 - Volunteers | That the Government consult broadly upon and review impediments to volunteering in the community and establish a taskforce to assist in removing barriers to volunteering, particularly with respect to: i harmonising the regime for reimbursement to community safety and emergency services volunteers for their out-of-pocket expenses; and ii reviewing the impact of work health and safety laws on the community safety and emergency service sector, particularly on the volunteer organisation. |
REC243-0843 | 6 - Insurance and legal liability | That the Government work with the Local Government Association to resolve questions of liability by volunteers who work for Councils, as raised with the Select Committee. |
REC243-0840 | 36 - Volunteers | That with regard to volunteer community safety and emergency service organisations that do not own land where their facilities exist: i. the Government audit all such land and consider gifting or providing at reduced or peppercorn rental Government-owned land to an organisation (and specifically the Select Committee recommends gifting the Adelaide Shores land to Surf Life Saving South Australia); and ii. the Government consider providing rebates to Councils that do not feel morally able to impose full commercial rent on community safety and emergency service volunteer occupied land. |
Rec-ID | Code | Recommendation |
---|---|---|
REC242-2645 | 36 - Volunteers | That the Government work with the Local Government Association to resolve questions of liability by volunteers who work for Councils, as raised with the Select Committee. |
REC242-2644 | 36 - Volunteers | That the Government work with the volunteer community safety and emergency service providers to organise a comprehensive advertising campaign to promote the community and personal benefits of volunteering in the sector. |
REC242-2642 | 6 - Insurance and legal liability | That with regard to volunteer community safety and emergency service organisations that do not own land where their facilities exist: |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-1017 | 36 - Volunteers | That each District office establish and maintain a register of suitably qualified Australasian Inter-service Incident Management System trained volunteers who are prepared to undertake the management of operations and provide these to the District Fire Management Group. |
REC241-0996 | 5 - Hazard reduction burns | That Section 66 (2) of the Fire and Rescue Service Act 1990 relating to the exemption for issuing of permits to burn in State Forests, National Parks and Reserves is withdrawn and Departments must work within the District Fire Management Plan. |
REC241-0978 | 36 - Volunteers | That in recognition of their commitment to the community volunteers employed by the State Government should be released to assist as volunteers for up to five (5) days per year in appropriately identified emergency operations. |
REC241-0995 | 5 - Hazard reduction burns | At the next reprint of the ‘Permit to Light Fire’ book, the requirement to notify neighbours when applying for a permit is reinstated to properly reflect the requirement under the Fire and Rescue Service Act 1990. |
REC241-0955 | 36 - Volunteers | That corporate support, such as administration and finance, to volunteer services be shared to enable a closer working relationship between the services. |
REC241-0994 | 5 - Hazard reduction burns | That the Rural Fire Service Queensland needs to provide greater emphasis and acknowledgement of the use of fire as a tool in sustainable land management. |
REC241-1016 | 6 - Insurance and legal liability | That a volunteer shall not be liable for any act or omission made in good faith provided it is not proven to be reckless, negligent or malicious. This protection is to be afforded in both Criminal and Common law. |
REC241-1040 | 36 - Volunteers | That RFSQ review local SAP function and delegation to enable effective and timely support for volunteers. |
REC241-0997 | 5 - Hazard reduction burns | That the electronic fire permit system used in the Mackay District be made available across the state for Fire Wardens who wish to use it. |
REC241-1004 | 15 - Inter-service cooperation | That a memorandum of understanding be developed between RFSQ and other organisations with fire fighting capacity at state level, to establish operational procedures when these organisations may be required for a joint response roles. Specifically, the intent will be: Vegetation Fire in a Rural Area: The Rural Fire Brigade in that area (boundary) is in charge and is the first Brigade called by Firecom. Structural Fire in a Rural Area: Firecom calls the Urban Brigade first and they control the incident. Local Rural Fire Brigade must also be notified by Firecom at the same time. Vegetation Fire in an Urban Levy Area: Firecom call the local Urban Brigade first and they control the incident. At their discretion they may call Rural Fire Brigades for assistance. Structural Fire in an Urban Levy Area: Firecom call the local Urban Brigade first and they control the incident. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2736 | 36 - Volunteers | That training for volunteers be reviewed to determine which courses require national standardisation. Organisational training should then address the remaining training needs. The review should take into account the risk exposure to government agencies if changes are to be made. |
REC239-2703 | 15 - Inter-service cooperation | That the protocols developed by the Queensland Police Service and SES for operations define the respective roles and responsibilities as well as recognise the varying capabilities of SES units across the State. |
REC239-2694 | 15 - Inter-service cooperation | That Queensland enters into a similar arrangement with Bureau of Meteorology to have an experienced forecaster seconded to Kedron State Disaster Coordination Centre for at least the duration of fire and storm seasons. |
REC239-2667 | 15 - Inter-service cooperation | That Queensland Corrective Service, the Queensland Police Service and Queensland Health should work together to develop a position that enables prisoners to have timely access to their prescribed medication despite travel between facilities and without the need for costly re-prescription. |
REC239-2746 | 36 - Volunteers | That volunteers should be engaged to assist in determining what constitutes ‘fit for task’ and how that should be implemented. |
REC239-2739 | 36 - Volunteers | That the Queensland Police Service and the Department of Community Safety develop intuitive, easily accessible systems that reduce the administrative burden on volunteers and their time. Greater exploitation of technology to deliver intuitive, simple and practical systems is required. |
REC239-2762 | 15 - Inter-service cooperation | That the Chief Executive Officer Portfolio Business in consultation with the Police Commissioner and the Commissioner Fire & Emergency Services should provide the direction for future information and communication technology strategies and acquisitions. |
REC239-2738 | 36 - Volunteers | That the current employer and family recognition practices be reviewed with a view to meet the needs of volunteers, their families and their employers. |
REC239-2761 | 15 - Inter-service cooperation | That systems development in the Queensland Police Service capitalises on the advances made by the Queensland Fire and Rescue Service in recent years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0799 | 18 - Access to fire ground | Develop and implement a program of cost-effective road improvement works that can enhance flood evacuation capacity in the short-medium term. |
Rec-ID | Code | Recommendation |
---|---|---|
REC230-2833 | 10 - Infrastructure | If recommendation 1 is not supported by the Australian Government, the committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate as a minimum requirement, 20 MHz in the 800 MHz band for the purposes of a public safety mobile broadband network. |
REC230-2832 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy take appropriate measures to secure, for public service agencies, priority access to an additional 10 MHz of spectrum in the 700 MHz band for public safety purposes. |
REC230-2831 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate 20 MHz of contiguous spectrum in the 700 MHz band for the purposes of a public safety mobile broadband network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC229-2844 | 15 - Inter-service cooperation | The committee recommends that Australian governments specifically address issues of compatibility and capacity to facilitate the most effective interoperability of emergency service organisations and their key personnel, especially for fire services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1623 | 15 - Inter-service cooperation | The Emergency Services Agency and the Territory and Municipal Services Directorate should develop and routinely review a strategic bushfire capability for the ACT. The contribution of ACT Fire and Rescue (including the Community Fire Units) and the ACT Rural Fire Service (including Parks Brigade) should be explicitly stated. |
REC228-1622 | 15 - Inter-service cooperation | The Emergency Services Agency and the Territory and Municipal Services Directorate should continue to improve working arrangements between the ACT Rural Fire Service Parks Brigade and the ACT Rural Fire Service headquarters, by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2847 | 15 - Inter-service cooperation | I recommend that Border Protection Command implement a surveillance strategy, possibly with the assistance of other Commonwealth authorities and organisations on the island such as the AFP, which heightens its coverage at times when the weather and sea conditions are rough. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0548 | 15 - Inter-service cooperation | Inter-agency cooperation to manage fire precincts in a tenure-blind fashion is necessary for effective fire suppression. |
REC226-0542 | 5 - Hazard reduction burns | A risk management approach is needed which considers risks both inside the prescribed burn and the risks that will need to be managed if the fire escapes. This risk assessment should be dynamic in line with the four day and seven day weather forecast. |
REC226-0553 | 5 - Hazard reduction burns | Rolling risk assessment conducted during ignition of prescribed burns should identify whether an escape is likely to develop into a Level 3 incident. As soon as possible after it has been identified that the escape cannot be contained, the incident should be declared a Level 3. |
REC226-0578 | 15 - Inter-service cooperation | There would be benefit in progressively aligning the geographic boundaries of each of the agencies and seeking to co-locate their headquarters within those boundaries. |
REC226-0544 | 5 - Hazard reduction burns | Prescribed burns which meet the ‘red flag’ criteria should have mandated risk Establish risk management criteria for management criteria imposed. |
REC226-0560 | 15 - Inter-service cooperation | There would be value in progressively aligning the geographical boundaries of emergency management agencies and co-locating where possible within regions and districts. |
REC226-0543 | 5 - Hazard reduction burns | There should be clearly established criteria for burns which are specially challenging, and these criteria need to extend beyond the intended boundaries of the prescribed burn. |
Rec-ID | Code | Recommendation |
---|---|---|
REC224-1634 | 10 - Infrastructure | The Minister for Emergency Services should urgently review the technical issues with the Western Australia Emergency Radio Network program that is forcing the State’s firefighters to revert to their older radio networks. |
REC224-1632 | 6 - Insurance and legal liability | The State Government prepare a consistent policy on how to assist or compensate the victims of future major natural disasters, such as bushfires, in an equitable fashion. |
REC224-1633 | 6 - Insurance and legal liability | The Treasurer undertake a review by the next bushfire season of the ability of RiskCover to efficiently undertake loss assessing and compensation activities for victims of major natural disasters, such as a bushfire, in an empathic and timely fashion. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0515 | 5 - Hazard reduction burns | The Department of Environment and Conservation urgently undertake a review of its risk management practices as they relate to prescribed burns including but not limited to: *reviewing risk management practices to ensure that they are in accordance with AS/NZS ISO 31000:2009; * finalising and implementing the new complexity model developed in house by the DEC; * considering a broader set of parameters of risk by conducting an environmental scan or similar tool for areas under consideration for a prescribed burn; *updating the prescribed fire plans to reflect the broader risk considerations discovered through environmental scanning; *better informing the risk considerations by updating the ‘Red Book’ to reflect current research on burning in coastal heath; and * reconsidering the utility of the ‘Red Flag Burn’ notification on files and either adopting it as a policy across the State or removing it as a consideration. |
REC223-0514 | 5 - Hazard reduction burns | The Department of Environment and Conservation review its current policies and operational guidelines in particular by: * strengthening the governance of operations by ensuring the Guidelines are relevant and practical; * ensuring the processes that are implemented for prescribed burns are: (a) value adding to the decisions and approvals required (b) informed by substantive input (c) focussed on outcome rather than process; *completing the draft management plan for the Leeuwin-Naturaliste Capes Area Parks and Reserves in accordance with the provisions of the Conservation and Land Management Act 1989; * exploring the possibility of automating and streamlining the various processes for formulating a prescription for prescribed burns for ease of access and updating; and * clarifying the guidance provided to decision makers as to the ‘edging’ and security of prescribed burns. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1857 | 15 - Inter-service cooperation | The Ministers for Health, Police, and Emergency Services ensure that the Western Australia Police, the Fire and Emergency Services Authority and St John Ambulance establish a formal platform to share their knowledge and experience in delivering programs to their staff and volunteers to address issues of stress from disasters and critical incidents, as is done in other Australian jurisdictions. |
REC222-1854 | 36 - Volunteers | The Premier amend Clause 35 of the Public Sector Award 1992 so that State Government employees who volunteer to assist the Australian Red Cross during a disaster are not required to take personal or annual leave. |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1874 | 15 - Inter-service cooperation | Fire services can improve outcomes by working with EPA as the regulator and licensing authority to achieve improved compliance with the required outcomes specified in the BPEM guidelines |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0701 | 6 - Insurance and legal liability | Letters notifying policy-holders that their claims have been denied should, at a minimum, state the information upon which the insurer has relied in making the decision. These letters should also advise policy-holders that copies of the information will be made available upon request (in accordance with clause 3.4.3 of the General Insurance Code of Practice) and indicate how policy-holders can make a request. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0699 | 6 - Insurance and legal liability | When a policy-holder makes a claim, the insurer should ascertain the policy-holder’s preferred method of contact and ensure that it is used (with other modes of communication if necessary) to keep the policyholder informed about the progress of the claim. However, important decisions regarding the claim – for example, determinations about the outcome of the claim and settlement sums – should always be confirmed in writing. |
REC210-0700 | 6 - Insurance and legal liability | Insurers should review their existing systems and processes and implement any improvements necessary to ensure that accurate and complete records of conversations with policy-holders are made. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0747 | 6 - Insurance and legal liability | Seqwater should ensure a legal review of the Wivenhoe manual and the North Pine manual is completed before the manual is submitted for approval. |
REC210-0686 | 6 - Insurance and legal liability | SunWater and the Central Highlands Regional Council should determine the issues of ownership and responsibility for maintenance of the LN1 drain system in Emerald. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0735 | 6 - Insurance and legal liability | The Crime and Misconduct Commission should investigate whether the conduct of Mr Tibaldi, Mr Ayre and Mr Malone relating to: • preparation of documents surrounding the January 2011 flood event, including the 17 January 2011 brief to the Minister, the 2 March 2011 flood event report, and statements provided to the Commission • oral testimony given to the Commission evidences offence/s against the Criminal Code, and/or official misconduct under the Crime and Misconduct Act 2001 committed by any, or all, of them. |
REC210-0757 | 15 - Inter-service cooperation | The protocol should make provision for the use of telephone and/or radio where communication by email is not possible. Where necessary, CS Energy and Seqwater should make additional radio equipment available to relevant personnel. |
REC210-0703 | 6 - Insurance and legal liability | The Insurance Council of Australia should amend clause 3.4.3 of the General Insurance Code of Practice so that it requires insurers to inform policy-holders of their right to request a review of an insurer’s decision to refuse to provide access to information on which it relied in assessing claims. |
REC210-0756 | 15 - Inter-service cooperation | CS Energy and Seqwater should agree upon and adhere to a formal communication protocol that requires CS Energy personnel to advise Seqwater, through the Flood Operations Centre, of water movements between Splityard Creek Dam and Wivenhoe Dam or Pryde Creek once a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. The protocol should ensure that a direct line of communication is established between CS Energy personnel physically located at the power station and the Flood Operations Centre. |
REC210-0702 | 6 - Insurance and legal liability | The Insurance Council of Australia should consider an amendment to Part 3 of the code which requires insurers to notify policy-holders of the information on which they relied in assessing claims. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
Rec-ID | Code | Recommendation |
---|---|---|
REC209-1671 | 15 - Inter-service cooperation | That Bushfires NT, NTFRS, DLP, Weeds Branch, Parks and Wildlife, the Natural Resources Management Board, Biodiversity staff and representatives of the Volunteer Fire Brigades get together, at least annually, to coordinate planning efforts for peri-urban areas. |
REC209-1669 | 15 - Inter-service cooperation | Conduct an information sharing and planning exercise between Bushfires NT and NTFRS to explore the current boundaries and the overlaps in the peri-urban areas between the NTFRS ERA and the Bushfires NT areas of responsibility for all major centres in the NT. |
REC209-1651 | 15 - Inter-service cooperation | Review the membership of the Bushfires Council, and the composition of Regional Committees to ensure that the Council and Committees have representational stakeholders. |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1906 | 6 - Insurance and legal liability | Governments should not subsidise household or business property insurance, whether directly or by underwriting risks. |
REC205-1905 | 6 - Insurance and legal liability | The Australian Government should only proceed with reforms that require all household insurers to offer flood cover if it can be demonstrated that the benefits to the wider community would exceed the costs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1910 | 6 - Insurance and legal liability | As part of its review of its contract management processes, Tourism WA (with the Board of Tourism WA taking a lead role) should amend its contract template for event sponsorship to ensure that: |
REC204-1914 | 15 - Inter-service cooperation | FESA, WA Police and St John Ambulance establish a uniform protocol for handling multiple agency emergency responses that does not involve callers having to make multiple calls to 000. |
REC204-1920 | 6 - Insurance and legal liability | The Attorney General gives urgent consideration to determining an ex gratia payment for: |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0282 | 5 - Hazard reduction burns | The burn prescription should capture the fuel characteristics and potential rate of spread for those areas outside the burn that will likely be critical during the initial attack on any escaping fire. |
REC203-0289 | 18 - Access to fire ground | There needs to be a better appreciation of the role of Vehicle Control Points (VCPs) and how they are managed in bushfire emergencies by all key agencies and the community |
REC203-0276 | 5 - Hazard reduction burns | There should be clearly established criteria for burns which are specially challenging, and these criteria need to extend beyond the intended boundaries of the prescribed burn. The criteria should be clarified and adopted as agency S OPs. |
REC203-0301 | 15 - Inter-service cooperation | Early in an incident, close and effective liaison needs to be established with local government agencies. |
REC203-0281 | 5 - Hazard reduction burns | Prescriptions need to be interpreted by experienced and knowledgeable personnel to ensure risk is fully understood. It is important that the background and justification for these decisions are captured at each stage and are visible to all levels in WA fire management hierarchy. |
REC203-0286 | 5 - Hazard reduction burns | Decisions taken on the basis of this risk assessment need to be captured and distributed across district and state. |
REC203-0299 | 15 - Inter-service cooperation | The state should converge on a single communications platform for all emergency management and support agencies. |
REC203-0280 | 5 - Hazard reduction burns | Contingency plans for escaping burns should be prepared in advance. |
REC203-0285 | 5 - Hazard reduction burns | A rolling risk assessment is required which captures the risks of the burn escaping and provides adequate resources. |
REC203-0298 | 15 - Inter-service cooperation | The state should progressively align on a shared platform, such as WebEO C , to establish a Common Operating Picture (COP). |
REC203-0292 | 18 - Access to fire ground | There is a need for community education on how road-blocks and VCPs operate in the event of an emergency. |
REC203-0279 | 5 - Hazard reduction burns | Once a burn is ignited, it needs to be the subject of continuing risk assessment and appropriate mitigation. |
REC203-0284 | 5 - Hazard reduction burns | DEC should investigate embedding an experienced forecaster in the state operations centre. |
REC203-0288 | 15 - Inter-service cooperation | The State Duty Officer from DEC and the State Duty Director, FES A need to confer whenever a Level 2 or 3 incident is declared to satisfy themselves that they have appropriate incident management structures and resources across the state are at an appropriate level of preparedness. |
REC203-0291 | 18 - Access to fire ground | Local knowledge should be accessed to inform the placement and operation of VCPs. |
REC203-0278 | 5 - Hazard reduction burns | Prescriptions should mandate consideration of measures to retire risk. |
REC203-0283 | 5 - Hazard reduction burns | Core ignition, particularly of red flag burns, should be informed by the 4 & 7 day forecasts (including a longer term perspective over 3 to 4 months) |
REC203-0287 | 15 - Inter-service cooperation | On a regional basis there would be value in closer working relationship between DEC crews and VBFBs to build mutual trust and confidence. This could be done by opportunity engagement of VBFBs in DEC fire management or through exercises. |
REC203-0290 | 18 - Access to fire ground | VCPs are one of the instruments by which the Incident Controller manages the emergency. VCPs without communications cannot be fully effective in their role. Determine and implement an appropriate communications platform for emergency management |
REC203-0277 | 5 - Hazard reduction burns | A risk-management approach is needed which considers risks both inside the prescribed burn and the risks that will need to be managed if the fire escapes. The risk assessment should be organised and in line with the four and seven day weather. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0509 | 36 - Volunteers | The Minister for Emergency Services and the Minister for Environment develop by December 2012 a Volunteer Charter that recognises the important work undertaken by the State’s volunteer bushfire and emergency services personnel. |
REC202-0504 | 15 - Inter-service cooperation | The Minister for Emergency Services ensure that the annual budget of FESA contains the funds it requires to coordinate an annual multi-agency bushfire field exercise, alongside other desktop exercises, to be held in different regions of the State each year. The outcomes of this field exercise should be included in the proposed annual Ministerial statement to Parliament on bushfire readiness before each season. |
REC202-0508 | 36 - Volunteers | The Minister for Emergency Services and the Minister for Local Government review and report to Parliament by May 2012 on ways in which the State’s volunteer firefighters and rescue workers can be more effectively managed and valued. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0260 | 15 - Inter-service cooperation | There are a range of opportunities identified from reviewing the three fires that will improve coordination between FESA and DEC, requiring limited resources, potentially generating some efficiencies and reflecting a joint, tenure blind approach to fire management in WA. The MIR acknowledges the progress made through the IBMC in these matters and notes these measures will require ongoing strong leadership. These include: · Clarification and consistent application of the Zone 2 and 2A mobilisation protocols; · Duplicating available information on websites; · Establishing a single State air desk and cross-utilising Air Attack Supervisors; · Completing common training for the conduct of public meetings;· Coordinating IMT training and exercises; · Operating joint IMT‘s during interface fires; FESA utilising the DEC mobile ICC when suitable ICPs are not available; · FESA engaging in daily weather teleconferences with DEC; Engaging a permanent BoM officer to support a common FESA and DEC SOC; · Developing a common ‗Tool Box‘ of forms and operational procedures for fire response; · Developing common jurisdictional arrangements to accommodate interstate support; · Developing a joint FESA/DEC SOC at the new (FESA) Emergency Services facility at Cockburn; · Adopting common and transparent Level 3 IC accreditation · Using a single mapping capability across both agencies and · Using common naming conventions for fires. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-0350 | 5 - Hazard reduction burns | The State Government consider resourcing the Department of Environment and Conservation and local governments to develop and administer a comprehensive prescribed burning program in Perth’s urban/rural interface to compliment DEC’s existing landscape-scale program. |
REC200-0369 | 18 - Access to fire ground | The Western Australian Police and the Fire and Emergency Services Authority jointly examine the Traffic Management System developed in response to the 2009 Victorian bushfires and seek its adaptation to use in WA with additional attention to the access and egress by bona fide residents to areas that are evacuated. |
REC200-1708 | 15 - Inter-service cooperation | The Fire and Emergency Services Authority and the Western Australian Police ensure they receive all necessary legal clarification in relation to Bushfire Responsibilities of Police Officers – Powers Used in Assisting Fire Authorities in Responding to Bushfires, to be promulgated across FESA and WAPOL. |
REC200-0386 | 15 - Inter-service cooperation | Emergency service agencies undertake more consultation and joint exercising involving the Fire and Emergency Services Authority, the Department of Environment, the Western Australian Police, the Department for Child Protection, local governments and volunteers – including Volunteer Bush Fire Brigades. This should include field exercises which test: Evacuation centres Critical infrastructure (including at the local level) Traffic management, including road blocks. Consideration should also be given to involving the community in exercising (see Recommendation 7) and using prescribed burns as exercises (see Recommendation 14) More detailed planning for exercises should be included in a revised WESTPLANBUSHFIRE to be endorsed by the State Emergency Management Committee. |
REC200-1692 | 5 - Hazard reduction burns | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments take proactive steps to conduct their prescribed burning programs as joint exercises. This will give effect to: |
REC200-1680 | 15 - Inter-service cooperation | Emergency Management Western Australia establish an inter-agency working group to continue the development of the new single emergency services Act. |
REC200-0356 | 5 - Hazard reduction burns | The State Government reaffirm its 2009 decision to approve DEC exercising greater flexibility in managing smoke within national guidelines, in order to achieve its prescribed burn program. |
REC200-1724 | 6 - Insurance and legal liability | Emergency Management Western Australia develop mechanisms to calculate the estimated total cost of a fire to the community. |
REC200-0338 | 15 - Inter-service cooperation | The Fire and Emergency Services Authority and the Department of Environment and Conservation develop and finalise their Memorandum of Understanding and commit to working in partnership. |
REC200-1691 | 5 - Hazard reduction burns | The State Government consider resourcing the Department of Environment and Conservation and local governments to develop and administer a comprehensive prescribed burning program in Perth‟s urban/rural interface to compliment DEC's existing landscape-scale program. |
REC200-1712 | 10 - Infrastructure | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-1679 | 15 - Inter-service cooperation | The Fire and Emergency Services Authority and the Department of Environment and Conservation develop and finalise their Memorandum of Understanding and commit to working in partnership. |
REC200-0351 | 5 - Hazard reduction burns | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments take proactive steps to conduct their prescribed burning programs as joint exercises. This will give effect to: Reducing fuel load Improving inter-operability A mutual understanding of the fire fighting techniques of each agency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0451 | 15 - Inter-service cooperation | the state ensure, as a matter of priority, that the State Control Centre is able to function as a fit for purpose, multi-agency emergency management centre. Necessary works to achieve this outcome should have an overarching focus on the implementation of common agency systems and processes to the fullest extent possible. |
REC199-0422 | 36 - Volunteers | the state establish a process for volunteer community member accreditation to allow volunteers to provide flood information to the control agency during a flood event. This process should establish a base competency standard and provide appropriate emergency management and Australasian Inter-service Incident Management System training to accredited community volunteers. |
REC199-0476 | 6 - Insurance and legal liability | the Department of Planning and Community Development examine strategies to address and clarify insurance coverage of community volunteers in emergency events |
REC199-0460 | 6 - Insurance and legal liability | the state formalise and continue the Emergency Response Legal Advisers Forum. |
Rec-ID | Code | Recommendation |
---|---|---|
REC198-2903 | 15 - Inter-service cooperation | The CFA works with MFB to ensure that the MFB control unit is available for responding to large fires and multi-agency incidents in fringe CFA areas |
Rec-ID | Code | Recommendation |
---|---|---|
REC197-1735 | 36 - Volunteers | A. The CFA continue to explore and develop initiatives with modern information and communication technologies to maximise the benefits that they may bring to volunteer involvement in the CFA. |
REC197-1770 | 36 - Volunteers | The CFA, in consultation with the VFBV and volunteers, review the arrangements for the reimbursement of volunteer expenses. This review could be done in conjunction with the review of possible reimbursement of employers of CFA volunteers as recommended in Recommendation 5. |
REC197-1734 | 36 - Volunteers | A. Consideration be given to the VFBV being funded directly by Government rather than by the CFA. |
REC197-1745 | 36 - Volunteers | The CFA revisit with the UFU the arrangements relating to Community Education Firefighters/Fire Officers and the use of volunteers in this role. |
REC197-1742 | 36 - Volunteers | The CFA, in consultation with the VFBV and volunteers, develop initiatives and strategies that will maximise the involvement of young people as volunteers and their retention as volunteers. |
REC197-1740 | 36 - Volunteers | The CFA, in consultation with the VFBV and volunteers, develop and introduce an arrangement whereby a volunteer can transfer from one brigade to another and still remain a member of the CFA, without the need to resign. |
REC197-1739 | 36 - Volunteers | The CFA, in consultation with the VFBV and volunteers, develop a systemic exit strategy, which ensures that relevant information is captured consistently across all brigades. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0335 | 10 - Infrastructure | Energy Safe Victoria ensures that the standards for vegetation clearance around power lines consider the impact of fire on electrical infrastructure and the risk of loss of electricity supply to the community. |
REC195-0327 | 15 - Inter-service cooperation | The Fire Services Commissioner ensures that the inter-relationship between Information Sections at all levels is understood. |
REC195-0318 | 15 - Inter-service cooperation | The Fire Services develop a joint protocol for each Fire Service to notify the other of fires reported from fire towers |
REC195-0309 | 15 - Inter-service cooperation | The Fire Services, and other emergency management agencies, use the Tostaree fire as a scenario exercise to improve understanding of fast-running fires and enhance interoperability and control strategies |
Rec-ID | Code | Recommendation |
---|---|---|
REC193-0227 | 5 - Hazard reduction burns | Local government councils implement a zoning approach to fuel management as recommended by COAG 2004. |
Rec-ID | Code | Recommendation |
---|---|---|
REC191-0261 | 6 - Insurance and legal liability | that the Minister for Police, Corrective Services and Emergency Services undertake a comprehensive legal review in order to clarify the legal position of RFBs and their members. |
REC191-0268 | 6 - Insurance and legal liability | that the QFRS investigate the possibility of insurance recovery when involved in vehicle retrieval activities at accident sites. |
Rec-ID | Code | Recommendation |
---|---|---|
REC187-2932 | 6 - Insurance and legal liability | That all home contents insurance policies include flood cover. |
REC187-2949 | 6 - Insurance and legal liability | That all home, contents and home unit insurance policies cover the policyholder for storm surge, tsunami and landslide, where the storm surge, tsunami or landslide is the result of another event that is covered under the policy and regardless of whether the insured property directly suffers damage from the underlying insured event. |
REC187-2965 | 6 - Insurance and legal liability | That ASIC conduct a review of the General Insurance Code of Practice three years after the amendments recommended to the Code in this Review are implemented, in order to assess the effectiveness of the Code with a view to determining whether an ASIC Regulatory Guide for claims handling should then be introduced. |
REC187-2921 | 6 - Insurance and legal liability | The Commonwealth Government guarantee the payment of claims by ensuring that, whenever a funding shortfall occurs in the reinsurance facility through claims exceeding the funds held in the facility, the Commonwealth would meet the shortfall and the Commonwealth would seek reimbursement of a portion of the shortfall from the State or Territory government in whose jurisdiction the flood occurred. |
REC187-2937 | 6 - Insurance and legal liability | That flood premium discounts be delivered through a model that requires insurers to retain and price a portion of the risk with the remainder to be ceded to the reinsurance facility at a discounted reinsurance premium. |
REC187-2954 | 6 - Insurance and legal liability | That subsection 35(2) of the Insurance Contracts Act 1984 be amended so that policyholders are not deemed to be clearly informed of a deviation from ‘standard cover’ by simply being provided a copy of the insurance policy or product disclosure statement. |
REC187-2926 | 6 - Insurance and legal liability | That flood premium discounts be provided for home building insurance for eligible homes: |
REC187-2942 | 6 - Insurance and legal liability | That a flood risk reinsurance facility, or reinsurance pool, be established which would have two primary functions: |
REC187-2959 | 6 - Insurance and legal liability | That every APRA-authorised general insurer adopt and comply with the General Insurance Code of Practice. |
REC187-2931 | 6 - Insurance and legal liability | That the definition of a home for the purposes of flood cover and flood premium discounts be any building for which a homeowner purchases a home insurance policy. |
REC187-2948 | 6 - Insurance and legal liability | That: |
REC187-2964 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend the General Insurance Code of Practice such that the General Insurance Code Compliance Committee: |
REC187-2920 | 6 - Insurance and legal liability | That a system of premium discounts be introduced in order that most purchasers of home insurance, home contents and home unit insurance policies in areas subject to flood risk be eligible for discounts against the full cost of flood insurance. |
REC187-2936 | 6 - Insurance and legal liability | That the questions of flood cover as standard in small business policies and access to discounted premiums for small business policyholders should be revisited once the recommended arrangements for homes, home units and home contents are in place. |
REC187-2953 | 6 - Insurance and legal liability | That all home building insurance policies providing sum insured cover be modified by the end of 2014 so as to include replacement value cover in the event of total loss of the home. That during the transition period insurers consider how the design features of home building replacement value policies should respond following a natural disaster, including the conditions under which cash settlements are to be offered and finalised. |
REC187-2925 | 6 - Insurance and legal liability | That the following five principles underpin the design of a system of premium discounts: |
REC187-2941 | 6 - Insurance and legal liability | That homes at high and extreme risk of flood be provided with discounts initially and that they be assessed regularly for mitigation work already undertaken and the potential for further mitigation. |
REC187-2958 | 6 - Insurance and legal liability | That, in order to give general insurance policyholders the same legal remedies as other consumers, unfair contract terms laws be applied to general insurance. |
REC187-2930 | 6 - Insurance and legal liability | That flood premium discounts be provided, in the same manner as for homes, to the bodies corporate of eligible properties, and on the same basis as for detached homes. |
REC187-2947 | 6 - Insurance and legal liability | That the Agency charge insurers a small administrative fee for each policy ceded to the reinsurance facility. |
REC187-2963 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend the General Insurance Code of Practice to require that: |
REC187-2968 | 6 - Insurance and legal liability | That the Government give priority to introducing legislation necessary to ensure that all home, contents and home unit insurance policies include flood cover and to establish a new national agency for flood risk management and flood reinsurance purposes. |
REC187-2919 | 6 - Insurance and legal liability | That all home insurance, home contents and home unit insurance policies include flood cover. |
REC187-2935 | 6 - Insurance and legal liability | That flood premium discounts not be provided to small businesses and that the reinsurance facility not offer reinsurance for small businesses. |
REC187-2952 | 6 - Insurance and legal liability | That lending institutions remind mortgagors annually of their obligations to hold home insurance and of the risks of under-insurance in order to minimise non-insurance and under-insurance of homes. |
REC187-2924 | 6 - Insurance and legal liability | That whenever flood cover is included in home building insurance policies: |
REC187-2940 | 6 - Insurance and legal liability | That for home contents insurance policies, policyholders pay for that portion of the risk retained by the insurer and pay nothing for the remainder of the risk up to $100,000. For contents with a value greater than $100,000 policyholders then pay the full cost of the portion of risk exceeding $100,000. |
REC187-2957 | 6 - Insurance and legal liability | That the Commonwealth Government introduce a standard definition of flood in the form proposed in the ‘Reforming flood insurance: Clearing the waters’ consultation paper. |
REC187-2929 | 6 - Insurance and legal liability | That all home unit insurance policies include flood cover, in the same manner as for homes. |
REC187-2945 | 6 - Insurance and legal liability | That to facilitate flood risk information being made publicly available, Commonwealth, State and Territory governments grant indemnities to the providers of flood risk information if the information is obtained and provided in good faith and in the absence of any gross negligence. |
REC187-2962 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend clause 4.5 of the General Insurance Code of Practice to extend the time within which claimants in natural disasters have the right to make further claims or lodge reviews after the finalisation of an initial claim to seven months from the date of the relevant natural disaster, regardless of when the initial claim was finalised. |
REC187-2934 | 6 - Insurance and legal liability | That all insurers offering small business insurance be obliged to include flood cover on an opt-out basis, instead of an opt-in/opt-out basis as at present, in all of their small business package policies. |
REC187-2951 | 6 - Insurance and legal liability | That access to insurance be enhanced through the development of alternative payment options, in particular: |
REC187-2967 | 6 - Insurance and legal liability | That the current formula for the cost of rebuilding of State and Territory assets under the Natural Disaster Relief and Recovery Arrangements be changed to expenditure before any insurance recoveries by the State or Territory rather than net of any insurance recoveries. |
REC187-2923 | 6 - Insurance and legal liability | That home building and home contents insurance should not be made compulsory. |
REC187-2939 | 6 - Insurance and legal liability | That for body corporate insurance policies receiving full discounts, policyholders pay for that portion of the risk retained by the insurer and pay nothing for the remainder of the risk up to $500,000 times the number of units. For properties with a value greater than $500,000 times the number of units policyholders then pay the full cost of the portion of risk exceeding $500,000 times the number of units. |
REC187-2956 | 6 - Insurance and legal liability | That a ‘health warning’ be provided by insurers to the purchasers of home and contents policies that do not include full flood cover or full replacement cover. The health warning should be provided: |
REC187-2928 | 6 - Insurance and legal liability | That there be limitations on the size of the discount available to high-value homes. |
REC187-2944 | 6 - Insurance and legal liability | That the Commonwealth seek reimbursement of some portion of the shortfall from the State or Territory government in whose jurisdiction the flood occurred. |
REC187-2961 | 6 - Insurance and legal liability | That the Insurance Council of Australia repeal clauses 4.3 and 4.4 of the General Insurance Code of Practice, so that claims arising from natural disasters are subject to the same minimum standards as other claims — including the four month time limit for a determination on liability and the nature of the loss/damage with respect to the claim. |
REC187-2933 | 6 - Insurance and legal liability | That discounts be provided, in the same manner as for homes, to home contents insurance policies for eligible properties. |
REC187-2950 | 6 - Insurance and legal liability | That the Commonwealth engage with the insurance industry and the States and Territories in planning for the future coordination of charitable and government payments to individuals to assist with recovery after future natural disasters. |
REC187-2966 | 6 - Insurance and legal liability | That the Commonwealth and State governments provide funding for legal advice and assistance with insurance disputes following natural disasters. |
REC187-2922 | 6 - Insurance and legal liability | That all home building insurance policies include flood cover. |
REC187-2938 | 6 - Insurance and legal liability | That for home building insurance policies receiving full discounts, policyholders pay for that portion of the risk retained by the insurer and pay nothing for the remainder of the risk up to $500,000. For properties with a value greater than $500,000 policyholders then pay the full cost of the portion of risk exceeding $500,000. |
REC187-2955 | 6 - Insurance and legal liability | That, in endorsing the Government proposal for a Key Facts Statement, the Key Facts Statement list replacement cover and all natural disaster events, identified as ‘standard cover’ in the Insurance Contracts Regulations 1985. That insurers issue a Key Facts Statement to policy holders with all new policies written and all policy renewals on an annual basis. |
REC187-2927 | 6 - Insurance and legal liability | The levels of the discounts and the phasing out periods be reviewed from time to time. |
REC187-2943 | 6 - Insurance and legal liability | That the Commonwealth Government guarantee payment of claims from the reinsurance pool by ensuring that, whenever a funding shortfall occurs in the pool through claims exceeding the funds held in the pool, the Commonwealth would meet the shortfall. |
REC187-2960 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend the Code of Practice to impose a four month time limit (subject to exceptional circumstances) to make a determination as to liability and the nature of the loss or damage with respect to a claim. That, should a claimant not receive a determination within the four month period, the claim be automatically escalated to an internal dispute resolution complaint and the insurer notify the Code Compliance Committee of the breach of the Code. |
Rec-ID | Code | Recommendation |
---|---|---|
REC185-1933 | 6 - Insurance and legal liability | The committee recommends that the Commonwealth Treasury clarify what is meant by the term 'cost-effective' as it relates to the 2011 NDRRA Determination and the scrutiny of the states' and territories' insurance arrangements. |
REC185-1932 | 6 - Insurance and legal liability | The committee recommends that a particular focus of the Natural Disasters Insurance Review into the adequacy of current insurance arrangements should be on whether the international insurance market offers reinsurance for the states' and territories' road networks. |
REC185-1930 | 6 - Insurance and legal liability | The committee recommends that the Commonwealth Government consult with state and territory governments to ensure that the states' and territories' captive insurance and reinsurance arrangements are reported transparently and on a comparable basis. |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0118 | 15 - Inter-service cooperation | A Memorandum of Understanding signed by the Chief Executives of DEC and FESA would be a valuable statement of joint commitment between the two agencies. |
REC183-0117 | 15 - Inter-service cooperation | The Interagency Bushfire Management Committee and its sub-committees are the logical central platform for developing and strengthening future joint bushfire strategies and common systems of work between bushfire management agencies in Western Australia. |
REC183-0116 | 15 - Inter-service cooperation | Triggers and a process for transfer of command and control from DEC to FESA should be developed and documented. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0125 | 15 - Inter-service cooperation | FESA, in partnership with other agencies and the community, develops Western Australia’s urban interface fire fighting capability and capacity. |
REC182-0124 | 15 - Inter-service cooperation | FESA and DEC take a whole of capability approach to joint operations, including developing joint doctrine that provides a common and articulated understanding of roles and responsibilities, resources and capabilities |
REC182-0129 | 15 - Inter-service cooperation | FESA maintains inter-agency relationships and arrangements, and develops formalised arrangements across the entire emergency management cycle for joint activities such as training, exercises and procedure development. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
REC181-0172 | 15 - Inter-service cooperation | The Country Fire Authority and the Department of Sustainability and Environment standardise their operating systems and information and communications technologies with the aim of achieving greater efficiency and interoperability between agencies. |
REC181-0169 | 18 - Access to fire ground | The Country Fire Authority provide to all CFA volunteers an identification card or similar to facilitate their passage through roadblocks established in accordance with the 2009 Guidelines for the Operation of Traffic Management Points during Wildfires. |
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
REC181-0207 | 5 - Hazard reduction burns | The Department of Sustainability and Environment report annually on prescribed burning outcomes in a manner that meets public accountability objectives, including publishing details of targets, area burnt, funds expended on the program, and impacts on biodiversity. |
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
REC181-0206 | 5 - Hazard reduction burns | The State fund and commit to implementing a long-term program of prescribed burning based on an annual rolling target of 5 per cent minimum of public land. |
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3369 | 6 - Insurance and legal liability | The obligation of companies involved in an incident to meet the full costs of monitoring and remediation should be made a condition of approval of proposals under the EPBC Act and OPGGS Act. Suitable arrangements (insurance or otherwise) need to be in place to ensure that companies have this capacity. |
REC177-3365 | 6 - Insurance and legal liability | The National Plan should specify that the cost of responding to an oil spill, or other damage to the offshore marine environment, will be totally met by the owner/operator. This would be consistent with the Inquiry’s recommendation for legislative changes to the regulatory framework concerning owner/operators meeting the cost of monitoring and remediation of environmental damage. |
REC177-3310 | 6 - Insurance and legal liability | Consideration should be given to ways to ensure that contractors who are involved in barrier installation (such as cementing companies) have a direct interest in the performance of works to a proper standard. In particular, consideration should be given to (i) preventing contractors from avoiding the economic consequences of negligent installation of barriers; and/or (ii) imposing specific legislative standards of workmanship on contractors with respect to well control (similar to those which presently apply to licensees). |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0147 | 5 - Hazard reduction burns | The Commonwealth encourages further research into prescribed burning and its effectiveness and into alternative bushfire mitigation approaches through improved bushfire risk understanding at the asset level. |
REC176-0138 | 10 - Infrastructure | The Productivity Commission undertake an examination of bushfire risk from ageing power infrastructure, including an assessment of replacement costs and likely suppression costs from bushfires caused by defective infrastructure. |
REC176-0139 | 10 - Infrastructure | Subject to the findings of the Productivity Commission, the Commonwealth examine options for the funding of replacement of power infrastructure that presents an unacceptable bushfire risk. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0012 | 18 - Access to fire ground | Main Roads Western Australia, Police and LGA’s be encouraged via State emergency arrangements to establish a distributed cache of “hard” road barriers for deployment to major incidents |
REC172-0039 | 18 - Access to fire ground | Dedicated information packages should be made available to personnel operating Vehicle Control Points at the shift briefing. |
REC172-0011 | 18 - Access to fire ground | At Level 3 incidents the position of ‘Traffic Operations Officer’ –be established and filled by a WAPOL officer. A role description for this position is required and should be included in the “Guidelines for the Operations of Road Closures During Bushfires 2008”. This officer is to be supported by a suitably qualified officer from MRWA that is capable of developing Traffic Management Plans that address risk and are cognisant of considerations associated with road type, appropriate speed limitations, signage requirements, traffic volumes, detours for local traffic and heavy haulage etc. This role should report to the IC and have strong links to the Operations Section, Planning Section (particularly the Situation Unit) and the Information Unit. |
REC172-0017 | 18 - Access to fire ground | Information packs to be provided to road traffic personnel to assist with enquiries by public or provision to members of public and landholders who are defending homes/stock etc |
REC172-0016 | 18 - Access to fire ground | Full briefings of traffic management personnel should be provided prior to dispatch to work areas – why road closed, what their authority level is, level of current risk etc |
REC172-0022 | 15 - Inter-service cooperation | The declaration of a potential Level 3 incident should be notified to FESA who can facilitate an early warning to CFCO’s in the Shire and surrounding LGA’s. |
REC172-0014 | 18 - Access to fire ground | The Interagency Guidelines for Road closure needs to be reviewed to incorporate a mechanism to identify bone-fide local landholders to facilitate their movement in and out of cordoned areas in sympathy with the Stay and Defend requirements. |
REC172-0013 | 18 - Access to fire ground | In preparing traffic management plans consideration should be given to which VCP’s are critical and need to be resourced with uniformed Police Officers and which VCP’s can be manned with civilian contractors. |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0059 | 15 - Inter-service cooperation | SEMC and EM WA should: ensure all agencies use the same approach to managing incidents. |
REC170-0058 | 15 - Inter-service cooperation | SEMC and EM WA should: ensure that all agencies can access other agencies’ operations centres when needed and that the procedures to do so are documented |
Rec-ID | Code | Recommendation |
---|---|---|
REC166-3007 | 15 - Inter-service cooperation | That Tasmania Fire Service implement Recommendation 5 above; and that Aurora continue to co-operate with that Service. |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0096 | 15 - Inter-service cooperation | The Department of Community Safety and Councils develop MOUs to reflect the genuine partnership that exists in present arrangements including an emphasis on the use of the agreed State disaster arrangements to task and deploy SES units following State/Local consultation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3446 | 15 - Inter-service cooperation | That emergency services are required to work directly with port/channel managers and the nominated marine safety authority to identify and ensure availability of marine resources necessary for emergency services to meet their statutory obligations in responding to marine emergencies (this recommendation should be read in conjunction with recommendation 26 & 27). |
REC158-3445 | 15 - Inter-service cooperation | That emergency services are required to work directly with ports and the nominated marine safety authority when ports are preparing marine emergency response arrangements. |
REC158-3444 | 15 - Inter-service cooperation | That the Office of the Emergency Services Commissioner ensures that an emergency services multi-agency working group is established to develop a specialist marine emergency response capability for Victoria based on the multi-agency Urban Search and Rescue (USAR) model. The specialist personnel should be required to have: |
REC158-3447 | 15 - Inter-service cooperation | That emergency services are required to work directly with port/channel managers and the nominated marine safety authority to ensure that a training and exercise regime is established to enable emergency services personnel to develop and maintain the skills and knowledge relevant to marine emergency management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
REC156-3485 | 15 - Inter-service cooperation | The integrated Emergency Coordination Centre be utilised during all significant multi-agency or multi-incident events with effective liaison with the State Emergency Response Coordinator. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3481 | 6 - Insurance and legal liability | That the Victorian Government establish a clear and consistent Bushfire Fencing Policy for damage caused by all future bushfires and prescribed burns. The Bushfire Fencing Policy should include the following provisions: |
REC155-3465 | 5 - Hazard reduction burns | That in order to enhance the protection of community and ecological assets, the Department of Sustainability and Environment increase its annual prescribed burning target from 130,000 hectares to 385,000 hectares. This should be treated as a rolling target, with any shortfalls to be made up in subsequent years. |
REC155-3471 | 6 - Insurance and legal liability | That the Victorian Government replace or compensate for water taken from domestic, stock and irrigation dams, or water needed for essential use, in the event of a fire, regardless of where the bushfire starts. |
REC155-3464 | 5 - Hazard reduction burns | That the Department of Sustainability and Environment implement remote sensing imagery as a routine part of its pre-burn and post-burn assessment process for prescribed burning. Maps of every prescribed burn should be produced in a similar format to those used in Western Australia, indicating the boundary of each burn and the varying fire intensities achieved within the burn area. The boundaries of all Fuel Management Zones within each burn should also be indicated. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1777 | 5 - Hazard reduction burns | That the Minister for Emergency Services and the Minister for Local Government consider the enactment of legislation that would empower Local Government to require the owners or occupiers of rural land to create fire breaks on the land of a kind that Local Government may determine and/or to require the removal of flammable materials from the land, as measures for preventing the outbreak of a bushfire, or for preventing the spread or extension of a bushfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC152-3401 | 15 - Inter-service cooperation | The streamlining correspondence to Emergency Service Agencies |
Rec-ID | Code | Recommendation |
---|---|---|
REC151-3109 | 36 - Volunteers | As a matter of priority, SAFECOM examine what further measures can be taken to provide support and protection for volunteers as potential witnesses in public enquiries. |
REC151-3108 | 36 - Volunteers | Liability and immunity as these provisions apply in Section 127 be reassessed in terms of burden of proof so as to ensure the best protection for volunteers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3212 | 6 - Insurance and legal liability | The Committee recommends that the Australian Government request the Productivity Commission to undertake an inquiry into the projected impacts of climate change and related insurance matters, with a particular focus on: |
Rec-ID | Code | Recommendation |
---|---|---|
REC144-3395 | 15 - Inter-service cooperation | The Committee recommends that the ACT Emergency Services and the Rural Fire Service in particular institute regular meetings with the NSW Rural Fire Service and other appropriate authorities, such as environment |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3558 | 6 - Insurance and legal liability | DHHS need to confirm adequate accident insurance coverage for staff working in retrieval medicine. Coverage specific to helicopter and fixed wing duties is required. |
Rec-ID | Code | Recommendation |
---|---|---|
REC132-3597 | 15 - Inter-service cooperation | Investigate engaging with other agencies involved in emergency management including SES, VicRoads, VicPolice, OESC and DHS to establish a single united emergency information line for Victoria that can be used to provide information to the public from all agencies involved. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1972 | 5 - Hazard reduction burns | That clarification be provided and information be made public in connection with the hazard reduction proposed under the Strategic Bushfire Management Plan for the area designated ‘Land Management Zone’, which appears to cover about 70 per cent of the ACT landscape and might be excluded from fuel-reduction burning |
REC126-1971 | 5 - Hazard reduction burns | That a hazard-reduction program be introduced, involving regular and strategic burning in all areas of the ACT – including the catchment areas – with a view to having fuel-reduced areas in a pattern across the landscape, excluding only small areas of particular ecological or conservation importance |
REC126-1981 | 15 - Inter-service cooperation | That senior officers in the Australian Federal Police and the Emergency Services Agency maintain regular and meaningful contact during fire emergencies, to ensure full dissemination of information and thus facilitate the making of good operational decisions |
REC126-1956 | 15 - Inter-service cooperation | That courses and programs be conducted to increase the level of Incident Control System training and augment the expertise of people who are likely to perform functions in an incident management team |
REC126-1975 | 5 - Hazard reduction burns | That prescribed burning operations be conducted according to agreed standard burning prescriptions |
REC126-1954 | 15 - Inter-service cooperation | That senior officers of the Emergency Services Agency give greater recognition to the skills, knowledge and experience of people from other agencies – particularly the land management agencies – as well as rural residents and private individuals and use these people in roles commensurate with their skills and experience |
REC126-1973 | 5 - Hazard reduction burns | If it is not part of the proposed version 2 of the Strategic Bushfire Management Plan, that the plan be revised to provide for a fuel-reduction burning regime in the ‘Land Management Zone’ that is equivalent to that contemplated for the corridors designated as the ‘Landscape Division Zone’ and that the regime involve burning areas in rotation to achieve an appropriately varying fire age spectrum across the entire landscape |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3891 | 15 - Inter-service cooperation | That Melbourne Water and councils explore opportunities for working collaboratively to address the management of flooding risks with a view to optimising the efficient and effective use of their flood mitigation resources. |
Rec-ID | Code | Recommendation |
---|---|---|
REC124-3885 | 5 - Hazard reduction burns | Align policies and processes, within the year round 365 day focus on fire management, to provide consistency in the approach to fire regardless of its origins,- that is fuel reduction burning, regeneration and ecological burning or unplanned fire; |
REC124-3884 | 5 - Hazard reduction burns | Develop new prescriptions for prescribed burning to accommodate local conditions in those areas where standard prescriptions are assessed to be inappropriate: |
REC124-3889 | 15 - Inter-service cooperation | Develop a component of the DSE Workforce Strategy to build organisational capacity and sustainability of the prescribed burning program across the networked emergency organisation: |
REC124-3883 | 15 - Inter-service cooperation | Integrate information management systems relating to the prescribed burning program to provide consistency across the networked emergency organisation: |
Rec-ID | Code | Recommendation |
---|---|---|
REC123-3876 | 15 - Inter-service cooperation | Metropolitan Fire Brigade and Aviation Rescue Fire Fighting service review and enhance the existing mutual response Memorandum of Agreement to provide more timely notification and therefore immediate access to appropriate resources to respond to emergencies. |
REC123-3875 | 15 - Inter-service cooperation | Melbourne Airport Emergency Planning Committee review the Airport Emergency Plan to ensure the capabilities of agencies are adequately documented and understood by all stakeholders, and that all agencies including airlines are represented at the appropriate organisational level on the Airport Emergency Planning Committee. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3703 | 6 - Insurance and legal liability | Alcohol and drug testing should be mandatory for any train driver or guard involved in any accident or incident. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC117-3635 | 15 - Inter-service cooperation | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter-Terrorism Committee, seek to create systematic mechanisms for better targeting and evaluating inter- agency coordination within the National Capability Development Exercise Programme and continuous improvement cycle. |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2107 | 10 - Infrastructure | The Working Group recommends that State/Territory emergency management plans should explicitly take the need for rapid assessment of damaged physical infrastructure into account. The importance of rapid physical infrastructure assessment in ensuring the supply of utilities including sewerage and drainage, electricity, water and gas to residential structures and other types should be recognised and considered. |
REC116-2119 | 6 - Insurance and legal liability | The Working Group recommends that the National Recovery Coordinators Group approach the Investment and Financial Services Association Limited, with a view to identifying the most appropriate way of engaging the life insurance industry in the recovery process. |
REC116-2098 | 15 - Inter-service cooperation | The Working Group recommends that Emergency Management Australia (EMA) facilitate national discussions into the capability of States/Territories to ensure thorough collaborative systems and plans for inter-jurisdictional resource interoperability exist, and where this has not already occurred at State/Territory level and appropriate agencies, committees or government departments can be identified, they should be tasked with progressing specific issues in the following areas: |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3906 | 10 - Infrastructure | Firefighting organisations should: resolve existing telecommunication problems and work with other emergency service organisations to establish compatible telecommunications systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3933 | 15 - Inter-service cooperation | That DPI formalises agreements between divisions and groups that allow staff to be involved in incursion responses and reflects this requirement in individual duty statements. |
REC112-3920 | 15 - Inter-service cooperation | That better use be made of Primary Industries Research Victoria's (PIRVIC) facilities by strengthening links with relevant groups of expertise, such as the Forest Science Centre. |
REC112-3927 | 6 - Insurance and legal liability | That PSB and PIRVIC review their service agreement to ensure that PIRVIC is compensated for its costs in providing PSB with the specified level of service. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2283 | 15 - Inter-service cooperation | That DSE, CFA, MFESB and VICSES work cooperatively to establish a common system for resource tracking during major fires and incidents. |
REC104-2231 | 6 - Insurance and legal liability | That DSE commences discussion with the Victorian WorkCover Authority in respect to employer liability for those staff being released to, and directed, by another agency in fire prevention and suppression activities. |
REC104-2328 | 36 - Volunteers | That CFA, VICSES and other volunteer-based emergency service organisations develop proposals in support of the strategies for sustainable volunteerism, and that the State Government advocate these initiatives to the Federal Government. |
REC104-2266 | 15 - Inter-service cooperation | That DSE and CFA review their joint planning for Incident Control Centres to ensure that, wherever safe and practicable, those Centres are located close to the fire area. |
REC104-2336 | 15 - Inter-service cooperation | That OESC work with the fire agencies in developing implementation strategies for recommendations agreed by Government. |
REC104-2218 | 6 - Insurance and legal liability | That Government work with the insurance industry to explore options for incentives such as a reduction in premiums for those who take appropriate self-protection measures on their properties, similar to incentives for anti-theft home security |
REC104-2265 | 15 - Inter-service cooperation | That in the review of Incident Control Centre locations, DSE and CFA give due consideration to: |
REC104-2323 | 15 - Inter-service cooperation | That CFA, DSE, MFESB, VICSES, Victoria Police and OESC, in consultation with the Municipal Association of Victoria, consult on the proposal to combine Municipal Councils’ current responsibilities for the development of an emergency management plan/committee, as required by the Emergency Management Act 1986 and a fire prevention plan/committee as required by the Country Fire Authority Act 1958. |
REC104-2217 | 6 - Insurance and legal liability | That CFA, in their education and information packages, encourage appropriate insurance cover, and ensure that insurance becomes a part of the householder’s annual checklist. |
REC104-2223 | 10 - Infrastructure | That Government review legislation for utilities operating within the State to ensure their involvement in regional fire preparedness and mitigation planning. |
REC104-2238 | 15 - Inter-service cooperation | That the Victorian fire agencies negotiate with their counterparts in New South Wales and South Australia to put in place agreements for mutual aid and the development of cross border strategy for the management of fires burning in the vicinity of, or across, State borders, and these agreements are reviewed annually. |
REC104-2322 | 15 - Inter-service cooperation | That DSE commits appropriate resources to work with OESC in developing the bushfire component of the model. |
REC104-2295 | 15 - Inter-service cooperation | That more emphasis should be given to communication and discussion in regard to State Aircraft Unit’s roles, responsibilities, practices and procedures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2172 | 6 - Insurance and legal liability | The Committee recommends that taxes on insurance premiums be calculated only on the premium in order to eliminate the current cascading cost. |
REC098-2138 | 10 - Infrastructure | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments resolve to increase water access points for bushfire fighting on public land to the minimum national standard. |
REC098-2157 | 6 - Insurance and legal liability | The Committee recommends that the Commonwealth Government work with Australasian Fire Authorities Council to review the insurance cover provided to volunteer fire fighters in all states and territories and ensure that cover is adequate for loss of life or injury and related loss of income and property lost in the line of duty. |
REC098-2173 | 36 - Volunteers | The Committee suggests that registered volunteer fire fighters be exempt from paying Fire Levy tax to help offset some of the expense they incur during active duty. The exemption could be for a period of 12 months |
REC098-2142 | 5 - Hazard reduction burns | The Committee recommends that the Commonwealth seek to ensure that the Council of Australian Governments seek agreement from the states and territories on the optimisation and implementation of prescribed burning targets and programs to a degree that is recognised as adequate for the protection of life, property and the environment. The prescribed burning programs should include strategic evaluation of fuel management at the regional level and the results of annual fuel management in each state should be publicly reported and audited. |
REC098-2156 | 36 - Volunteers | The Committee recommends that: |
REC098-2183 | 6 - Insurance and legal liability | Further to recommendation 21 in Chapter 4, the Committee recommends that the Commonwealth seeks to ensure that the proposed Council of Australian Governments review of the bushfire management, initiate |
REC098-2167 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority, in conjunction with the respective state and territory governments, ensure the survivability of essential communication installations during fire incidents by strategic fuel management around the assets. |
REC098-2175 | 6 - Insurance and legal liability | The Committee recommends that insurance companies ensure that potential and existing policyholders are aware of the need to regularly review their insurance policies to prevent undervaluing. This could be done through renewal notices and quarterly reminders. This should include a list of bushfire risk reduction measures that policyholders can implement to decrease the cost of their premium. |
REC098-2163 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority jointly with the Australasian Fire Authorities Council: |
Rec-ID | Code | Recommendation |
---|---|---|
REC061-3248 | 15 - Inter-service cooperation | The Committee recommends to the Minister for Police and Emergency Services that a joint communications and dispatch facility be established under the Minister's control to implement the following minimum services to the Victoria Police and the emergency services: |
REC061-3413 | 15 - Inter-service cooperation | The Committee recommends to the Minister for Police and Emergency Services that a joint communications and dispatch facility be established under the Minister's control to implement the following minimum services to the Victoria Police and the emergency services: |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4149 | 10 - Infrastructure | A sub-committee of telecommunication officers and representatives of the Bush Fires Board be appointed to investigate and encourage the development of a modern system of radio equipment for bush fire brigades. |
REC019-4146 | 6 - Insurance and legal liability | Insurance companies be asked to subsidise the bush fire equipment fund by an amount at least equal to the amount they at present remit on premiums received for fire insurance in approved districts and that the Government contribute an amount to the fund at least equal to that contributed by the Insurance Companies. |
REC019-4152 | 5 - Hazard reduction burns | The Forests Department make every endeavour to improve and extend the practice of control burning to ensure that the forests receive the maximum protection practicable consistent with silvicultural requirements. |
REC019-4157 | 18 - Access to fire ground | Local authorities and if necessary the Minister take active steps to enforce the removal of fire hazards from the vicinity of buildings in rural areas and that special attention be given to the removal of dead trees on the edges of pasture land and on firebreaks in timbered country. |
REC019-4148 | 10 - Infrastructure | The Commonwealth Government be asked to complete as far as practicable, the connection of telephones to outlying country centres before the end of 1961. |
REC019-4143 | 5 - Hazard reduction burns | It be made clear to all fire control officers that the conditions for burning prescribed in the Bush Fires Act are minimal only, and that it is their duty to prescribe such further conditions as will ensure that should unfavourable weather conditions un-expectedly develop a situation would not arise which the local bush fire control organisation could not reasonably be expected to handle. |
REC019-4142 | 5 - Hazard reduction burns | Landowners desiring to carry out developmental burns be required to inform the local authority sufficiently early to enable that body to direct them or request the local bush fire brigade to carry out protective burning around the area before the prohibited season starts. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |
REC016_3953 | 15 - Inter-service cooperation | It is therefore recommended that the State Electricity Commission should be advised by someone whose profession it is to consider and devise methods of forest fire protection and suppression; that he should collaborate with others to devise a general scheme of organized protection of the undertaking and township of Yallourn; and that above all, he should have direct access to the Commissioners themselves, lest his advice should lose something of its strength and reality in its journey through the “proper channels” of the Commission’s organization. |
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3947 | 15 - Inter-service cooperation | It is recommended that the services of this body [Air Raids Precautions Body] be used in future if to do so be thought desirable. |
Rec-ID | Code | Recommendation |
---|---|---|
REC013_3980 | 6 - Insurance and legal liability | To provide that any person desirous of insuring his crops against fire shall first submit his proposal to two responsible persons for their endorsement that, in their opinion, the crop is likely to produce the value for which the insurer proposes to take out the oolicy, and that, in the event of such endorsement not being obtained, the risk be not accepted. |
REC013_3975 | 5 - Hazard reduction burns | To burn, where necessary, at least 33 feet where there is a risk of fire, on the outside of the railway fence, in conjunction with the railway employees. |
REC013_3969 | 6 - Insurance and legal liability | The subsidy of such Fire Brigade organisations by the insurance companies and the Government to be given favourable consideration, from a proportion of which the expenses of the Central Administration might be met. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |