REC325-4321 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General of Emergency Management recommends this report be returned to the Office of the Inspector-General of Emergency Management to monitor, evaluate, and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4290 | 20 - Role of police | That the NSW Government embed into its emergency plans the appointment of a senior police officer with combat experience to lead recovery efforts following natural disasters. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4219 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends should a Queensland Government Action Plan be considered, clarity about the intent of the recommendations be sought from the Inspector-General Emergency Management to assist in informing this process. |
REC322-4220 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services and the Department of Environment and Science monitor the progress of relevant improvement activities resulting from the K’gari (Fraser Island) Bushfire Review, through their respective lessons management programs. |
REC322-4240 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends the next review of the Queensland State Disaster Management Plan examines and provides guidance in respect to the application of Queensland’s disaster management arrangements to support hazard specific events such as bushfire. |
REC322-4223 | 5 - Hazard reduction burns | The Inspector-General Emergency Management recommends the Department of Environment and Science implements the proposed treatments for fire identified in the Queensland Parks and Wildlife Service K’gari Compliance Strategy. |
REC322-4243 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science identify opportunities to increase Queensland Parks and Wildlife Service’s capability in incident management and multi-agency fire response, through exercising plans and procedures in collaboration with other stakeholders, including disaster and fire management groups at all levels. |
REC322-4246 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends the Interagency Protocol for Fire Management be reviewed by all relevant entities, including representatives of the Butchulla people, and be updated as a matter of priority. Entities responsible for the protocol should implement a process for regular review and evaluation of its effectiveness. This review process should be conducted after a major bushfire event, or to reflect any material change to applicable legislation and policy. It should also consider pre-arranged approvals and a range of agreed fiscal protocols between the agencies. |
REC322-4248 | 5 - Hazard reduction burns | The Inspector-General Emergency Management recommends the prescribed burn program for K’gari be developed by the Department of Environment and Science, in collaboration with the Locality Specific Fire Management Group and the Butchulla people, based on the principles of the National Position on Prescribed Burning. This program should incorporate a process for monitoring and evaluation of outcomes and integration of evolving fire management practices. |
REC322-4245 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science establish pre-determined financial delegations and authority for Queensland Parks and Wildlife Service Incident Controllers. |
REC322-4235 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science review the resourcing model to ensure surge capacity is available to support incident management functions during response operations. This includes processes to request assistance from other departments and entities with responsibilities for fire and incident management. |
REC322-4252 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services regularly review and evaluate the effectiveness of the Queensland Bushfire Plan with land managers and stakeholders, including disaster management groups. A review should occur in line with any material change to the Queensland State Disaster Management Plan, the Disaster Management Act 2003, the Prevention Preparedness Response and Recovery Guideline, or after major bushfire events, to ensure appropriate alignment and currency. |
REC322-4218 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends this report be returned to the IGEM to monitor, evaluate and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4201 | 10 - Infrastructure | We recommend that DELWP improves the Powerline Bushfire Safety Program's transparency by publicly reporting on activities, costs and risk-reduction outcomes. |
REC321-4217 | 5 - Hazard reduction burns | We recommend that DELWP in partnership with Country Fire Authority and Fire Rescue Victoria develops, implements and publicly reports on a holistic suite of performance metrics to demonstrate: - the impact that planned burning has on public and private land on bushfire risk - the impact that planned burning has on public and private land on ecosystem resilience - the impact that non-burn fuel management activities have on public and private land on bushfire risk - the impact that its activities at local and regional levels have on bushfire risk - the cost-effectiveness of its fuel management activities on public and private land. |
REC321-4202 | 10 - Infrastructure | We recommend that DELWP investigates incentives and advises government on options to accelerate burying and insulating the remaining high-voltage bare-wire powerlines in the 33 highest risk areas. |
REC321-4207 | 25 - Inquiry, audit, lessons management and after action review | We recommend that DELWP reviews its target for the number of fuel hazard assessments conducted and ensures that this measure is evidence based, accurately reflects regional performance, and that the department monitors and reports on each region’s performance against it. |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4182 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in partnership with agencies engaged in state, regional and incident control centres: |
REC318-4181 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in collaboration with the emergency management sector and as part of the emergency management planning reforms: |
REC318-4178 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – in collaboration with the Country Fire Authority and local government – undertake a review of the current residual risk target to ensure that it remains contemporary in terms of its designated percentage value. The review should: |
REC318-4171 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that the State review (and where necessary amend) legislation including but not limited to the Country Fire Authority Act 1958, Forest Act 1958 and Local Government Act 2020 to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4083 | 10 - Infrastructure | The Australian Government should work with state and territory governments and critical infrastructure operators to improve information flows during and in response to natural disasters: |
REC317-4082 | 10 - Infrastructure | The Australian Government, working with state and territory governments and critical infrastructure operators, should lead a process to: |
REC317-4070 | 10 - Infrastructure | Australian, state and territory governments should expedite the delivery of a Public Safety Mobile Broadband capability. |
REC317-4102 | 25 - Inquiry, audit, lessons management and after action review | Australian, state and territory governments should review Australian Medical Assistance Team capabilities and procedures and develop necessary training, exercising and other arrangements to build capacity for domestic deployments. |
REC317-4086 | 22 - Role of local Gvt | State and territory governments should review their arrangements for sharing resources between their local governments during natural disasters, including whether those arrangements: |
REC317-4074 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government should review the content of the Defence Assistance to the Civil Community manual to ensure consistency of language and application with a revised COMDISPLAN. |
REC317-4085 | 22 - Role of local Gvt | State and territory governments should take responsibility for the capability and capacity of local governments to which they have delegated their responsibilities in preparing for, responding to, and recovering from natural disasters, to ensure local governments are able to effectively discharge the responsibilities devolved to them. |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4038 | 25 - Inquiry, audit, lessons management and after action review | The CCIP be reviewed in conjunction with the review of the Emergency Plan and the two synchronised. A workable approach to delivering operational emergency communications and strategic WhoG communications is developed with simple and clear reporting arrangements. |
REC316-4033 | 25 - Inquiry, audit, lessons management and after action review | The BFC Terms of Reference be reviewed to ensure they are contemporary and reflect learnings from this and recent bushfire seasons. |
REC316-4018 | 25 - Inquiry, audit, lessons management and after action review | The five year review of the Emergencies Act examine amendments to better define the rationale for a State of Alert / State of Emergency whilst ensuring that the relevant Minister / Chief Minister still has sufficient discretion to make a declaration based on advice from relevant Government officials and committees. |
REC316-4014 | 25 - Inquiry, audit, lessons management and after action review | That Justice and Community Safety Directorate (JACS) lead a working group from across relevant organisations to undertake the five year review of the Emergencies Act in conjunction with a wholistic review of the Emergency Plan and relevant sub-plans; and recommendations from this review, to the extent they are accepted by Government. Bringing together a small Taskforce of staff from across government for a set period would assist the working group in delivering the work needed to address these and other recommendations. |
REC316-4042 | 25 - Inquiry, audit, lessons management and after action review | ACT Government undertake a detailed legislative review to ensure that information regarding vulnerable community members can be appropriately accessed, provided and used during an emergency event. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3851 | 10 - Infrastructure | That, to ensure mobile generators are sourced and distributed on a priority basis during natural disasters, the EUSFAC work with the NSW Telco Authority, relevant NSW government agencies and commercial stakeholders to develop a mobile asset deployment strategy. The strategy should reduce duplication in purchasing, maintaining and housing mobile generators and improve agility in deployment. |
REC315-3817 | 5 - Hazard reduction burns | That Government, noting that hazard reduction targeted in proximity to assets is on balance more likely to provide help than hinder, should: |
REC315-3812 | 25 - Inquiry, audit, lessons management and after action review | That Government commit to: |
REC315-3808 | 22 - Role of local Gvt | That, in order to strengthen the capability of local councils in future emergency events: |
REC315-3827 | 10 - Infrastructure | That, in order to minimise communication outages and extend basic communication coverage during bush fires, the NSW Government work directly, or together with other Australian governments and/or their relevant power and telecommunications regulatory, policy and market bodies, to: |
REC315-3816 | 5 - Hazard reduction burns | That Government re-commit to the current, regionally based approach to planning and coordinating hazard reduction activities across all tenures through Bush Fire Management Committees but ensure that it is actually being implemented at a high-level of quality across NSW. Getting it to a high-level of quality requires: |
REC315-3798 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure recommendations accepted by the Government are implemented in a timely and transparent manner, Government establish a central accountability mechanism to track implementation of recommendations from bush fire-related reviews and inquiries and consider expanding this to other policy areas. |
REC315-3873 | 25 - Inquiry, audit, lessons management and after action review | That Resilience NSW review existing functional area arrangements to ensure they are closely aligned to agencies responsible for direct service delivery. |
REC315-3826 | 10 - Infrastructure | That, in order to maximise the protection of critical infrastructure in a bush fire, Australian governments revise the regulatory framework for the provision to government authorities of information about all critical infrastructure (public and private) including a possible change to compel the owners of critical assets to provide all needed metadata, updated annually, for appropriate planning, preparation and response for bush fire. This would include information about location, ownership, access, details of service the infrastructure supports, and fire treatments of building and surrounding zones. |
REC315-3860 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure the guiding principles and approval processes are contemporary, streamlined and more flexible, the NSW and Commonwealth Governments review the Defence Assistance to the Civil Community (DACC) arrangements. This review should include the circumstances in which the State can request Commonwealth assistance, and the level of information provided by the ADF to the State on available resources and capabilities. |
REC315-3859 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure State Emergency Operations Centre (SEOC) interoperability during all natural disasters, Resilience NSW review the current SEOC arrangements and location including responsibilities for ongoing resourcing and maintenance. |
REC315-3856 | 10 - Infrastructure | That, in order to improve response times to Triple Zero calls, the NSW RFS implements the integrated dispatch system before the 2020-21 fire season commences. |
REC315-3858 | 25 - Inquiry, audit, lessons management and after action review | That, in order to improve cross-agency communication and coordination during bush fires, the NSW RFS review Fire Control Centres (FCCs) in areas that were heavily affected by fire. The results should be combined with the Emergency Operations Centre (EOC) Facilities Review to identify areas that would benefit from a purpose-built FCC, enabling co-location with the EOC. |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
REC314-3266 | 14 - Incident Mgt Teams | Engage with the Australian Defence Force (ADF) once or twice a year to understand the capabilities that could potentially be deployed. Educate IMTs about how to deploy ADF assistance effectively and develop a streamlined ‘call out’ procedure. |
REC314-3265 | 14 - Incident Mgt Teams | Prepare to ‘scale up’ capability during major bushfire events with senior representatives (including BoM staff) in the SEC 24/7, ensure adequate facilities for IMTs, base camps (e.g. Humanihuts) and recovery centres. Consider the resource implications of providing firefighters to interstate operations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC313-2508 | 25 - Inquiry, audit, lessons management and after action review | Regularly reviewing these plans to ensure that they reflect the current operating environment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2505 | 25 - Inquiry, audit, lessons management and after action review | This report be returned to the InspectorGeneral Emergency Management to monitor, evaluate and report on progress and implementation of the recommendation(s) that are accepted in whole or in part by government. |
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2504 | 25 - Inquiry, audit, lessons management and after action review | To enable entities in the sector to proactively work to achieve better results for the community, the recommendations and lessons of this review should be evaluated through the lessons management processes of entities involved in dam safety for their value and relevance. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
REC311-2494 | 22 - Role of local Gvt | To increase shared understanding of risks, enable coordinated plans and collaboratively engage with downstream community members, residents listed within a dam EAP be identified by the Local Government Area (LGA) they reside in. |
Rec-ID | Code | Recommendation |
---|---|---|
REC310-2481 | 22 - Role of local Gvt | Greater clarity about responsibilities for recovery at the community, local, and district levels should be considered in any future review of the Disaster Management Act (2003). |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2480 | 22 - Role of local Gvt | Councils should formalise arrangements with entities that have the skills, capability and capacity to effectively manage spontaneous volunteers. These should be documented and integrated into planning and exercising. |
REC309-2473 | 22 - Role of local Gvt | Councils, with the support of stakeholders, continue to develop and promote local disaster dashboards as the ‘point of truth’ for community information and messaging during disaster events. Greater use during recovery should be considered. |
REC309-2478 | 25 - Inquiry, audit, lessons management and after action review | The progress of recovery for this event be reviewed incrementally over the next 2 to 3 years, with a formal, independent report provided on the effectiveness of the recovery after 3 years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2456 | 22 - Role of local Gvt | A Local Government Association of Queensland representative should be included on the Crisis Communications Network to enhance the delivery of consistent information across and between levels of government. |
REC308-2449 | 25 - Inquiry, audit, lessons management and after action review | Queensland should implement and maintain a system-wide lesson management program. |
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
REC308-2459 | 14 - Incident Mgt Teams | Significant effort should be invested to provide disaster decision-makers at every level with a shared understanding of risks, the situation, and capability, so that they can agree on the best decisions for the communities they serve. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2446 | 14 - Incident Mgt Teams | Coordinated arrangements for liaison officer deployment should be considered and documented by disaster management groups across the full spectrum of risk identified for their area of responsibility, and not rely on a singular inflexible approach. |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2424 | 22 - Role of local Gvt | We recommend that the four councils develop floodplain management plans in accordance with Recommendation 2.12 of the Final Report of the Queensland Floods Commission of Inquiry. |
Rec-ID | Code | Recommendation |
---|---|---|
REC304-2419 | 28 - Personal responsibility | Further define the principle of landholder responsibility for fire management and strengthen its fundamental place in the Act. This should include a clear requirement for landholders to prevent fire on their land from spreading to neighbouring properties. |
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2385 | 25 - Inquiry, audit, lessons management and after action review | TFS should initiate a policy review (seeking support from government as appropriate) to clearly identify what body or agency is responsible for planning, carrying out and enforcing fuel management on private property at a township level. If current arrangements are unclear or ineffective, TFS should request government to consider making this a statutory responsibility of TFS and provide any additional funding required to support this function. |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1344 | 25 - Inquiry, audit, lessons management and after action review | That a review of the cross‑tenure approach be undertaken to determine its effectiveness and to address issues that arise in fire prevention on private and public land. |
REC299-1343 | 25 - Inquiry, audit, lessons management and after action review | That the Government conduct a review of fire prevention |
REC299-1347 | 5 - Hazard reduction burns | In order to manage a reduced time window available to undertake the current types of planned burns, alternative methods, including the indigenous mosaic ‘cool’ burns, should be examined and trialled as they may extend the period in which planned burns can be undertaken while reducing overall risk and fuel loads. |
REC299-1341 | 5 - Hazard reduction burns | That in conjunction with a risk‑based approach, a minimum hectare target is also maintained that can be measured and compared. This minimum target should not be below the 5% target established by the Victorian Bushfire Royal Commission. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1250 | 22 - Role of local Gvt | That in flood-prone municipalities, the respective Municipal Committee develops or reviews flood-related sub-plans within a Municipal Emergency Management Plan at least every two years and submits each sub-plan to the Regional Controller for approval. In addition, that each Municipal Committee maintains a current flood plan, in a standardised format, which at least identifies: • flood-prone parts of their locality, particularly those where lives may be at risk; • required actions to be taken in the event of a flood threat, especially timely evacuation; • trigger points for taking required actions and how those trigger points will be monitored; and • how the community can access flood-plan information |
REC297-1261 | 28 - Personal responsibility | That heightened awareness and action is needed by communities when BoM issues flood watches and related warnings. Councils and SES need to facilitate this. |
REC297-1258 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the WMAwater report along with its own, analyses the differences, consults with the Forest Practices Authority and Environment Protection Authority, and proposes an appropriate course of action to Government. |
REC297-1273 | 25 - Inquiry, audit, lessons management and after action review | That the State Emergency Management Committee allocates resources to reviewing all findings and recommendations in the Productivity Commission Report No. 74 relevant to Tasmania and, for those identified as relevant, actions taken and, if none, why not. |
REC297-1264 | 25 - Inquiry, audit, lessons management and after action review | That the Flood Warning Consultative Committee reviews flood classification levels in the Service Level Specifications with BoM specifically relating to flood level triggers on gauges. |
REC297-1259 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the Forest Practice Code 2015 for relevance of its concepts to farming and other business activities near rivers, streams and naturally occurring dams and makes recommendations to Government accordingly. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1326 | 14 - Incident Mgt Teams | Establish a State-wide resourcing capability to support incident management teams, regional coordination centres, zone emergency centres, relief centres, recovery centres and State control centres. some of the features of such a capability should include: a) multi-agency, cross-government, State-wide pool of incident management and emergency management personnel building on the State incident management team concept currently facilitated by the Country Fire Service, and expanded to include all hazards, multiagency teams with a roster that provides year-round coverage b) a system that enables staff and volunteers from any agency to identify their availability for upcoming shifts c) a rostering system that enables one or more incident management teams, staging areas, regional coordination centres, State control centres and relief centres to develop, maintain and distribute rosters and structure charts in a more coordinated manner d) identifying areas of expertise for key incident and emergency management functions (e.g. public information, alerts and warning, media liaison, logistics and resource management) that would benefit from a coordinated and resource pooling approach and take steps to implement (consider the Mapping Functional Support Group model as a potential service delivery model). |
REC295-1297 | 25 - Inquiry, audit, lessons management and after action review | Engage an independent business analyst to review the current call, receipt and dispatch process for emergency services i.e. the Metropolitan Fire Service, Country Fire Service and State Emergency Service, from the initial call for assistance through to response of emergency service resources, including the allocation and coordination of multiple taskings. |
REC295-1276 | 25 - Inquiry, audit, lessons management and after action review | That SA Health undertake a review of their emergency management arrangements. Health State Controllers should be consulted during this review and arrangements should be consistent throughout the department and across the State and compatible with State emergency management arrangements and information systems |
REC295-1328 | 25 - Inquiry, audit, lessons management and after action review | Update the SEMP Part 3, Annex F ‘Debriefs’ to provide more guidance regarding the types of debriefs, when they are required to be undertaken and at what level and guidance for undertaking and recording debriefs, and implementing lessons identified. |
REC295-1307 | 20 - Role of police | That, as with earthquake, SA Police be designated the Control Agency under the State Emergency Management Plan for black system events or other major power outages. |
REC295-1327 | 25 - Inquiry, audit, lessons management and after action review | Establish a lessons management capability across the SA emergency management sector to collect, analyse and track lessons identified during debriefs and reviews following events and other sources such as interstate and oversees reviews and inquiries. |
REC295-1304 | 20 - Role of police | That SA Police, as the control agency for search and rescue, and State Emergency Service who have the responsibility for providing search and rescue services under the State Emergency Management Plan, develop a swiftwater rescue capability plan that describes key swiftwater risk locations, roles and responsibilities of emergency services, State swiftwater resources and dispatch arrangements. |
REC295-1317 | 25 - Inquiry, audit, lessons management and after action review | Review representation in the State Emergency Centre including: a) determining if there is a more suitable functional support group e.g. the Procurement Functional Support Group, to replace the Logistics Functional Support Group, and if so, Chief Procurement Officer, DPC, has responsibility for the management of this role within the State Emergency Centre. b) That when the State Crisis Centre is not operating from a physical location, a State Crisis Centre liaison officer is attached to the State Emergency Centre. |
REC295-1302 | 28 - Personal responsibility | That the State Emergency Service together with the Local Government Association and Country Fire Service establish a plan for coordinated provision of sandbags to the public, including options for what is provided, where and when, and the process for effective communication of availability to the public. |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1278 | 20 - Role of police | That SA Police develop an evacuation plan for the Adelaide Central Business District (CBD) which includes: |
REC295-1315 | 25 - Inquiry, audit, lessons management and after action review | That a review of the role and effectiveness of the State Emergency Management Committee (SEMC) including: the legislative functions; membership including the chair; roles and responsibilities; and, SEMC Advisory Groups be undertaken. |
Rec-ID | Code | Recommendation |
---|---|---|
REC292-2370 | 25 - Inquiry, audit, lessons management and after action review | I recommend that the New South Wales Police Force undertake a formal assessment of alternatives to the TOU’s current soft-point ammunition to determine whether a more appropriate form of ammunition is reasonably available. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1237 | 5 - Hazard reduction burns | The Department of Fire and Emergency Services, utilising the Office of Bushfire Risk Management, to develop a simplified and fast track hazard reduction burn (and other fuel mitigation techniques) planning and approval process to ensure the timely conduct of township and asset protection burns by Bush Fire Brigades and individual property owners. The process is to be agile and adaptable for the range of stakeholders which may participate in low risk, small scale, low complexity burn planning and approvals. |
REC291-1249 | 25 - Inquiry, audit, lessons management and after action review | The Department of the Premier and Cabinet to conduct an independent review of the current arrangement for the management and distribution of the Emergency Services Levy. The review will have the specific purpose of: · seeking input from key entities including the Departments of Treasury, Finance, Fire and Emergency Services, Lands, and Parks and Wildlife, WA Local Government Association, and the Office of Bushfire Risk Management. · ensuring the arrangement has the flexibility and agility to deal with emerging bushfire risk priorities. · establishing a budget process that enables a shift in investment towards prevention, mitigation and building community resilience and capability. |
REC291-1235 | 5 - Hazard reduction burns | The Department of Parks and Wildlife to continue emphasis on landscape hazard reduction burning with the annual objective of treating 140,000 hectares per annum in Land Management Zone C. In combination with Recommendation 2 (above) the strategic objective will be that a fuel age of less than six years will be maintained across 45% of the landscape on State Forest, National Parks and other Parks and Wildlife managed lands in the South West and Perth Hills. This will address the current backlog (created from under achievements of the recent two decades of burn programs) by the end of the 2020-2021 burning season (i.e. within the next 5 years). |
REC291-1240 | 14 - Incident Mgt Teams | The Departments of Parks and Wildlife and Fire and Emergency Services to adopt the policy that all bushfire Level 3 Incident Management Teams in the Perth Hills and the South West will be integrated and pre-formed from the start of the 2016/17 fire season with substantial involvement of both the Departments of Parks and Wildlife and Fire and Emergency Services personnel on all teams. |
REC291-1233 | 25 - Inquiry, audit, lessons management and after action review | The State Government to explore options for streamlining the functions and the independence of the State Emergency Management Committee Secretariat and the Office of Bushfire Risk Management with a view to including an inspectorate function, and appointing a person who is dedicated to that role. The purpose is to provide assurance and reporting, and to inquire into, monitor and report transparently on emergency management standards, preparedness, capability, service delivery and investment performance outcomes. Within two years of the establishment of this arrangement the State Government to review and assess whether it is meeting the desired outcomes. |
REC291-1234 | 5 - Hazard reduction burns | The Department of Parks and Wildlife to plan for the highest priority hazard reduction burning effort around settlements and critical assets in the South West and Perth Hills. The annual objective is to treat a total of 60,000 hectares of priority hazard reduction per annum, comprising 20,000 hectares per annum of Land Management Zone A and 40,000 hectares per year of Land Management Zone B. |
REC291-1239 | 14 - Incident Mgt Teams | The State Government to establish an arrangement to develop a ‘network’ of Western Australian State Government agency personnel who can be called upon for bushfire and emergency incident management capability within Western Australia. The arrangement will be led by the State Emergency Management Committee and modelled on systems used by the Department of Parks and Wildlife. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1214 | 14 - Incident Mgt Teams | Flexible pre‐formed multi‐ agency IMTs |
Rec-ID | Code | Recommendation |
---|---|---|
REC288-1195 | 5 - Hazard reduction burns | The Committee finds that on the evidence presented, that the Fuel Reduction Burn Program should be maintained and have its budget directly funded to ensure that the program continues and does not hinder other services or programs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC287-1185 | 25 - Inquiry, audit, lessons management and after action review | The Tasmanian fire agencies take steps at a national level to share learnings from the 2016 fires about the administration of interstate assistance and support the codifcation of the workings, structure and reporting lines of an Interstate and International Liaison Unit for future complex deployments within Australia and New Zealand. |
REC287-1188 | 25 - Inquiry, audit, lessons management and after action review | The Tasmanian fire agencies commission a review into the efectiveness of aerial firefghting in the 2016 fires, in order to better understand and to document for future reference the cost-efectiveness of specifc fire suppression strategies and tactics in different vegetation types. The Review should include a comparative analysis of fire suppression options whether aerial or ground-based. |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-2031 | 10 - Infrastructure | Improve information about electricity demand during heatwaves. |
REC286-2070 | 25 - Inquiry, audit, lessons management and after action review | Test the Biosecurity Act 2015. |
REC286-2052 | 22 - Role of local Gvt | Undertake local level emergency management planning for areas at risk of debris flow. |
REC286-1460 | 25 - Inquiry, audit, lessons management and after action review | Review seismic monitoring network alert systems to ensure emergency managers are on the contact lists. |
REC286-2043 | 22 - Role of local Gvt | Assessment of council’s capacity to manage land effectively. |
REC286-1442 | 25 - Inquiry, audit, lessons management and after action review | Review legislation relating to Fuel Stove only areas, Fire Permit System and Total Fire Bans to ensure appropriate incentives to modify individuals’ behaviour. |
REC286-2041 | 22 - Role of local Gvt | Development mechanisms to support small councils to manage treatment across the PPRR spectrum (across all hazards). |
REC286-1441 | 5 - Hazard reduction burns | Continue the Fuel Reduction Program. |
REC286-2084 | 10 - Infrastructure | Establish emergency services ICT redundancy arrangements for damage loss of communications infrastructure. |
REC286-1438 | 25 - Inquiry, audit, lessons management and after action review | Consider outcomes of national review of warnings and review resilience of warning systems’ infrastructure. |
REC286-1443 | 14 - Incident Mgt Teams | Build capacity to enable Incident Management Teams to manage the likely increased frequency and intensity of major fire events. |
Rec-ID | Code | Recommendation |
---|---|---|
REC285-2524 | 25 - Inquiry, audit, lessons management and after action review | The report recommends that Ambulance Tasmania investigate why the level of multiple responses had increased. |
REC285-2520 | 25 - Inquiry, audit, lessons management and after action review | The report recommends that Ambulance Tasmania investigate whether the additional resources in the North and North West regions were effective in reducing average response times. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1203 | 22 - Role of local Gvt | Impact Assessment Data Sharing The Office of Emergency Management: · with the SEOCON, jointly provides further guidance to Regional Emergency Management Officers about their role in facilitating local council access to the Impact Assessment Data Base · with REMOs and the SEOCON jointly provides further information to local councils about Impact Assessment Data Sharing Arrangements and the data available through this mechanism · includes information about the Impact Assessment Data Sharing Arrangements in the Local Recovery Toolkit · develops a mechanism to allow local councils to have direct access to the collated impact data. |
REC281-1201 | 25 - Inquiry, audit, lessons management and after action review | Preventing Flood Related Fatalities: The NSW Government consider the recommendations from the Preventing Flood Related Fatalities Report when it is released. |
Rec-ID | Code | Recommendation |
---|---|---|
REC280-1377 | 5 - Hazard reduction burns | That the NSW Rural Fire Service, in collaboration with the NSW National Parks and Wildlife Service, review and improve the system of bush fire management zones to ensure that greater priority is given to hazard reduction on land classified within land management zones. |
REC280-1376 | 5 - Hazard reduction burns | That the NSW National Parks and Wildlife Service establish a regime of frequent mosaic burning within the Warrumbungle National Park, where conditions permit, to be monitored and evaluated via a formal fully funded research program. This program should then inform the Service’s approach to the wider national park estate. |
REC280-1375 | 5 - Hazard reduction burns | That the NSW Government commit to and fund a long term program of prescribed burning based on the recommendation of the 2009 Victorian Bushfires Royal Commission of an annual rolling target of a minimum of five per cent of public land per year, and that the NSW Government commit to extending the funding for the National Parks and Wildlife Service five year hazard reduction program past 2016. |
REC280-1396 | 25 - Inquiry, audit, lessons management and after action review | That the Minister for Police and Emergency Services review the communications technologies used by the NSW Rural Fire Service, Fire and Rescue NSW, the NSW National Parks and Wildlife Service and Forestry NSW during fire fighting operations, to ensure that systems are standardised and effective. Within this context, the potential value of satellite phone technology should be investigated. |
REC280-1388 | 25 - Inquiry, audit, lessons management and after action review | That the NSW Rural Fire Service: |
REC280-1378 | 5 - Hazard reduction burns | That the NSW Rural Fire Service: -improve accountability in relation to the implementation of bush fire risk management plans as a means of delivering more hazard reduction. |
Rec-ID | Code | Recommendation |
---|---|---|
REC277-1164 | 14 - Incident Mgt Teams | Establish multi-agency preformed IMTs: An effective IMT for large and complex fire incidents requires the capacity and expertise of multiple agencies. Establishing multi-agency preformed IMTs will have three main benefits: adequate IMT resources can be deployed with ease • strong working relationships will be built between IMT members • common approaches to incident management and fire response can be embedded. |
Rec-ID | Code | Recommendation |
---|---|---|
REC274-1412 | 20 - Role of police | That Victoria Police assesses and where practical addresses limitations to available data and trials the use of response times for internal performance measurement. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1139 | 14 - Incident Mgt Teams | SACFS appoint the Regional Controller and/or Coordinator as the IC for any Level 3 incident occurring within their Region to provide better continuity and improved coordination. The position of the regional controller and/or coordinator could then be backfilled by a suitably qualified individual as required. |
REC273-1138 | 14 - Incident Mgt Teams | Review the communication and request procedures within SACFS to ensure that the most effective chain of command and line of communications are established between the Incident Management Team, region and state. |
REC273-1135 | 14 - Incident Mgt Teams | That SACFS conduct a review of SIMT with a view to increasing the number of teams from four to six, aligning them with each of the six regions within SA. |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1415 | 25 - Inquiry, audit, lessons management and after action review | An audit of all local government areas vulnerable to storm tide events is completed and opportunities identified to resolve gaps in evacuation zone planning to ensure consistency with the Queensland Evacuation Guidelines for Disaster Management Groups and neighbouring local government areas. |
REC272-1419 | 22 - Role of local Gvt | Opportunities should be identified through the Local Government Association of Queensland council to council arrangement to share structural engineers to assess potential places of refuge against the Department of Housing and Public Works’ structure classification criteria. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1533 | 14 - Incident Mgt Teams | State Disaster Coordination Centre considers requesting a representative from critical infrastructure owners be present as a liaison officer in the State Disaster Coordination Centre during activations for events that may impact on their assets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC268-1424 | 25 - Inquiry, audit, lessons management and after action review | The Queensland Emergency Alert Guidelines is reviewed to reflect current practice and incorporate evidence-based improvements informed by lessons learned and research. |
REC268-1422 | 25 - Inquiry, audit, lessons management and after action review | The Queensland State Disaster Management Plan is reviewed to: |
REC268-1423 | 22 - Role of local Gvt | The State Disaster Coordination Centre Notification Matrix is reviewed to ensure local governments are notified of any event affecting, or likely to affect, their local government area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1158 | 28 - Personal responsibility | Farm Management Deposits |
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1102 | 25 - Inquiry, audit, lessons management and after action review | SEMC Secretariat Community Emergency Management Officers should work with the Shire to document the Shire of Mundaring’s learnings from the Parkerville Stoneville Mt Helena fire with a view to sharing this with other local authorities particularly those facing similar situations in order to extend the range of tools available to assist local governments to understand their roles and responsibilities in future emergencies. |
REC265-1109 | 14 - Incident Mgt Teams | Future appointments to the role of Incident Controller should be limited to one for the entire duration of the incident, with nominated Deputy Incident Controllers to assist or ‘take charge’ in the Incident Controller’s absence. This measure will provide for a single point of responsibility and control for the incident and assist with any subsequent review or enquiry. If it is not possible to implement this proposal for liability reasons, the number of Incident Controllers should nevertheless be reduced to the minimum. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1087 | 25 - Inquiry, audit, lessons management and after action review | GDF Suez: • practice and ensures that, by taking a risk management approach, it is suitable for fire prevention, mitigation and suppression in all parts of the Hazelwood mine; and review its ‘Mine Fire Service Policy and Code of Practice’ so that it refects industry best • work plan for the Hazelwood mine. incorporate the revised ‘Mine Fire Service Policy and Code of Practice’ into the approved |
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
REC264-1086 | 25 - Inquiry, audit, lessons management and after action review | GDF Suez: • consequences of fire in the worked out areas of the Hazelwood mine, and an assessment of the most effective fre protection for the exposed coal surfaces; conduct, assisted by an independent consultant, a risk assessment of the likelihood and • controls are in place to eliminate or reduce the risk of fre; and prepare an implementation plan that ensures the most effective and reasonably practicable • implement the plan |
REC264-1072 | 25 - Inquiry, audit, lessons management and after action review | The State empower and require the Auditor-General or another appropriate agency, to: • oversee the implementation of these recommendations and the commitments made by the State and GDF Suez during this Inquiry; and • report publicly every year for the next three years on the progress made in implementing recommendations and commitments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1490 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority critically reviews: |
REC262-1489 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority reclassifies its State Emergency Communications Centres as critical national infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1508 | 25 - Inquiry, audit, lessons management and after action review | That the NSW Rural Fire Service review its procedures, systems and infrastructure for notifying community members of bush fires, both when a fire has broken out and as it proceeds, to ensure the provision of timely and adequate information. |
REC261-1505 | 25 - Inquiry, audit, lessons management and after action review | That the NSW Rural Fire Service: |
REC261-1495 | 5 - Hazard reduction burns | That the NSW Rural Fire Service: |
REC261-1500 | 10 - Infrastructure | That the NSW Government improve the protection of media and telecommunications towers around New South Wales by: |
REC261-1493 | 5 - Hazard reduction burns | That the NSW National Parks and Wildlife Service establish a regime of frequent mosaic burning within the Warrumbungle National Park, where conditions permit, to be monitored and evaluated via a formal fully funded research program. This program should then inform the Service’s approach to the wider national park estate. |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1063 | 5 - Hazard reduction burns | That the National Parks and Wildlife Service consider reviewing its guidelines and protocols in respect of hazard reduction planning and burning-off operations in the light of the evidence from experts witnesses in these proceedings that the incidence of, and intensity of, major fires is increasing and in the light of expert evidence given in these proceedings concerning the dangers of vorticity-driven lateral spread. |
REC260-1052 | 14 - Incident Mgt Teams | That the Rural Fire Service consider amending its fire prediction reports to include a checklist of significant factors that have not been able to be considered in the prediction model and a warning to be alert for them and seek intelligence on them from fire ground managers. |
REC260-1058 | 28 - Personal responsibility | That NPWS and the RFS consider developing a land management policy that requires active engagement with property owners adjoining the Park to ensure that hazard reduction and asset protection is encouraged and undertaken before the bush fire season commences |
REC260-1066 | 14 - Incident Mgt Teams | That during periods of ‘severe’ or worse fire conditions, that the National Parks and Wildlife Service consider adopting a posture of pre-emptive planning and deployment of incident management teams in national parks similar to the manner in which the Rural Fire Service does. |
REC260-1070 | 5 - Hazard reduction burns | The NPWS conduct a review of its prescribed burns program to ensure, as far as reasonably practicable, that all necessary managerial approvals for a prescribed burn are provided as promptly as possible. |
REC260-1053 | 14 - Incident Mgt Teams | That in Class 3 fire-fighting operations, the Rural Fire Service consider including a fire behaviour analyst in the incident management team if feasible. |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2549 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority provides full disclosure of audit findings at audit exit briefings in accordance with international best practice. |
REC258-2528 | 25 - Inquiry, audit, lessons management and after action review | The Australian Transport Safety Bureau investigates as many fatal accidents in the sport and recreational aviation sector as its resources will allow. |
REC258-2556 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority structures all regulations not yet made with the three-tier approach, and subsequently reviews all other Civil Aviation Safety Regulation Parts (in consultation with industry) to determine if they should be remade using the three-tier structure. |
REC258-2552 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority implements a system of using third-party commercial audits as a supplementary tool to its surveillance system. |
REC258-2551 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority assures consistency of audits across all regions, and delivers audit reports within an agreed timeframe. |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1555 | 14 - Incident Mgt Teams | The lines of responsibility be made clearer and some individual, perhaps the Regional Environmental Officer, or agency be given overarching responsibility to ensure recommended works related to bushfire mitigation on Defence Estate are carried out in accordance with the Bushfire Management Plan which the Manual for Fire Protection Engineering directs be prepared. |
REC257-1548 | 25 - Inquiry, audit, lessons management and after action review | The Regional Director-Defence Support-Northern NSW, make contact with Deputy Commissioner ~~~~~ Director of Operational Services Rural Fire Service, to arrange a headquarters driven bipartite review of the events of 16 October 2013 with a review to mitigation of future fire events generally, and with specific reference to: |
REC257-1546 | 25 - Inquiry, audit, lessons management and after action review | Defence undertake a review of its ability to respond to a fire within Marrangaroo Training Area, whether bushfire or structural. The underlying assumption should be that the only response available to fight a fire within Marrangaroo Training Area will be provided by Defence. Further, such response must occur while a fire is in its initial stages. A review must either acknowledge the risk of fire occurring in th future, or upgrade Defence's firefighting capability at Marrangaroo Training Area. |
REC257-1539 | 25 - Inquiry, audit, lessons management and after action review | Defence Security Authority conduct an investigation into the whereabouts of items of anaccounted explosive ordnance issued to Defence Explosive Ordnance Training School Exercise Marrangaroo. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1573 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government should schedule an independent and public review of the progress of reforms to natural disaster funding arrangements five years after implementation has commenced. This review should examine the operation and efficacy of the arrangements, including the: |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1587 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
REC254-1585 | 14 - Incident Mgt Teams | DFES and Local Government Bushfire Brigades ensure that only those with the required AIIMS competence have the authority to manage Level 1 incidents, noting they may not be Fire Control Officers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC252-2570 | 25 - Inquiry, audit, lessons management and after action review | Western Australia Health should carry out targeted clinical audits in volunteer country sub-centres until longer term solutions are in place |
REC252-2570 | 25 - Inquiry, audit, lessons management and after action review | Western Australia Health should carry out targeted clinical audits in volunteer country sub-centres until longer term solutions are in place |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0790 | 25 - Inquiry, audit, lessons management and after action review | The Department of Justice should review the current model for rapid impact assessment to improve the quality of the information collected. |
REC250-0791 | 22 - Role of local Gvt | Local Government Victoria should lead the design and implementation of strategies to support councils to further develop social capital needed for recovery. |
REC250-0796 | 25 - Inquiry, audit, lessons management and after action review | The Department of Premier and Cabinet should lead: x the development of an evaluation framework, based on work undertaken to date by the Department of Human Services, to be used in assessing the impact of relief and recovery programs in the recent floods and in future disaster events x an evaluation of the impact of relief and recovery programs in the recent floods, using this framework. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0947 | 20 - Role of police | That Tasmania Police develops and implements a program for examining emergency management arrangements and facilities in Australia. |
REC247-0909 | 25 - Inquiry, audit, lessons management and after action review | That the plans for social recovery be reviewed, and plans and procedures are established ready for implementation. |
REC247-0938 | 5 - Hazard reduction burns | That Tasmania Fire Service or another suitable agency provides information to the community which shows, in simple form, the legislation applicable to approvals for lighting fires on private property and the various relationships between that legislation. |
REC247-0951 | 25 - Inquiry, audit, lessons management and after action review | That an independent means of monitoring and reporting on the implementation of approved recommendations is established. |
REC247-0946 | 20 - Role of police | That Tasmania Police establishes a section within its structure with responsibility for developing and maintaining contemporary expertise in emergency management, progressing innovation, assisting organisational change initiatives and supporting its responsibilities in state emergency management arrangements. |
REC247-0903 | 25 - Inquiry, audit, lessons management and after action review | That the role of Red Cross in emergency management plans and procedures for the activation of Red Cross be reviewed. |
REC247-0911 | 14 - Incident Mgt Teams | That emergency management plans specifically include processes and resources for effectively engaging with and using local communities, including volunteers |
REC247-0941 | 25 - Inquiry, audit, lessons management and after action review | That the Strategic Fuel Management Plan includes measurable targets and they are actively monitored and reported on to the community. |
REC247-0945 | 20 - Role of police | That Tasmania Police conducts a review to ensure emergency management is treated as a priority and a core function throughout the organisation, including the development of contemporary capabilities, and is supported by an appropriate culture. |
REC247-0873 | 25 - Inquiry, audit, lessons management and after action review | If it is considered more information is required on action to suppress the fires in Dunalley and why fire operations did not continue, the Department of Justice should conduct an independent examination of this matter. |
REC247-0862 | 14 - Incident Mgt Teams | That Tasmania Fire Service and its partner agencies establish a means of monitoring and reviewing the effectiveness of centralising the location of Incident Management Teams. |
REC247-0927 | 25 - Inquiry, audit, lessons management and after action review | That an accountability process be established for managing improvement in the emergency management arrangements, including annual State of Readiness Reports by relevant departments and agencies and on the overall emergency management arrangements. |
REC247-0904 | 10 - Infrastructure | That the Department of Infrastructure Energy and Resources consult Aurora Energy on the use of wooden poles for overhead infrastructure with a view to mitigating the risk in bushfires. |
REC247-0861 | 14 - Incident Mgt Teams | That Tasmania Fire Service examines options for developing and issuing fire management objectives and tactics from Incident Management Teams in a more timely way, including ‘quick’ plans. |
REC247-0926 | 25 - Inquiry, audit, lessons management and after action review | That membership of the State Emergency Management Committee, and other processes to link in appropriate agencies and organisations to emergency management, be included in the recommended review of the emergency management arrangements. |
REC247-0853 | 14 - Incident Mgt Teams | That the State Controller (or an alternate if they are not available) be expected to personally take an active role in controlling and coordinating response and recovery operations, depending on the nature and scale of the emergency, and until other identified arrangements for ongoing operations are established. |
REC247-0923 | 25 - Inquiry, audit, lessons management and after action review | That a process be established for the timely implementation of approved recommendations from the 2009 Victorian Bushfires Royal Commission. |
REC247-0939 | 5 - Hazard reduction burns | That Tasmania Fire Service conducts a review of the fire permit system in the Fire Service Act 1979, and implements change to improve the efficiency and effectiveness of the system by: • considering whether it is appropriate to authorise persons or organisations to conduct fuel reduction burning during a permit period • providing a better match between the period, area and fire risk • maintaining a timely and efficient process for issuing permits • naming the period in a way that draws attention to bushfire risk • establishing a reporting and accountability process. |
Rec-ID | Code | Recommendation |
---|---|---|
REC246-0786 | 14 - Incident Mgt Teams | TFS develop written guidelines for the use of IMTs about the use of evacuation in a bushfire context, and triggers for decision-making. |
REC246-0788 | 25 - Inquiry, audit, lessons management and after action review | TFS seek to address the following outstanding items from the recommendations of the Victorian Bushfires Royal Commission. § 45 out of 53 Community Bushfire Response Plans for “at risk” communities have been finalized. The remaining eight should be completed as a priority action. § That TFS progress the development of Community Bushfire Mitigation Plans for the 53 at risk communities, possibly as an action for reactivated Fire Management Area Committees. § TFS, together with other ESOs and local government, should develop a common comprehensive approach to the option of planned evacuation from dangerous or potentially dangerous areas to safer areas and eventual return. § TFS should include factors for consideration for evacuation during a bushfire into their training doctrine for Incident Controllers. § The IAP Template and its application be reinforced as an important operational requirement for IMT’s during the 2013-14 pre-season briefing program. 10 § That TFS review their use of IRMS to ascertain if either its full potential is not being realized through a lack of operator training or it is in fact not providing the required functionality and there is a need to research an improved resource management system which enhances interoperability. § The TFS Publication: Guidelines for Development in Bushfire Prone Areas of Tasmania http://www.fire.tas.gov.au/userfiles/stuartp/file/Publications/BushDeve… s2012.pdf requires an update to reflect the provisions of Planning Directive #5 Bushfire-Prone Areas Code. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2600 | 25 - Inquiry, audit, lessons management and after action review | An external audit of shared services performed by SAFECOM and services now provided by the three ESOs which have the potential to be shared, be undertaken to determine the most efficient and cost effective way such services can be delivered to the sector. The three ESO Chiefs need to have input into this process. |
REC244-2631 | 25 - Inquiry, audit, lessons management and after action review | Review Section 134 to ensure that it is not a deterrent to a group of farm fire units operating at an incident. |
REC244-2620 | 25 - Inquiry, audit, lessons management and after action review | Review employment conditions under the F&ES Act to align with those under the Public Sector Act unless there is a compelling reason to the contrary. |
REC244-2617 | 25 - Inquiry, audit, lessons management and after action review | When judging major incidents in the future, consideration be given to Eburn and Dover’s proposal to establish processes with a statutory basis that sufficiently balance the community’s interests in ensuring that true lessons, including lessons of error or neglect, are identified, whilst also protecting members of the emergency services. Processes need to be developed for emergency services such as those used in aviation and medicine, to facilitate open and honest disclosure of errors. |
REC244-2606 | 22 - Role of local Gvt | The Act be amended to require the mandatory appointment of Authorised Officers by each rural council or council that has within its area a Designated Urban Bushfire Risk Area(s) with an option for the CFS Chief Officer to exempt council from this requirement (similar to Section 105B). |
REC244-2601 | 25 - Inquiry, audit, lessons management and after action review | That an independent review of the operational and geographic boundaries of the ESOs be conducted recognising the limitations of the current governance structures to adequately address such issues. Such a review needs to be performed periodically, but not less than every 8 years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC242-2643 | 25 - Inquiry, audit, lessons management and after action review | That the Government consult broadly upon and review impediments to volunteering in the community and establish a taskforce to assist in removing barriers to volunteering, particularly with respect to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-0997 | 5 - Hazard reduction burns | That the electronic fire permit system used in the Mackay District be made available across the state for Fire Wardens who wish to use it. |
REC241-0996 | 5 - Hazard reduction burns | That Section 66 (2) of the Fire and Rescue Service Act 1990 relating to the exemption for issuing of permits to burn in State Forests, National Parks and Reserves is withdrawn and Departments must work within the District Fire Management Plan. |
REC241-0999 | 28 - Personal responsibility | That on all land where fuel load creates a fire risk, the owner shall be responsible for the construction and maintenance of effective firebreaks. Failure to provide effective and accessible firebreaks will result in the cost of firebreak construction to control a wildfire on this land being debited to the land owner |
REC241-0995 | 5 - Hazard reduction burns | At the next reprint of the ‘Permit to Light Fire’ book, the requirement to notify neighbours when applying for a permit is reinstated to properly reflect the requirement under the Fire and Rescue Service Act 1990. |
REC241-0994 | 5 - Hazard reduction burns | That the Rural Fire Service Queensland needs to provide greater emphasis and acknowledgement of the use of fire as a tool in sustainable land management. |
REC241-1030 | 25 - Inquiry, audit, lessons management and after action review | That Rural Fire Brigades only be required to conduct an audit of finances if the Brigades income exceeds $5,000 for a financial year. RFSQ District offices should investigate options for savings on the costs of auditing Brigades in their district through either an in-house or external provider. Legal Status of Brigades |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2757 | 20 - Role of police | That the Queensland Police Service executive team reassesses its preparedness to collaborate with other agencies to deliver a whole of Government approach to delivering community safety. |
REC239-2689 | 20 - Role of police | That, where appropriate, the Commissioner of Police appoints appropriately trained and experienced public service officers to appropriate roles in the disaster management system to support District Disaster Coordinators in their vital roles. |
REC239-2763 | 25 - Inquiry, audit, lessons management and after action review | That the proposed efficiency review includes a focus on the rank structure of both the Queensland Police Service and the proposed Fire and Emergency Services. |
REC239-2752 | 20 - Role of police | That the roll-out of the Queensland Police Service digital technology should take into consideration adopting and facilitating new processes including the police response to domestic violence. |
REC239-2758 | 25 - Inquiry, audit, lessons management and after action review | That the Chief Executive Officer Portfolio Business leads an efficiency review of portfolio agencies beginning with the Queensland Police Service. |
REC239-2750 | 20 - Role of police | That the Queensland Police Service: |
REC239-2688 | 22 - Role of local Gvt | That in establishing new disaster districts, the first guiding principle must be to align with local government boundaries and that divergence should only occur when there is a need to address a unique local circumstance. |
REC239-2727 | 25 - Inquiry, audit, lessons management and after action review | That as part of its efficiency review, the Queensland Fire and Rescue Service instigate an independent review of commercial operations in terms of statutory obligations and current ‘full cost pricing’ methodology to ensure: |
REC239-2748 | 20 - Role of police | That the Queensland Police Service considers adopting the broader use of ANPR in line with other Australian jurisdictions in consultation with the Privacy Commissioner. |
REC239-2777 | 25 - Inquiry, audit, lessons management and after action review | That the review of this Queensland Fire and Rescue Services business unit be done in conjunction with the efficiency review proposed for the Queensland Police Service. |
REC239-2725 | 25 - Inquiry, audit, lessons management and after action review | That the Queensland Fire and Rescue Service community safety operations be joined in the efficiency review of the Queensland Police Service focussing on both the community safety outcomes achieved and the extent to which they support the Government’s economic priorities. |
REC239-2747 | 20 - Role of police | That as the Queensland Police Service moves to a digital platform the strategy around effective targeting and alternative automated number plate recognition models should form part of the design architecture. |
REC239-2776 | 25 - Inquiry, audit, lessons management and after action review | That the proposed efficiency review of the Queensland Police Service examine whether: |
REC239-2724 | 25 - Inquiry, audit, lessons management and after action review | That the Queensland Fire and Rescue Service undertake a review of all standing orders, incident directives and guidelines regarding response protocols with a view to reducing risk to staff and other road users associated with urgent duty driving. |
REC239-2726 | 20 - Role of police | That the Queensland Fire and Rescue Service enters into discussion with the Queensland Police Service regarding the possibility for the Queensland Police Service to assist with prosecutions that may arise out of fire safety matters. |
REC239-2764 | 25 - Inquiry, audit, lessons management and after action review | That the proposed efficiency review consider whether special service functions are core business, whether this practice is sustainable, and other options such as the use of casual employees. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0802 | 25 - Inquiry, audit, lessons management and after action review | Review the NSW state-wide governance arrangements for flood risk management so that broader issues identified by this Review can be most effectively addressed. |
Rec-ID | Code | Recommendation |
---|---|---|
REC236-2795 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that a short inquiry be conducted by the Senate Standing Committee on Rural and Regional Affairs and Transport into the current status of aviation regulatory reform to assess the direction, progress and resources expended to date to ensure greater visibility of the processes. |
REC236-2793 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that CASA processes in relation to matters highlighted by this investigation be reviewed. This could involve an evaluation benchmarked against a credible peer (such as FAA or CAA) of regulation and audits with respect to: non-RPT passenger carrying operations; approach to audits; and training and standardisation of FOI across regional offices. |
REC236-2792 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the investigation be re-opened by the ATSB with a focus on organisational, oversight and broader systemic issues. |
REC236-2806 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the relevant agencies investigate appropriate methods to ensure that information about the incidence of, and variable weather conditions at, Norfolk Island is available to assist flight crews and operators managing risk that may result from unforseen weather events. |
REC236-2805 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the relevant agencies review whether any equipment or other changes can be made to improve the weather forecasting at Norfolk Island. The review would include whether the Unicom operator should be an approved meteorological observer. |
REC236-2801 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the ATSB review its process to track the implementation of recommendations or safety actions to ensure it is an effective closed loop system. This should be made public, and provided to the Senate Regional and Rural Affairs and Transport Committee prior to each Budget Estimates. |
Rec-ID | Code | Recommendation |
---|---|---|
REC233-1590 | 25 - Inquiry, audit, lessons management and after action review | Department of Broadband, Communications and the Digital Economy seek regular updates from Telstra on the implementation of the recommendations of its inquiry into the Warrnambool exchange fire. |
REC233-1602 | 28 - Personal responsibility | Individuals without a mobile phone who are concerned about access to Triple Zero during a prolonged telecommunications outage could consider purchasing a low cost mobile phone with a charger to keep at home for use during such outages. Since mobile phones do not require SIM cards to make emergency calls (‘000’ and ‘112’), there will be no ongoing costs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2827 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government, in consultation with state and territory governments, conduct a comprehensive national audit and mapping exercise to: |
REC232-2815 | 25 - Inquiry, audit, lessons management and after action review | The Department of Health and Ageing review the existing evidence base to evaluate the cost-effectiveness of its policy to use heat scanners at ports of entry as a measure to mitigate the risk of infectious disease importation. |
REC232-2828 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government, in consultation with state and territory governments, commission an independent review to assess the case for establishing a national centre for communicable disease control in Australia. The review should outline the role of a national centre and how it might be structured to build on and enhance existing systems. It should examine different models, considering a range of options for location, governance and staffing. The review should incorporate a cost-benefit analysis for each of the models presented. |
Rec-ID | Code | Recommendation |
---|---|---|
REC230-2833 | 10 - Infrastructure | If recommendation 1 is not supported by the Australian Government, the committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate as a minimum requirement, 20 MHz in the 800 MHz band for the purposes of a public safety mobile broadband network. |
REC230-2832 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy take appropriate measures to secure, for public service agencies, priority access to an additional 10 MHz of spectrum in the 700 MHz band for public safety purposes. |
REC230-2831 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate 20 MHz of contiguous spectrum in the 700 MHz band for the purposes of a public safety mobile broadband network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1609 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency should undertake audits to meet the requirements in the Strategic Bushfire Management Plan for the preparation, sharing and publication of annual progress reports. Annual progress reports should be made available to the ACT Bushfire Council. |
REC228-1620 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency, in consultation with the Territory and Municipal Services Directorate, should review the Farm FireWise Program, including: |
REC228-1614 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency, in consultation with the ACT Bushfire Council, should conduct a review of the ACT Bushfire Council against its recently developed terms of reference (July 2013) within two years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2849 | 20 - Role of police | I recommend that the AFP takes steps to ensure that there are on Christmas Island at all times appropriately trained AFP officers who have completed the National Police Search and Rescue Manager’s Course and that upskilling should be ongoing to establish a cadre of trained search and rescue personnel. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0555 | 14 - Incident Mgt Teams | The state should identify the number of fully trained, experienced and accredited Level 3 Incident Controllers required to be available at any time and establish a process for identification of suitable personnel, ongoing training and accreditation. |
REC226-0585 | 14 - Incident Mgt Teams | DEC’s fire management expertise should be augmented by multi-agency IMTs that incorporate the expertise of other agencies and in fast developing situations the appropriate decisions will need to be made early. |
REC226-0597 | 22 - Role of local Gvt | Given the prominent role played by the Shire in the management of welfare aspects in this emergency, there may be a need for state sponsored training for shire staff who are involved in implementing state emergency management policies and plans including how to deal with traumatised individuals. |
REC226-0563 | 14 - Incident Mgt Teams | Procedures to relocate IMTs need to be established in doctrine and exercised to ensure continuity of control. |
REC226-0570 | 14 - Incident Mgt Teams | Logistics and resource officers in IMTs need to collaborate and establish full awareness and control over the available resources. |
REC226-0544 | 5 - Hazard reduction burns | Prescribed burns which meet the ‘red flag’ criteria should have mandated risk Establish risk management criteria for management criteria imposed. |
REC226-0554 | 14 - Incident Mgt Teams | For incidents of this complexity, effective control in the critical phase (first 24-36 hours of the fire) requires an appropriately resourced IMT. |
REC226-0584 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command and not through agency chains of command |
REC226-0593 | 22 - Role of local Gvt | Good Local Government planning and management facilitates community resilience. |
REC226-0562 | 14 - Incident Mgt Teams | Opportunities be sought to utilise local government representatives in other areas of the IMT particularly in public information or other community related functions. |
REC226-0567 | 14 - Incident Mgt Teams | IMTs need to establish early and effective liaison with Local Governments. |
REC226-0543 | 5 - Hazard reduction burns | There should be clearly established criteria for burns which are specially challenging, and these criteria need to extend beyond the intended boundaries of the prescribed burn. |
REC226-0551 | 14 - Incident Mgt Teams | As presently implemented, the AIIMS planning role is under-developed and provides insufficient support to the Incident Controller. |
REC226-0575 | 14 - Incident Mgt Teams | In multi-agency responses the culture, training and equipment characteristics of each of the agencies should be considered in their employment. |
REC226-0559 | 22 - Role of local Gvt | Early contact with the LG A is critical. |
REC226-0558 | 14 - Incident Mgt Teams | Predetermined locations for Level 3 IMTs should be reviewed and adequately resourced with necessary communications and IT capacity. |
REC226-0566 | 14 - Incident Mgt Teams | Incident Controllers should be supported by a planning function that combines experienced weather forecasters, fire behaviour experts and local knowledge. |
REC226-0542 | 5 - Hazard reduction burns | A risk management approach is needed which considers risks both inside the prescribed burn and the risks that will need to be managed if the fire escapes. This risk assessment should be dynamic in line with the four day and seven day weather forecast. |
REC226-0550 | 14 - Incident Mgt Teams | Greater investment in training on specific functions within the AIIMS structure will improve the support provided to the Incident Controller. |
REC226-0574 | 14 - Incident Mgt Teams | Clear direction to divisional and sector commanders and a common communications platform enables maximum return to be gained from the application of tactical resources and this rests on good incident action planning, and good command and control. |
REC226-0557 | 14 - Incident Mgt Teams | An intensive exercise/training program should be developed and maintained across agencies to identify and establish a pool of current Incident Controllers who are capable of managing a Level 3 incident. |
REC226-0587 | 14 - Incident Mgt Teams | To be effective, multi-agency IMTs will need to be exercised regularly and supported by sound and comprehensive doctrine. |
REC226-0565 | 14 - Incident Mgt Teams | Contingency planning is a critical function in the early stages of an escalating incident, and should provide the foundation of an IAP. |
REC226-0573 | 14 - Incident Mgt Teams | Strategic direction seeks to identify and resource those areas of tactical action that offer the greatest advantage. |
REC226-0556 | 14 - Incident Mgt Teams | Within the AIIMS IMT doctrine the roles of the Incident Controller and Deputy Incident Controllers should be defined and well-practiced. |
REC226-0586 | 14 - Incident Mgt Teams | At Level 3, the available fire management expertise should be applied overwhelmingly to the fire management aspects of emergency management, possibly in incident control, and certainly in situations planning and operations roles. |
REC226-0564 | 14 - Incident Mgt Teams | The expected scenario, with a view to the worst-case scenario should provide the basis for an IAP. |
REC226-0572 | 14 - Incident Mgt Teams | Contingency planning before the fire may have supported the IMT in recognising and seizing strategic opportunities earlier. |
REC226-0553 | 5 - Hazard reduction burns | Rolling risk assessment conducted during ignition of prescribed burns should identify whether an escape is likely to develop into a Level 3 incident. As soon as possible after it has been identified that the escape cannot be contained, the incident should be declared a Level 3. |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0540 | 25 - Inquiry, audit, lessons management and after action review | : In due course, acts of bravery are considered and recommendations for awards are submitted, including commendations for the delivery of First Aid. |
REC225-0538 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC224-1634 | 10 - Infrastructure | The Minister for Emergency Services should urgently review the technical issues with the Western Australia Emergency Radio Network program that is forcing the State’s firefighters to revert to their older radio networks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0523 | 25 - Inquiry, audit, lessons management and after action review | The Government consider enacting legislation to facilitate the review of all future major incidents, including but not limited to fire, earthquake, storm and marine inundation, and the emergency response to them. |
REC223-0522 | 25 - Inquiry, audit, lessons management and after action review | The response operation to the Margaret River bushfire in November 2011 be the subject of a review with independent oversight. |
REC223-0515 | 5 - Hazard reduction burns | The Department of Environment and Conservation urgently undertake a review of its risk management practices as they relate to prescribed burns including but not limited to: *reviewing risk management practices to ensure that they are in accordance with AS/NZS ISO 31000:2009; * finalising and implementing the new complexity model developed in house by the DEC; * considering a broader set of parameters of risk by conducting an environmental scan or similar tool for areas under consideration for a prescribed burn; *updating the prescribed fire plans to reflect the broader risk considerations discovered through environmental scanning; *better informing the risk considerations by updating the ‘Red Book’ to reflect current research on burning in coastal heath; and * reconsidering the utility of the ‘Red Flag Burn’ notification on files and either adopting it as a policy across the State or removing it as a consideration. |
REC223-0516 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Conservation review its implementation of the findings of the Ferguson Review conducted in 2010. |
REC223-0514 | 5 - Hazard reduction burns | The Department of Environment and Conservation review its current policies and operational guidelines in particular by: * strengthening the governance of operations by ensuring the Guidelines are relevant and practical; * ensuring the processes that are implemented for prescribed burns are: (a) value adding to the decisions and approvals required (b) informed by substantive input (c) focussed on outcome rather than process; *completing the draft management plan for the Leeuwin-Naturaliste Capes Area Parks and Reserves in accordance with the provisions of the Conservation and Land Management Act 1989; * exploring the possibility of automating and streamlining the various processes for formulating a prescription for prescribed burns for ease of access and updating; and * clarifying the guidance provided to decision makers as to the ‘edging’ and security of prescribed burns. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1869 | 25 - Inquiry, audit, lessons management and after action review | The Ministers for Emergency Services, Environment and Police ensure their departments include provisions for regular external audits of invoices for payment in their next round of Employee Assistance Program contract negotiations. |
REC222-1862 | 25 - Inquiry, audit, lessons management and after action review | The Minister for Emergency Services request the State Emergency Management Committee to review by June 2013 the sharing of data between the State’s emergency response agencies using the WebEOC software and any further enhancements that can be made to this process. |
REC222-1847 | 25 - Inquiry, audit, lessons management and after action review | The Ministers for Emergency Services, Environment and Police ensure their departments undertake a formal review by 30 June 2013 of the welfare services addressing stress and trauma provided to both their career and volunteer members. |
REC222-1855 | 22 - Role of local Gvt | Local government authorities incorporate into their Local Emergency Management Plans their procedures for dealing with any trauma experienced by bushfire brigade volunteers, having regard to best practice in managing trauma. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1825 | 22 - Role of local Gvt | When developing flood mitigation options in lowland areas, local governments should give consideration to the use of temporary levees as an alternative or addition to permanent structures. To maximise the use of these structures and limit flood damage, and aid affordability, consideration should be given by local governments to the sharing of temporary levees among different townships and different council areas. |
REC217-1819 | 22 - Role of local Gvt | In consultation with local communities, local councils will develop flood response plans as subplans to their current Municipal Emergency Management Plans. As part of the flood risk assessment process, these plans will be informed by the best available flood mapping and modelling, and will identify agreed activities to be undertaken during floods including, where appropriate, the construction of temporary levees. The condition of levees will be incorporated into such plans to enable improved emergency response. |
REC217-1840 | 25 - Inquiry, audit, lessons management and after action review | The state government implement the Victorian Floods Review recommendation 8, to review the flood gauging network. As part of the review, consideration should also be given to the use of portable telemetered river gauges, and to the replacement of manual gauges with telemetered gauges over time and where appropriate. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2867 | 14 - Incident Mgt Teams | Agency incident management preparedness: refining IT tools to process the intelligence. |
REC216-2866 | 14 - Incident Mgt Teams | Agency incident management preparedness: provide clarity and certainty in specific roles and responsibilities for each agency. |
REC216-2871 | 22 - Role of local Gvt | Efficient and effective supporting tools and processes: high-quality local/municipal planning. |
REC216-2868 | 14 - Incident Mgt Teams | Agency incident management preparedness: a more comprehensive approach to planning, including the number of personnel, their training and better use of on-the-ground intelligence in the affected areas that enables immediate and strategic decision-making to be concurrent processes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1871 | 14 - Incident Mgt Teams | Fire services can improve outcomes by developing a checklist for use by incident controllers |
REC215-1879 | 25 - Inquiry, audit, lessons management and after action review | Regulators can help to achieve improved outcomes by auditing compliance with the BPEM guidelines on a regular basis |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0668 | 22 - Role of local Gvt | Councils should review their assessment processes to ensure that: • the person with primary responsibility for the assessment of the development application considers what expert input is required • where a development application is subject to comment by a number of professionals, the responsibilities and accountability of each contributor are clear • where flood-related information is referred to an expert for advice, the expert is required to comment on the extent of compliance by reference to each relevant assessment criteria and identify and explain any inability to comment. |
REC210-0630 | 22 - Role of local Gvt | If the Queensland Government does not include a requirement for such an overlay map in the model flood planning controls, councils should include a flood overlay map in their planning schemes. The map should identify the areas of a council region: • that are known not to be affected by flood • that are affected by flood and on which councils impose planning controls (there may be subsets in each area to which different planning controls attach) • for which there is no flood information available to council. |
REC210-0688 | 22 - Role of local Gvt | All councils should periodically conduct risk assessments to identify areas at risk of backflow flooding. In respect of such areas, councils should consider how such risks can be lessened, including in that process consideration of the installation of backflow prevention devices. Backflow devices should not, however, be installed unless and until a full risk based assessment has been undertaken. |
REC210-0650 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require that: a. the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) take place above a certain flood level, determined following an appropriate risk based assessment, or b. structures on land susceptible to flooding and used for the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) be designed to prevent the intrusion of floodwaters |
REC210-0738 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that any future peer review process: • is co-ordinated by someone independent of those who wrote the report • entails the provision of all relevant information to the peer reviewers • permits sufficient time for the review • documents all contact between those whose actions are under review and the reviewers. |
REC210-0667 | 22 - Role of local Gvt | If the Queensland Government does not include such a policy in the model flood planning controls, councils should include a planning scheme policy in their planning schemes that sets out the information to be provided in development applications in relation to stormwater and flooding. The policy should specify: • the type of models and maps to be provided • the substantive information required to be shown in the development application • how the assumptions and methodologies used in preparing the models and maps should be presented • the form in which the information on stormwater and flooding is to be presented in the application. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0610 | 22 - Role of local Gvt | Councils in floodplain areas should, resources allowing, develop comprehensive floodplain management plans that accord as closely as practicable with best practice principles. |
REC210-0687 | 22 - Role of local Gvt | The Bundaberg Regional Council should investigate the adequacy of the drain and take reasonable steps to ensure the Moore Park area is effectively served. |
REC210-0679 | 28 - Personal responsibility | If the Queensland Development Code is amended to include provisions requiring homeowners to install sewage reflux valves, the Queensland Government should develop and make available to homeowners appropriate guidance material to assist them in meeting their responsibilities to maintain reflux valves. |
REC210-0648 | 22 - Role of local Gvt | Councils should ensure that, when applications for environmentally relevant activities are approved by a council, the details of those activities, including their nature and location, are provided to the Department of Environment and Resource Management. |
REC210-0737 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should ensure that an independent and appropriately qualified person immediately starts the task of reviewing the March flood event report to ensure that the review is completed before the start of the 2012/2013 wet season. |
REC210-0663 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should consider including assessment criteria in their planning schemes that address: • the prospect of isolation or hindered evacuation • the impact of isolation or hindered evacuation. |
REC210-0773 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should prioritise dam safety audits according to risk. The risk assessment should be informed by criteria including: • structure and materials used in construction • age of the dam • time since last inspection • occurrence of a flood event since last audit and the size of that flood event • population at risk if the dam were to fail • experience and capability of dam owner • dam owner compliance history • time since last audit. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0608 | 22 - Role of local Gvt | Elected representatives from all agencies involved in a flood study should be informed of recommendations made for future work, and determine, on a risk basis, whether that further work is to be completed. |
REC210-0671 | 22 - Role of local Gvt | Councils should consider providing advice to development applicants during pre-lodgement meetings, and at the time of receiving a development application, about the way in which the development will be assessed for flood risk and what flood information council will be relying on to make this assessment. |
REC210-0643 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require the impact of flood on commercial property to be minimised. |
REC210-0736 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that proper support and oversight mechanisms are put in place around both the substantive and procedural aspects of drafting flood event reports. Seqwater should consider engaging consultants with expertise in the production of reports following significant events to advise on these mechanisms. Measures to be considered should include: • ensuring appropriate systems are in place to ensure the recollections of flood engineers and other parties are recorded immediately after the event, perhaps by engaging an external party to interview the flood engineers and other parties • ensuring that a methodology for writing the report is set out clearly in advance, in writing, and that the final report includes a statement of that methodology • putting in place systems to ensure that members of senior management have sufficient understanding of both the methodology and process by which the report is prepared to allow themselves to be satisfied that these are appropriate. |
REC210-0769 | 22 - Role of local Gvt | Toowoomba Regional Council and the Department of Environment and Resource Management should continue to co-operate to assess the referable dam status of existing detention basins and any future detention basins constructed in the West Creek and East Creek catchment areas. |
REC210-0655 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should consider including assessment criteria in their planning schemes which require that works in a floodplain: • do not reduce on-site flood storage capacity • counteract any changes the works will cause to flood behaviour of all floods up to and including the acceptable defined flood event by measures taken within the subject site (for example, use of compensatory works, detention basins or other engineering mechanisms), and • do not change the flood characteristics outside the subject site in ways that result in: – loss of flood storage – loss of/changes to flow paths – acceleration or retardation of flows, or – any reduction in flood warning times elsewhere on the floodplain. |
REC210-0772 | 25 - Inquiry, audit, lessons management and after action review | Prior to each wet season, the Department of Environment and Resource Management should audit the compliance of each owner of a referable dam with the obligation to have an emergency action plan approved by the Queensland Government. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0607 | 22 - Role of local Gvt | Elected representatives from councils should be informed of the results of each flood study relevant to the council’s region, and consider the ramifications of the study for land planning and emergency management. |
REC210-0670 | 22 - Role of local Gvt | Councils should not rely on a condition requiring an evacuation plan as the sole basis for approving a development susceptible to flooding. |
REC210-0641 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in model flood planning controls, councils should include assessment criteria in their planning schemes that require community infrastructure (including the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood) to be located and designed to function effectively during and immediately after a flood of a specified level of risk. |
REC210-0726 | 25 - Inquiry, audit, lessons management and after action review | The Queensland Fire and Rescue Service should require that each region records in writing the results of its risk assessment undertaken as part of its annual review of its special operations functional plan. |
REC210-0768 | 22 - Role of local Gvt | Toowoomba Regional Council should engage external consultants to carry out failure impact assessments on the detention basins along East Creek. |
REC210-0724 | 28 - Personal responsibility | Councils should consider making available to business owners locality specific information that would assist them to develop evacuation plans for commercial premises, for example, any evacuation sub-plan created under Emergency Management Queensland’s disaster evacuation guidelines. |
REC210-0653 | 22 - Role of local Gvt | Councils (particularly Brisbane City Council) should consider including in their planning schemes more stringent standards for the design and construction of prescribed tidal work than those in the code for development applications for prescribed tidal work in the Coastal Protection and Management Regulation 2003. |
REC210-0762 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should consider commissioning an investigation into the extent of cracking below the level of the upper gallery of Somerset Dam and the impact of any such cracking on the dam’s stability and, in turn, its operation. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0605 | 22 - Role of local Gvt | As far as is practicable, councils should maintain up-to-date flood information |
REC210-0669 | 22 - Role of local Gvt | Councils should take care when imposing conditions to ensure that each condition has purpose; standardised conditions should not be included where they have no application to the development in question. |
REC210-0632 | 22 - Role of local Gvt | If the Queensland Government does not include such a code in the model flood planning controls, councils should include in their planning schemes a flood overlay code that consolidates assessment criteria relating to flood. |
REC210-0698 | 22 - Role of local Gvt | Councils should consider implementing a property buy-back program in areas that are particularly vulnerable to regular flooding, as part of a broader floodplain management strategy, where possible obtaining funding from the Natural Disaster Resilience Program for this purpose. |
REC210-0723 | 28 - Personal responsibility | Councils should support and encourage business owners to develop private flood evacuation plans by providing the following to business owners in areas known to be affected by flood: • information about the benefits of evacuation plans • contact details of relevant council and emergency service personnel for inclusion in evacuation plans. |
REC210-0651 | 22 - Role of local Gvt | When approving applications for development which involve the manufacture or storage of hazardous materials, councils should not restrict the conditions imposed to ones which are solely reliant on human intervention to remove the materials in the event of flood. |
REC210-0743 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should, in creating the new Wivenhoe and North Pine flood mitigation manuals, comprehensively consider: • the amount of discretion that is able to be exercised by the flood engineers and the senior flood engineers, and the description of the circumstances in which such discretion may be exercised • the circumstances in which it might be appropriate to release water in advance of an impending flood on the basis of forecasts from the Bureau of Meteorology • if strategies of the form of strategy W2 and W3 in Revision 7 are included in the revised manual, or any strategy defined as a ‘transition strategy’, when and how those strategies should be implemented • if the concept of ‘urban inundation’ is relevant to the operation of the dam, how it should be defined, and if the definition involves diverse concepts, how those concepts can be related back to the strategies, so that flood engineers can reach a clear understanding of their objectives and primary considerations • if the concept of ‘natural peak flow’ is relevant, how it should be defined. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1693 | 22 - Role of local Gvt | The Fire and Emergency Services Authority and local governments ensure that the ability to: |
REC209-1643 | 25 - Inquiry, audit, lessons management and after action review | An evaluation be conducted into the integration of the appropriate elements of the South Australian Country Fire Service “Crimson” networking system into Bushfires NT ICT. |
REC209-1646 | 28 - Personal responsibility | Spreading the message of enforcement of landholder’s obligations and responsibilities through active consultation and ultimately the issuing of infringement notices be adopted as a planned strategic intervention to promote the importance of compliance with the Bushfires Act. |
REC209-1645 | 14 - Incident Mgt Teams | Ensure that adequate administrative personnel are available within the incident control structure to provide administrative and knowledge management support for incident management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC208-0526 | 25 - Inquiry, audit, lessons management and after action review | That OEH’s testing procedures for determining the impact of pollution incidents incorporate additional requirements for the checking and verification of results before those results are released. |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1903 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government should commission an independent public review of disaster prevention and recovery arrangements. This should be broader than the review currently being conducted by the Attorney-General’s Department. The review should cover the Natural Disaster Relief and Recovery Arrangements, as well as the funding mechanisms for disaster mitigation, including the National Partnership Agreement on Natural Disaster Resilience. This review should: |
REC205-1902 | 25 - Inquiry, audit, lessons management and after action review | The Council of Australian Governments should commission an independent public inquiry to develop an appropriate response to managing the risks of climate change to existing settlements. The inquiry should: |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1916 | 25 - Inquiry, audit, lessons management and after action review | Local Emergency Management Committee (LEMC) processes should be reviewed to ensure that: |
REC204-1913 | 25 - Inquiry, audit, lessons management and after action review | The Department of the Attorney General consider conducting a review of the Civil Liability Act 2002 (WA) in light of the 2011 Kimberley Ultramarathon. Such a review should consider issues such as the effectiveness given to competitor waivers under the Act and the potential difficulties of establishing proceedings and enforcing a judgement against foreign‐based providers of recreational activities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0284 | 5 - Hazard reduction burns | DEC should investigate embedding an experienced forecaster in the state operations centre. |
REC203-0278 | 5 - Hazard reduction burns | Prescriptions should mandate consideration of measures to retire risk. |
REC203-0283 | 5 - Hazard reduction burns | Core ignition, particularly of red flag burns, should be informed by the 4 & 7 day forecasts (including a longer term perspective over 3 to 4 months) |
REC203-0300 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command, and not through agency chain of command. |
REC203-0277 | 5 - Hazard reduction burns | A risk-management approach is needed which considers risks both inside the prescribed burn and the risks that will need to be managed if the fire escapes. The risk assessment should be organised and in line with the four and seven day weather. |
REC203-0282 | 5 - Hazard reduction burns | The burn prescription should capture the fuel characteristics and potential rate of spread for those areas outside the burn that will likely be critical during the initial attack on any escaping fire. |
REC203-0294 | 14 - Incident Mgt Teams | Opportunities should be sought to embed other local government representatives in other areas of the IMT particularly in public information. |
REC203-0276 | 5 - Hazard reduction burns | There should be clearly established criteria for burns which are specially challenging, and these criteria need to extend beyond the intended boundaries of the prescribed burn. The criteria should be clarified and adopted as agency S OPs. |
REC203-0281 | 5 - Hazard reduction burns | Prescriptions need to be interpreted by experienced and knowledgeable personnel to ensure risk is fully understood. It is important that the background and justification for these decisions are captured at each stage and are visible to all levels in WA fire management hierarchy. |
REC203-0286 | 5 - Hazard reduction burns | Decisions taken on the basis of this risk assessment need to be captured and distributed across district and state. |
REC203-0280 | 5 - Hazard reduction burns | Contingency plans for escaping burns should be prepared in advance. |
REC203-0285 | 5 - Hazard reduction burns | A rolling risk assessment is required which captures the risks of the burn escaping and provides adequate resources. |
REC203-0279 | 5 - Hazard reduction burns | Once a burn is ignited, it needs to be the subject of continuing risk assessment and appropriate mitigation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0497 | 25 - Inquiry, audit, lessons management and after action review | The Minister for Local Government have urgent discussions with the Western Australian Local Government Association (WALGA) as to why they are not supporting the full Recommendations addressed to local government in the Keelty Report. The Minister ensure that by May 2012 WALGA and its member councils have the resources to fully implement theimplementation of the Recommendations. |
REC202-0495 | 25 - Inquiry, audit, lessons management and after action review | At the conclusion to the 2011-12 bushfire season, the Minister for Emergency Services institute a thorough review of the operations of FESA, the Police and DEC in protecting the State from bushfires and other natural disasters, with a primary focus on: · staffing levels; · equipment levels and coordination; and · training needs. The Minister report to Parliament by June 2012 on any changes that need to be made to the current departmental structures to optimise the State’s preparedness for the 2012-13 bushfire season. |
REC202-0493 | 25 - Inquiry, audit, lessons management and after action review | The Minister for Emergency Services report to Parliament every six months on the progress made in completing all of the outstanding Recommendations of the Keelty Report. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0254 | 14 - Incident Mgt Teams | FESA should continue to develop with DEC and Local Government a number of rostered pre-formed IMT‘s available throughout the fire season, regardless of predicted weather. |
REC201-0256 | 22 - Role of local Gvt | Noting existing legislative and policy arrangements, there is merit in considering options for the future management of Level 3 fires in Local Government areas. |
REC201-0253 | 14 - Incident Mgt Teams | Review the command function of the MROC for Level 3 incidents when the SOC is activated. |
REC201-0251 | 14 - Incident Mgt Teams | All responding crews and the incident command appointments should adopt a ‘Size Up‘ reporting format. |
REC201-0247 | 28 - Personal responsibility | Local residents must take a degree of shared responsibility to prepare their properties by reducing the risk of bushfire around their properties and planning for a bushfire emergency. |
REC201-0248 | 14 - Incident Mgt Teams | To provide Level 3 IC‘s (and FESA) with a level of confidence and to maintain currency across the pool of accredited IC‘s, regular exercising of IC‘s and Level 3 IMT‘s is required. |
REC201-0258 | 14 - Incident Mgt Teams | FESA should review the size of the existing pre-formed IMT to include additional Information and Planning officers and increased resourcing of scribes and management support for all Level 3 incidents. |
REC201-0255 | 14 - Incident Mgt Teams | FESA and DEC need to appoint accredited Level 3 IC‘s based on experience, competency and currency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1692 | 5 - Hazard reduction burns | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments take proactive steps to conduct their prescribed burning programs as joint exercises. This will give effect to: |
REC200-1695 | 22 - Role of local Gvt | The Western Australian Local Government Association explore the feasibility of local governments utilising aerial and satellite imagery to monitor firebreaks and fuel loads on private property. |
REC200-1732 | 25 - Inquiry, audit, lessons management and after action review | The State Government review implementation of the Special Inquiry's recommendations in two years. |
REC200-0356 | 5 - Hazard reduction burns | The State Government reaffirm its 2009 decision to approve DEC exercising greater flexibility in managing smoke within national guidelines, in order to achieve its prescribed burn program. |
REC200-0361 | 25 - Inquiry, audit, lessons management and after action review | The Fire and Emergency Services Authority convene a facilitated debriefing session between the families who remained behind to protect their properties, and the incident controllers. This session should include open discussion and explain the decisions of all parties – including how the incident controllers determined priorities, and why residents chose not follow their advice to evacuate. The learning outcomes should be promulgated across all agencies and incorporated in future level 3 incident controller training programs. |
REC200-0391 | 14 - Incident Mgt Teams | The Interagency Bushfire Management Committee develop a consistent program of education, training (including media), testing and review of Level 3 Incident Controllers. This should include provision for a formal review of the performance of individual Level 3 Incident Controllers after every incident. |
REC200-0367 | 22 - Role of local Gvt | Main Roads Western Australia undertake more frequent examinations of its bridges located in areas prone to bushfire and ensure that the risk posed to loss of infrastructure in a fire is understood by local authorities. |
REC200-1712 | 10 - Infrastructure | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-1691 | 5 - Hazard reduction burns | The State Government consider resourcing the Department of Environment and Conservation and local governments to develop and administer a comprehensive prescribed burning program in Perth‟s urban/rural interface to compliment DEC's existing landscape-scale program. |
REC200-1701 | 25 - Inquiry, audit, lessons management and after action review | The Fire and Emergency Services Authority convene a facilitated debriefing session between the families who remained behind to protect their properties, and the incident controllers. |
REC200-0351 | 5 - Hazard reduction burns | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments take proactive steps to conduct their prescribed burning programs as joint exercises. This will give effect to: Reducing fuel load Improving inter-operability A mutual understanding of the fire fighting techniques of each agency. |
REC200-0366 | 14 - Incident Mgt Teams | The Fire and Emergency Services Authority and the Department of Environment and Conservation ensure that their Incident Controllers identify critical infrastructure as part of their initial assessment and preparation of Incident Action Plans when attending major incidents. |
REC200-0368 | 20 - Role of police | The Fire and Emergency Services Authority and the Western Australian Police ensure they receive all necessary legal clarification in relation to Bushfire Responsibilities of Police Officers – Powers Used in Assisting Fire Authorities in Responding to Bushfires, to be promulgated across FESA and WAPOL. |
REC200-0354 | 22 - Role of local Gvt | Local governments consider increasing the number of green waste collections carried out each year to encourage a more proactive approach to property (and vegetation) maintenance by residents. |
REC200-1683 | 22 - Role of local Gvt | Local Government recognise the work of the Gas Technical Regulatory Council and ensure any amendments to the Australian Standard are enforced. |
REC200-0350 | 5 - Hazard reduction burns | The State Government consider resourcing the Department of Environment and Conservation and local governments to develop and administer a comprehensive prescribed burning program in Perth’s urban/rural interface to compliment DEC’s existing landscape-scale program. |
REC200-0353 | 22 - Role of local Gvt | The State Government give its full support to the Western Australian Local Government Association’s Send to Solve initiative. |
REC200-1729 | 22 - Role of local Gvt | The Fire and Emergency Services Authority and local governments ensure that Community Emergency Service Managers are physically based in local government. |
REC200-0345 | 22 - Role of local Gvt | Local governments continue to include information on bushfire risk and preparedness with rates notices. |
REC200-0392 | 25 - Inquiry, audit, lessons management and after action review | The State Government review implementation of the Special Inquiry’s Recommendations in two years. |
REC200-1706 | 14 - Incident Mgt Teams | The Fire and Emergency Services Authority and the Department of Environment and Conservation ensure that their Incident Controllers identify critical infrastructure as part of their initial assessment and preparation of Incident Action Plans when attending major incidents. |
REC200-1715 | 22 - Role of local Gvt | Local governments institute a comprehensive program to assess fuel loads and bushfire preparedness on private properties. The program should give reference to the creation and maintenance of a Building Protection Zone, in line with FESA guidelines. |
REC200-0342 | 22 - Role of local Gvt | Local Government recognise the work of the Gas Technical Regulatory Council and ensure any amendments to the Australian Standard are enforced. Local Government provide information to residents on any changes to the Australian Standard relating to tethering gas tanks and encourage property owners to take action to comply with the Standard. |
REC200-0384 | 25 - Inquiry, audit, lessons management and after action review | Emergency Management Western Australia develop mechanisms to calculate the estimated total cost of a fire to the community. |
REC200-0375 | 22 - Role of local Gvt | Local governments institute a comprehensive program to assess fuel loads and bushfire preparedness on private properties. The program should give reference to the creation and maintenance of a Building Protection Zone, in line with FESA guidelines. This program should be implemented and managed under the Bush Fires Act 1954 in a manner similar to the fire break inspection program. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0445 | 25 - Inquiry, audit, lessons management and after action review | the state develop and implement operational performance standards for each state agency involved in emergency management response and recovery and that: • each agency be assessed by the Emergency Services Commissioner periodically against these performance standards for both capability and capacity; and • where performance against these standards for either capability or capacity cannot be demonstrated by any agency – appropriate advice is communicated to the relevant Minister, departmental/agency head and State Emergency Response Coordinator; and – an action plan is developed and implemented to address the relevant capability or capacity deficiency in both the short and longer term. |
REC199-0453 | 20 - Role of police | Victoria Police revise coordinator arrangements to ensure: • a coordinator presence is maintained at the place where incident control is being exercised • effective control is established and is maintained until the response phase has concluded • key control roles may be performed by personnel from agencies other than the designated control agency • that the timely compilation and distribution of an appropriate Incident Action Plan is recognised as a fundamental component of establishing effective control • those performing the coordinator role at an Incident Control Centre be suitably trained, skilled and experienced in emergency management and where possible possess a degree of local knowledge of the relevant area; and • that the revised coordinator arrangements are reflected within the State Emergency Response Plan |
REC199-0428 | 25 - Inquiry, audit, lessons management and after action review | the state clarify which agency is responsible for collecting post-flood extent and related data. This should include: • the development of guidelines to ensure consistent standards are applied to post-flood data collection; and • an appropriate process to ensure funding availability for such activities. |
REC199-0407 | 25 - Inquiry, audit, lessons management and after action review | the state: • undertake a strategic review to identify areas at risk from flash or riverine flooding. Shortcomings in the flood gauging networks identified in the review should then be the focus of remedial action • seek to address as a priority any notable gaps in the total flood warning system as apparent in the 2010–11 floods (including south west Victoria, Wimmera and north central region) by enhancing mapping, gauging and education programs; and • seek a commitment from the Bureau of Meteorology to ensure any new gauges installed are utilised to enhance flood prediction capability and coverage. |
REC199-0401 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to establish an effective audit regime of the total flood warning system. |
REC199-0486 | 22 - Role of local Gvt | the state, following the completion of the Municipal Association of Victoria Improving Emergency Management in Local Government program, work with municipalities to revise the role and responsibilities of local government in emergency management. The issue of capability and capacity of each local government should be addressed in all related emergency management arrangements. |
REC199-0482 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to develop and undertake the regular audit of emergency management plans at all levels. |
REC199-0468 | 22 - Role of local Gvt | municipal councils undertake a risk assessment of caravan parks and decide if any should be included in the list of facilities where vulnerable people may be located. |
REC199-0450 | 25 - Inquiry, audit, lessons management and after action review | the state ensure that appropriate record management processes are developed and implemented and that these processes also provide record accountability for multi-agency operations. Agency processes should be standardised to the fullest extent possible |
REC199-0413 | 14 - Incident Mgt Teams | the state clarify the role of intelligence cell staff (for example, hydrologists and/or Catchment Management Authority) who are utilised in Incident Control Centres during flood events |
Rec-ID | Code | Recommendation |
---|---|---|
REC198-2905 | 14 - Incident Mgt Teams | The Fire Services Commissioner ensures that there is a single standard for the tabards worn by the IMT on the fireground and in control centres to ensure consistency and aid interoperability. |
REC198-2902 | 14 - Incident Mgt Teams | The Fire Services Commissioner clarifies the role of regional controller for major fires and incidents other than bushfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC197-1733 | 25 - Inquiry, audit, lessons management and after action review | That a review of the Country Fire Authority Act 1958 and the Country Fire Authority Regulations 2004 be undertaken. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0315 | 14 - Incident Mgt Teams | The Fire Services, as part of the regular review of Incident Management Teams – Readiness Arrangements, reassess current resource sustainability and identify opportunities for a more flexible application. |
REC195-0323 | 14 - Incident Mgt Teams | Incident Controllers ensure that Emergency Management Teams consider, provide advice, and manage the broader consequences of actions, such as reopening roads, the resumption of public transport and school buses, and the welfare of those impacted by traffic management points. |
REC195-0336 | 20 - Role of police | Victoria Police, under the auspice of the Regional Emergency Response Plan, lead a task force to ensure that the Princes Highway is treated as an asset of significance and an appropriate risk-based approach is adopted to minimise the impact of fire. This approach is to be integrated into regional and municipal fire management plan |
REC195-0317 | 14 - Incident Mgt Teams | The Fire Services ensure that an incident action plan (summary) is developed in accordance with the Standard Operating Procedure J3.03. |
REC195-0335 | 10 - Infrastructure | Energy Safe Victoria ensures that the standards for vegetation clearance around power lines consider the impact of fire on electrical infrastructure and the risk of loss of electricity supply to the community. |
REC195-0316 | 14 - Incident Mgt Teams | The Fire Services continue to develop fire behaviour analysis and predictive science capability by ensuring the Fire Behaviour Analysis Team is appropriately resourced with accredited staff and available to provide services to the IMT. |
Rec-ID | Code | Recommendation |
---|---|---|
REC193-0226 | 22 - Role of local Gvt | Local government councils should: strongly encourage owners to make improvements to construction or increase buffers in order to meet minimum safety standards implement programs to audit impacted properties and issue abatement notices where necessary monitor and maintain their reserves to ensure that adequate buffers to neighbouring buildings exist. |
REC193-0225 | 22 - Role of local Gvt | Local government councils should move promptly to: adopt the Tasmania Fire Service Guidelines for Development in Bushfire Prone Areas of Tasmania give effect to the Department of Primary Industries, Parks, Water and Environment Neighbouring Developments and Fire Management Policy. |
REC193-0222 | 22 - Role of local Gvt | The Local Government Association of Tasmania advocate, coordinate and support local councils’ input of bushfire risk assets data into the Bushfire Risk Assessment Model. |
REC193-0227 | 5 - Hazard reduction burns | Local government councils implement a zoning approach to fuel management as recommended by COAG 2004. |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0114 | 14 - Incident Mgt Teams | Higher level DEC guidance to Level 3 Incident Controllers could be improved by introducing a more explicit and robust process of questioning, engagement, monitoring and oversight of Level 3 Incident Controllers. |
REC183-0113 | 14 - Incident Mgt Teams | A summary Incident Action Plan could allow the Incident Controller to more quickly appreciate the situation and articulate a plan early in an incident. |
REC183-0112 | 14 - Incident Mgt Teams | DEC’s incident management capability could be enhanced by: – Appointing a Deputy Incident Controller for every Level 3 IMT. – Establishing a fast response “short” IMT capability for each Level 3 IMT. – Establish clear triggers to initiate sending in a “short” IMT to a fire. – Including FESA officers in pre-formed Level 3 IMT’s. – Establishing additional pre-formed Level 3 IMT’s with FESA. – Where appropriate, appointing a local Bush Fire Brigade officer as Deputy Operations Officer. |
REC183-0111 | 14 - Incident Mgt Teams | Conducting a pre-fire season exercise for each Pre-Formed Incident Management Team could be used to “re-accrediting” each team on an annual basis. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0131 | 14 - Incident Mgt Teams | FESA establishes a dedicated intelligence function in Incident Management Teams for major bushfires and ensure this function is appropriately supported with threat based tools and systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
REC181-0195 | 22 - Role of local Gvt | The State press municipal councils—in particular, Murrindindi Shire Council—to urgently adopt a bushfire policy in their Local Planning Policy Framework and incorporate bushfire risk management in their planning policies and strategies for rebuilding communities such as Marysville, Kinglake and others affected by the January–February 2009 fires. |
REC181-0160 | 20 - Role of police | The State clarify whether, during major fires, Victoria Police should discharge its coordination functions from the State Emergency Response Coordination Centre or from the State Control Centre. |
REC181-0206 | 5 - Hazard reduction burns | The State fund and commit to implementing a long-term program of prescribed burning based on an annual rolling target of 5 per cent minimum of public land. |
REC181-0167 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment establish before the 2010–11 fire season: ■ a uniform, objective and transparent process based on the current DSE approach for the accreditation of level 3 Incident Controllers; ■ a performance review system for level 3 Incident Controllers; ■ a traineeship program for progression from level 2 to level 3 incident management team positions. |
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
REC181-0181 | 22 - Role of local Gvt | Municipal councils include in their municipal fire prevention plans for areas of high bushfire risk provision for the identification of hazard trees and for notifying the responsible entities with a view to having the situation redressed. |
REC181-0165 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment: ■ amend their procedures to require that an incident action plan summary be completed within the first four hours of an incident being reported and be provided to the State Control Centre and, where established, to the relevant Area of Operations Control Centre; ■ adopt DSE’s incident action plan summary as the template to be used by all incident management teams and ensure that the template is included in the online IMT Tool Box; ■ provide regular training to IMT staff, highlighting the importance of information and reinforcing the support available from specialists within the State Control Centre. |
REC181-0217 | 25 - Inquiry, audit, lessons management and after action review | The State consider the development of legislation for the conduct of inquiries in Victoria —in particular, the conduct of royal commissions. |
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
REC181-0159 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment prescribe and audit the minimum number and nature of level 3 joint training exercises in which incident management team staff (including volunteers) are required to participate. |
REC181-0216 | 25 - Inquiry, audit, lessons management and after action review | The State appoint an independent monitor or the Victorian Auditor-General to assess progress with implementing the Commission’s recommendations and report to the Parliament and the people of Victoria by 31 July 2012. |
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
REC181-0185 | 20 - Role of police | Victoria Police continue to pursue a coordinated statewide approach to arson prevention and regularly review its approach to ensure that it contains the following elements: ■ high-level commitment from senior police; ■ a research program aimed at refining arson prevention and detection strategies; ■ centralised coordination that includes comprehensive training, periodic evaluation of arson prevention strategies and programs, and promotion of best-practice prevention approaches; ■ a requirement that all fire-prone police service areas have arson prevention plans and programs, according to their level of risk. |
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
REC181-0202 | 22 - Role of local Gvt | The State develop and implement, in consultation with local government, a mechanism for sign-off by municipal councils of any permit conditions imposed under the Bushfire-prone Overlay and the regular assessment of landowners’ compliance with conditions. |
REC181-0207 | 5 - Hazard reduction burns | The Department of Sustainability and Environment report annually on prescribed burning outcomes in a manner that meets public accountability objectives, including publishing details of targets, area burnt, funds expended on the program, and impacts on biodiversity. |
REC181-0168 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment amend their procedures to require that a suitably experienced, qualified and competent person be appointed as Incident Controller, regardless of the control agency for the fire. |
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
REC181-0153 | 22 - Role of local Gvt | The State establish mechanisms for helping municipal councils to undertake local planning that tailors bushfire safety options to the needs of individual communities. In doing this planning, councils should: ■ urgently develop for communities at risk of bushfire local plans that contain contingency options such as evacuation and shelter; ■ document in municipal emergency management plans and other relevant plans facilities where vulnerable people are likely to be situated—for example, aged care facilities, hospitals, schools and child care centres; ■ compile and maintain a list of vulnerable residents who need tailored advice of a recommendation to evacuate and provide this list to local police and anyone else with pre-arranged responsibility for helping vulnerable residents evacuate. |
Rec-ID | Code | Recommendation |
---|---|---|
REC180-2969 | 22 - Role of local Gvt | Councils should strengthen governance arrangements for business continuity by: |
REC180-2973 | 22 - Role of local Gvt | Local Government Victoria should, further to its work on strengthening the oversight role of audit committees, assist councils to develop good practice approaches to implementing, overseeing and continuously improving business continuity management. |
REC180-2972 | 22 - Role of local Gvt | Councils should strengthen their continuous improvement frameworks by: |
REC180-2971 | 22 - Role of local Gvt | Councils should improve the structure, format and content of their business continuity plans to provide greater clarity on roles and responsibilities for emergencies, more specificity on continuity and recovery responses, and better integration with other council disaster recovery and emergency plans. |
REC180-2970 | 22 - Role of local Gvt | Councils should improve assessments of business continuity risks by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3344 | 25 - Inquiry, audit, lessons management and after action review | There should be a review to determine whether it is appropriate to introduce a rigorous civil penalty regime and/or substantially increase some or all of the penalties that can be imposed for breaches of legislative requirements relating to well integrity and safety. |
REC144-3387 | 25 - Inquiry, audit, lessons management and after action review | In order that the ACT public can be reassured about the project management and financial planning in relation to the Fairbairn site as a proposed centralised accommodation facility for emergency services, the Auditor-General undertake a review of the project from a financial probity and project management perspective. |
REC177-3378 | 25 - Inquiry, audit, lessons management and after action review | In view of the numerous well integrity problems in all of the Montara Oilfield wells, the Minister should commission a detailed audit of all the other offshore wells operated by PTTEPAA to determine whether they too may suffer from well integrity problems. |
REC177-3374 | 25 - Inquiry, audit, lessons management and after action review | The Minister should, as the JA for the offshore area of the Territory of Ashmore and Cartier Islands, undertake a review of PTTEPAA’s permit and licence to operate at the Montara Oilfield. |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0139 | 10 - Infrastructure | Subject to the findings of the Productivity Commission, the Commonwealth examine options for the funding of replacement of power infrastructure that presents an unacceptable bushfire risk. |
REC176-0147 | 5 - Hazard reduction burns | The Commonwealth encourages further research into prescribed burning and its effectiveness and into alternative bushfire mitigation approaches through improved bushfire risk understanding at the asset level. |
REC176-0138 | 10 - Infrastructure | The Productivity Commission undertake an examination of bushfire risk from ageing power infrastructure, including an assessment of replacement costs and likely suppression costs from bushfires caused by defective infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC174-2985 | 25 - Inquiry, audit, lessons management and after action review | To provide adequate assurance on the validity of claims paid for disaster recovery assistance, the ANAO recommends that Centrelink: |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0007 | 14 - Incident Mgt Teams | A formal OAMG meeting should be convened as early as possible for incidents with the potential to be Level 3 incidents. At the very least early advice to potential OAMG members should be made on days that exhibit extreme fire weather and other high ignition risk factors that a meeting is likely to be convened. The initial OAMG should include all OAMG representatives identified by LEMAC and DEMAC for each area to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0006 | 14 - Incident Mgt Teams | Prior to the bushfire season, potential IMG members, many of whom are members of the Local Emergency Management Committee (LEMC) should be made aware of, and possibly exercise, their role as an IMG member. |
REC172-0035 | 14 - Incident Mgt Teams | At Level 3 incidents the Information Services Unit should be adequately resourced with information technology and at least 6 persons, all of whom are very experienced and capable in dealing with the information demands of a Level 3 incident. |
REC172-0005 | 14 - Incident Mgt Teams | Potential IMG membership should be identified in local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA. |
REC172-0010 | 14 - Incident Mgt Teams | The responsibilities and obligations for an OAM and OAMG (when established) needs to clarified and codified in Westplan Bushfire with regard to • Provision of information to participating organisations about the progress and potential of an incident; • Dealing with information disseminated to the public; and • Sourcing, coordinating and prioritising resources required by incidents within the Operations Area. There is lack of clarity in current arrangements concerning the role of the agency undertaking control operations e.g. DEC or a local govt and the transfer of these responsibilities to an OAMG when established. |
REC172-0004 | 14 - Incident Mgt Teams | A formal IMG meeting should be convened as early as possible at initiating incidents with potential. At the very least early advice to potential IMG members should be made that a meeting is likely to be convened. The initial IMG should include all IMG representatives to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0009 | 14 - Incident Mgt Teams | When an OAMG is established, a formal declaration of its establishment needs to be transmitted to all organisation/agencies involved. The declaration should clearly establish the reporting arrangements for Incident Controllers to the OAM as described in Westplan Bushfire. |
REC172-0008 | 14 - Incident Mgt Teams | Potential OAMG membership should be identified in DEMC protocols and local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA.] |
Rec-ID | Code | Recommendation |
---|---|---|
REC171-0067 | 14 - Incident Mgt Teams | That to the extent it has not already done so, DEC take action to ensure that in future cases relevant weather forecast information, particularly information as to significant wind changes, is promptly transmitted through the Incident Management Team and made available to persons with field operation responsibility. |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0055 | 22 - Role of local Gvt | SEMC and EM WA should: monitor and take action to ensure local plans are in place and cover areas where the hazard could occur |
REC170-0062 | 25 - Inquiry, audit, lessons management and after action review | Agencies should: annually assess their capability to respond to emergencies and take measures to address any shortfalls |
REC170-0054 | 22 - Role of local Gvt | SEMC and EM WA should: work with local government to ensure up-to-date, comprehensive local arrangements are in place |
Rec-ID | Code | Recommendation |
---|---|---|
REC166-3009 | 25 - Inquiry, audit, lessons management and after action review | That the Tasmania Fire Service conduct an audit of all shopping centres to ensure that there exists within those centres adequate fire protection and evacuation systems. |
REC166-3006 | 20 - Role of police | That the recommendations contained in the Police Operational Debrief Report of 22 October 2007 to 7 November 2007, submitted to the Coroner, be further considered by the Tasmania Police for adoption where considered appropriate by Tasmania Police. |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0085 | 20 - Role of police | The Commissioner of Police, through a dedicated Assistant Commissioner (supported by a cohort of Assistant Commissioners to ensure adequate coverage), be assigned responsibility for overall control of each natural Disaster Management event in Queensland as the preferred arrangement. |
Rec-ID | Code | Recommendation |
---|---|---|
REC164-0073 | 25 - Inquiry, audit, lessons management and after action review | SERCon consider that the proposed State Recovery Committee provide an interim report to government on these and |
Rec-ID | Code | Recommendation |
---|---|---|
REC161-3030 | 25 - Inquiry, audit, lessons management and after action review | That National Offshore Petroleum Safety Authority review the risk assessment of pipelines. National Offshore Petroleum Safety Authority should focus, in particular, on the efficacy of anti-corrosion systems, and recognise potential interference effects and MAE escalation risks associated with adjacent pipelines and unlicenced pipes even if they fall outside its direct regulatory responsibilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC159-3058 | 25 - Inquiry, audit, lessons management and after action review | ACTAS should improve patient care processes by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3452 | 25 - Inquiry, audit, lessons management and after action review | That the nominated marine safety authority undertakes a further assessment to determine the recommendations from this Review that may also be applicable to State waters outside commercial port waters. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
REC156-3492 | 22 - Role of local Gvt | The review of the municipal emergency management planning guidelines being led by the Office of the Emergency Services Commissioner clarify local governments’ role in community information about emergencies. |
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3516 | 28 - Personal responsibility | All Victorians should: |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3465 | 5 - Hazard reduction burns | That in order to enhance the protection of community and ecological assets, the Department of Sustainability and Environment increase its annual prescribed burning target from 130,000 hectares to 385,000 hectares. This should be treated as a rolling target, with any shortfalls to be made up in subsequent years. |
REC155-3464 | 5 - Hazard reduction burns | That the Department of Sustainability and Environment implement remote sensing imagery as a routine part of its pre-burn and post-burn assessment process for prescribed burning. Maps of every prescribed burn should be produced in a similar format to those used in Western Australia, indicating the boundary of each burn and the varying fire intensities achieved within the burn area. The boundaries of all Fuel Management Zones within each burn should also be indicated. |
REC155-3466 | 25 - Inquiry, audit, lessons management and after action review | A comprehensive review of the effectiveness of the increased prescribed burning target in meeting ecological and bushfire suppression needs should be conducted every three years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1799 | 14 - Incident Mgt Teams | That the South Australian Country Fire Service establish preplanned Level 2 Incident Management Teams in each Region for deployment to Level 2 incidents. |
REC153-1780 | 22 - Role of local Gvt | That the Minister for Local Government cause rural councils to appoint an Officer whose duties consist entirely of bushfire prevention, such Officer being required to become a trained, operative member of the South Australian Country Fire Service during the currency of his or her appointment. |
REC153-1791 | 14 - Incident Mgt Teams | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service consider the creation of a position within an Incident Management Team of a Landowner Liaison Officer the duties and responsibilities of whom is to establish contact with and liaise with the owner and/or occupiers of rural land on which a fire is situated. |
REC153-1777 | 5 - Hazard reduction burns | That the Minister for Emergency Services and the Minister for Local Government consider the enactment of legislation that would empower Local Government to require the owners or occupiers of rural land to create fire breaks on the land of a kind that Local Government may determine and/or to require the removal of flammable materials from the land, as measures for preventing the outbreak of a bushfire, or for preventing the spread or extension of a bushfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3145 | 25 - Inquiry, audit, lessons management and after action review | NOPSA should consider an audit regime that targets Greenfields operations at commencement of operations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3175 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia to review, at least once every two years, the operating procedures to ensure that they adequately identify and manage the risk of entry and spread of equine influenza associated with the importation of horses into Australia. The outcome of each such review should be the subject of a written report and recommendations to the person responsible for the importation of horses and the Executive Director of AQIS. A determination should then be made as to whether any, and if so what, changes should be made to the operating procedures. |
REC148-3170 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia to conduct within six months, an inspection and review of the process of horse importation from the time horses arrive in Australia until the completion of their post-arrival quarantine in order to: |
REC148-3167 | 25 - Inquiry, audit, lessons management and after action review | That the facilities at Eastern Creek and Spotswood Quarantine Stations be reviewed by AQIS in consultation with experts in biosecurity and interested parties including state and territory governments, import agents, veterinarians, farriers, operators of private quarantine stations, and representatives of horse owners, horse racing organisations and equestrian organisations. There should in any event be constructed without delay, an adequate supply of hygienic, modern showering facilities and places of entry and exit to the stations and the horse sections of them that can be supervised and monitored continually. There should also be provided at those stations as soon as is practicable suitable means of electronic surveillance, including closed-circuit television; a secure place to store chemicals, drugs, instruments and equipment for use by people attending the quarantined horses, and a set of horse stalls and yards separate from the main stalls and yards to enable isolation of horses suffering from contagious or infectious diseases. These reviews should also consider the desirability of separate areas in quarantine stations to hold horses forming part of a single quarantine intake but that have been imported from different regions or have undergone pre-export quarantine in different places. The reviews should be carried out without delay, and the two quarantine stations should be upgraded in accordance with the recommendations of the reviews. |
REC148-3154 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia or another qualified body to inspect and review the activities and events that occur from the time horses enter pre-export quarantine until the time they arrive at an airport in Australia, in order to identify any biosecurity risks and recommend any necessary changes to import conditions or other requirements. This inspection and review shall be performed without delay for each country or region from which horses are imported to Australia, and it should take account of my other recommendations and comments in this report. |
REC148-3182 | 25 - Inquiry, audit, lessons management and after action review | That Biosecurity Australia review that formal import risk analysis at least once every two years to take into account any relevant developments in scientific knowledge—specifically testing methods, vaccines, vaccination procedures and other matters that affect biosecurity. Reports on the reviews should be provided to the officer responsible for the importation of horses and should contain recommendations for any necessary changes to policies for importation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC146-3193 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the Australian National Audit Office audit CASA's implementation and administration of its Safety Management Systems approach. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3231 | 22 - Role of local Gvt | The Committee recommends that the Australian Government request that the Centre for Excellence for Local Government ensure a particular focus on capacity building for coastal local councils. Capacity building should focus on addressing issues relating to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC144-3379 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that a thorough review be undertaken of the communications and coordination between the separate agencies which make up the Emergency Services Agency, to assess the extent to which cultural factors are detrimental to the effective operation of the ESA. |
Rec-ID | Code | Recommendation |
---|---|---|
REC139-3546 | 22 - Role of local Gvt | Local Government to be maintained as an important component of bushfire management in South Australia because of the link with the community. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3598 | 25 - Inquiry, audit, lessons management and after action review | That the Department of Primary Industries incorporates reviews of plans and operating procedures as a result of emergency incidents and exercises and ensures that there is adequate commitment from all participants in the review process. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1947 | 25 - Inquiry, audit, lessons management and after action review | That the ACT Government commission a review of coroners’ jurisdiction in order to determine whether that jurisdiction ought to be limited or expanded and, if so, to what extend |
REC126-1953 | 14 - Incident Mgt Teams | That appointments of personnel to functional positions within the incident management team be based solely on competence and experience and be made by the Chief of the ACT Rural Fire Service or, in the absence of that officer, the Deputy Chief of the ACT Rural Fire Service |
REC126-1975 | 5 - Hazard reduction burns | That prescribed burning operations be conducted according to agreed standard burning prescriptions |
REC126-1973 | 5 - Hazard reduction burns | If it is not part of the proposed version 2 of the Strategic Bushfire Management Plan, that the plan be revised to provide for a fuel-reduction burning regime in the ‘Land Management Zone’ that is equivalent to that contemplated for the corridors designated as the ‘Landscape Division Zone’ and that the regime involve burning areas in rotation to achieve an appropriately varying fire age spectrum across the entire landscape |
REC126-2011 | 25 - Inquiry, audit, lessons management and after action review | That the taskforce review the recommendations of the seven reviews of the Emergency Services Bureau carried out before the McLeod inquiry and ensure implementation of any of those recommendations that remain relevant but have not been implemented |
REC126-1972 | 5 - Hazard reduction burns | That clarification be provided and information be made public in connection with the hazard reduction proposed under the Strategic Bushfire Management Plan for the area designated ‘Land Management Zone’, which appears to cover about 70 per cent of the ACT landscape and might be excluded from fuel-reduction burning |
REC126-2010 | 25 - Inquiry, audit, lessons management and after action review | That the taskforce review the extent to which the recommendations in the McLeod report have been implemented in order to ensure implementation of those not yet implemented |
REC126-1971 | 5 - Hazard reduction burns | That a hazard-reduction program be introduced, involving regular and strategic burning in all areas of the ACT – including the catchment areas – with a view to having fuel-reduced areas in a pattern across the landscape, excluding only small areas of particular ecological or conservation importance |
REC126-1952 | 25 - Inquiry, audit, lessons management and after action review | That regular periodic reviews be undertaken of changes made to the operational and management arrangements for dealing with wildfires and other emergencies in the ACT, to ensure that those arrangements continue to comply with the Australian Inter-Agency Incident Management System Incident Control System |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3898 | 25 - Inquiry, audit, lessons management and after action review | That agencies develop a detailed improvement plan and commit resources to its implementation. |
REC125-3894 | 22 - Role of local Gvt | That councils develop flood risk management practices consistent with best practice risk management, and that these incorporate: |
REC125-3901 | 22 - Role of local Gvt | That councils formulate, track and report on measures that show their performance in managing drainage assets. |
REC125-3899 | 22 - Role of local Gvt | That councils implement a condition assessment and monitoring program conforming to best practice principles. |
REC125-3896 | 22 - Role of local Gvt | That councils plan for, and implement, formal consultation arrangements with stakeholders to set drainage goals and objectives, and desired service levels. |
Rec-ID | Code | Recommendation |
---|---|---|
REC124-3885 | 5 - Hazard reduction burns | Align policies and processes, within the year round 365 day focus on fire management, to provide consistency in the approach to fire regardless of its origins,- that is fuel reduction burning, regeneration and ecological burning or unplanned fire; |
REC124-3884 | 5 - Hazard reduction burns | Develop new prescriptions for prescribed burning to accommodate local conditions in those areas where standard prescriptions are assessed to be inappropriate: |
Rec-ID | Code | Recommendation |
---|---|---|
REC123-3877 | 25 - Inquiry, audit, lessons management and after action review | All agencies review formal and informal incident notification processes to ensure they support the earliest possible reporting of emergencies to all stakeholders involved in the Airport Emergency Plan and in so doing, ensure early access to specialist advice and support. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3693 | 25 - Inquiry, audit, lessons management and after action review | ITSRR should ensure that, as a condition of accreditation, each of these recommendations is carried into effect and should audit against them to enforce compliance. |
REC121-3666 | 14 - Incident Mgt Teams | The rail commander should have complete authority to direct and control any rail employees attending the site of a rail accident, in accordance with directions given or arrangements put in place by the site controller, until the rescue phase of the emergency response to the rail accident has been completed. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3757 | 25 - Inquiry, audit, lessons management and after action review | RailCorp should conduct internal and external safety audits to evaluate the adequacy of its safety management system and to ensure that any risk control measures are effective. |
REC121-3691 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should audit the RMC to ensure communications protocols are being followed. The sanction for non-compliance with communications protocols should be identical to that in the aviation industry and involve immediate removal from duty. Any RailCorp employee not following communications protocols should be required to undertake further training. If, following return to duties after such training, the officer continues to fail to comply with communications protocols, that officer is not to be employed in communications related work. |
REC121-3665 | 14 - Incident Mgt Teams | The role of the rail commander should be to provide support and assistance to the site controller and emergency services personnel until the rescue phase of the emergency response to any rail accident is completed. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3664 | 20 - Role of police | The location of the command post for site control at the scene of any rail accident should be identified by NSW Police by a distinctive flashing light. |
REC121-3753 | 25 - Inquiry, audit, lessons management and after action review | The RailCorp Board should establish independent external safety auditing processes to regularly audit and report to the Board on the implementation of an integrated safety management system by RailCorp and on safety performance generally. |
REC121-3663 | 14 - Incident Mgt Teams | The incident command system should clearly identify the roles of the rail commander, site controller, police commander and commanders of the other emergency services, and the way in which each is to work together during the recovery phase of any rail accident. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3726 | 25 - Inquiry, audit, lessons management and after action review | The OTSI should continue to conduct rail accident investigations on behalf of ITSRR and report directly to the Chief Executive of ITSRR. |
REC121-3768 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR, when considering a re-application for accreditation, should conduct a field audit of the organisation to ensure that it is carrying on its activities in accordance with the basis upon which it seeks accreditation. |
REC121-3652 | 14 - Incident Mgt Teams | A designated staff member at the RMC should act as the rail emergency management co-ordinator. He or she should be the sole point of contact at the RMC with other rail personnel involved in the rail accident and emergency services personnel during the rescue phase of the emergency response. |
REC121-3713 | 25 - Inquiry, audit, lessons management and after action review | Recommendations one to seven of the final report of the Special Commission of Inquiry into the Glenbrook Rail Accident should be fully implemented, save that the random auditing referred to in recommendations five and seven should be carried out by ITSRR. |
REC121-3676 | 14 - Incident Mgt Teams | A direct line of communication should be established between the RMC and Emergency Services Operations Control Centre by a “tie line” or otherwise, so as to ensure that in the case of a serious rail accident there is an open line of communication between the officer in charge of the management of the incident at the RMC and the various emergency response services. |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3704 | 28 - Personal responsibility | RailCorp should continue its system of voluntary self-identification and rehabilitation of employees with alcohol or drug related problems. |
REC121-3765 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct field audits to satisfy itself that all accredited rail organisations conduct their activities in accordance with the safety management system on the basis of which each was accredited. |
REC121-3694 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct random audits of accredited rail organisations for compliance with communications protocols. |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3758 | 25 - Inquiry, audit, lessons management and after action review | Following completion of any external audit, a corrective action plan to remedy any identified safety deficiencies should be developed by RailCorp, implemented and followed up within the business groups affected, to ensure appropriate and timely completion of the action plan, by a formal examination of the effectiveness of the controls put in place. Senior management personnel should certify that the corrective action plan has been implemented and is effective. Senior management personnel should be accountable for any such certification. |
Rec-ID | Code | Recommendation |
---|---|---|
REC119-3649 | 25 - Inquiry, audit, lessons management and after action review | It is recommended that the Board: |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2107 | 10 - Infrastructure | The Working Group recommends that State/Territory emergency management plans should explicitly take the need for rapid assessment of damaged physical infrastructure into account. The importance of rapid physical infrastructure assessment in ensuring the supply of utilities including sewerage and drainage, electricity, water and gas to residential structures and other types should be recognised and considered. |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3902 | 14 - Incident Mgt Teams | Government should: establish a State-wide command structure across volunteer Bush Fire Brigades for fighting major bushfires, to more effectively manage the coordination of personnel and resources |
REC113-3906 | 10 - Infrastructure | Firefighting organisations should: resolve existing telecommunication problems and work with other emergency service organisations to establish compatible telecommunications systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3932 | 25 - Inquiry, audit, lessons management and after action review | That DPI conducts and documents debriefs after all incursions, and adopts any improvements that are identified through debriefs. |
REC112-3922 | 25 - Inquiry, audit, lessons management and after action review | That DPI maintains ISO 9000 accreditation for at least one laboratory and seeks NATA accreditation for key diagnostic tests. This should be done in combination with Plant Health Australia’s laboratory accreditation project. |
REC112-3919 | 25 - Inquiry, audit, lessons management and after action review | That the model for state funding be reviewed to ensure that DPI can confidently build and maintain a core level of diagnostic expertise and research capability. |
REC112-3912 | 25 - Inquiry, audit, lessons management and after action review | That DPI, as part of the development of the Victorian plant biosecurity strategy, undertake a strategic review of its plant health planning framework so that: • corporate and business unit plans at all levels of the department align to each other and to government policy so that staff have a coherent frame of reference to guide their work • performance indicators are developed, used, reported against and evaluated regularly • all plans (including service agreements with other parts of DPI) are communicated to staff and implemented in their day-to-day activities and responsibilities. |
REC112-3907 | 25 - Inquiry, audit, lessons management and after action review | That Department of Primary Industries (DPI), in partnership with the Department of Sustainability and Environment, reviews all legislation relating to plant biosecurity with a view to streamlining the legislative framework. |
Rec-ID | Code | Recommendation |
---|---|---|
REC111-3939 | 25 - Inquiry, audit, lessons management and after action review | It is recommended that the State Disaster Management Group and the Department of Emergency Services review the current disaster district boundary framework and its relevance to the regional boundaries established by other public sector lead entities to ensure that resources within the Disaster Management System are economically, efficiently and effectively allocated across Queensland. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2304 | 22 - Role of local Gvt | That Municipal Emergency Resource Officers develop registers of volunteers willing and available to provide assistance and support during the response to, and recovery from, emergency incidents. |
REC104-2271 | 14 - Incident Mgt Teams | That DSE and CFA ensure that agreed strategy and tactics, and the rationale, be communicated to personnel involved in the fire fight and be included in briefings for fire line personnel. |
REC104-2282 | 25 - Inquiry, audit, lessons management and after action review | That quality control or performance assessments are routinely completed post fire season, to ensure that contractors who have not performed to an agreed standard are not re-engaged for the consequential rehabilitation works. |
REC104-2280 | 14 - Incident Mgt Teams | That DSE and CFA ensure that: |
REC104-2222 | 22 - Role of local Gvt | That Municipal Councils: |
REC104-2333 | 25 - Inquiry, audit, lessons management and after action review | That in doing so, this Review must consult with the agencies mentioned above, and others such as VICSES and the Departments of Human Services and Primary Industries. |
REC104-2291 | 28 - Personal responsibility | That after each fire season, measures of the effectiveness of aerial firefighting be collated, analysed and used for the assessment of the State Aircraft Fleet composition and the adequacy of Training and Accreditation programs. |
REC104-2269 | 14 - Incident Mgt Teams | That the fire agencies ensure that Incident Action Plans developed by Incident Management Teams are consistent with, and built on, the agreed Fire Control Priorities. |
REC104-2281 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA work cooperatively to review the management and application of bulldozers in fire suppression operations to ensure that they are used effectively, appropriately and are adequately supervised. |
REC104-2279 | 14 - Incident Mgt Teams | That operational briefings in multi-agency fires should, wherever possible, be joint briefings of all agencies involved. |
REC104-2332 | 25 - Inquiry, audit, lessons management and after action review | That the Review of emergency operations centres by the Departments of Premier and Cabinet and Treasury and Finance and the Office of the Emergency Services Commissioner: |
REC104-2267 | 14 - Incident Mgt Teams | That DSE and CFA develop an agreed process for the effective transfer of control from one Incident Control Centre to another, including processes for communicating this change to fire ground supervisors and local communities. |
REC104-2277 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA review methods of gathering and processing fire information to ensure all methods are pursued to greatest effect. |
REC104-2275 | 14 - Incident Mgt Teams | That the ‘Incident Objectives’ established for any response should reflect the endorsed Statewide ‘Fire Control Priorities’, and the relevant Municipal Fire Management Plan. |
REC104-2293 | 25 - Inquiry, audit, lessons management and after action review | That aviation contractors be required to submit a copy of their annual independent regulatory compliance audit prepared for Civil Aviation Safety Authority to the State Aircraft Unit. |
REC104-2262 | 14 - Incident Mgt Teams | That the practice of appointing Deputy Planning Officer, Deputy Operations Officer and Deputy Logistics Officer in an Incident Management Team be abandoned. This recommendation acknowledges the benefits of retaining a Deputy Incident Controller from the support agency (in accordance with section 4.2.6 of the Emergency Management Manual Victoria), to ensure that the command structure of that agency is preserved. |
REC104-2228 | 25 - Inquiry, audit, lessons management and after action review | That the Government identifies an appropriate body, or bodies, to undertake the audit of the Municipal Fire Management Plans. |
REC104-2273 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader be given flexibility to alter tactics to take advantage of changed conditions on the fire ground. |
REC104-2292 | 25 - Inquiry, audit, lessons management and after action review | That a systematic performance audit of State Aircraft Fleet contractors be conducted jointly by agency and SAU personnel. |
REC104-2258 | 14 - Incident Mgt Teams | That, wherever possible, Incident Management Team members from DSE, CFA and MFESB who are likely to be deployed together to manage fire, should train and exercise together. |
REC104-2223 | 10 - Infrastructure | That Government review legislation for utilities operating within the State to ensure their involvement in regional fire preparedness and mitigation planning. |
REC104-2197 | 25 - Inquiry, audit, lessons management and after action review | That a review of the fuel management zones be implemented with a view to reducing the number of zones so as to focus clearly on (i) asset protection (especially at the Public/Private land interface), and (ii) ecological burns. |
REC104-2272 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader on the fire ground are actively encouraged to provide input into the selection of strategies and tactics. |
REC104-2284 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA review the management of personnel deployed ensuring that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2167 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority, in conjunction with the respective state and territory governments, ensure the survivability of essential communication installations during fire incidents by strategic fuel management around the assets. |
REC098-2155 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that Emergency Management Australia initiate a process involving Australasian Fire Authorities Council and the Australian Assembly of Volunteer Fire Brigades Association to review |
REC098-2163 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority jointly with the Australasian Fire Authorities Council: |
REC098-2138 | 10 - Infrastructure | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments resolve to increase water access points for bushfire fighting on public land to the minimum national standard. |
REC098-2142 | 5 - Hazard reduction burns | The Committee recommends that the Commonwealth seek to ensure that the Council of Australian Governments seek agreement from the states and territories on the optimisation and implementation of prescribed burning targets and programs to a degree that is recognised as adequate for the protection of life, property and the environment. The prescribed burning programs should include strategic evaluation of fuel management at the regional level and the results of annual fuel management in each state should be publicly reported and audited. |
Rec-ID | Code | Recommendation |
---|---|---|
REC061-3423 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that the Metropolitan Fire Brigades Board be reviewed five years from the tabling of this report in Parliament. |
REC061-3258 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that the Metropolitan Fire Brigades Board be reviewed five years from the tabling of this report in Parliament. |
Rec-ID | Code | Recommendation |
---|---|---|
REC037-4164 | 22 - Role of local Gvt | The role of local government in counter—disaster affairs be clearly defined and formalised by legislation. Local government authorities would then be fully aware of their responsibilities and of their entitlement to financial and other counter—disaster resources from State Government level. [Reference paragraphs: 232 to 233] |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4143 | 5 - Hazard reduction burns | It be made clear to all fire control officers that the conditions for burning prescribed in the Bush Fires Act are minimal only, and that it is their duty to prescribe such further conditions as will ensure that should unfavourable weather conditions un-expectedly develop a situation would not arise which the local bush fire control organisation could not reasonably be expected to handle. |
REC019-4142 | 5 - Hazard reduction burns | Landowners desiring to carry out developmental burns be required to inform the local authority sufficiently early to enable that body to direct them or request the local bush fire brigade to carry out protective burning around the area before the prohibited season starts. |
REC019-4149 | 10 - Infrastructure | A sub-committee of telecommunication officers and representatives of the Bush Fires Board be appointed to investigate and encourage the development of a modern system of radio equipment for bush fire brigades. |
REC019-4152 | 5 - Hazard reduction burns | The Forests Department make every endeavour to improve and extend the practice of control burning to ensure that the forests receive the maximum protection practicable consistent with silvicultural requirements. |
REC019-4148 | 10 - Infrastructure | The Commonwealth Government be asked to complete as far as practicable, the connection of telephones to outlying country centres before the end of 1961. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |
Rec-ID | Code | Recommendation |
---|---|---|
REC013_3968 | 22 - Role of local Gvt | Any number of persons, wishing to form a Bush Fire Brigade, may, by a majority vote of the ratepayers in the particular area, requisition the Shire Council to proclaim such area a Bush Fire Brigade area, and the Council may then impose, with the concurrence of a majority of such ratepayers, a special levy for the purpose of equipping such brigades and carrying out its neccessary functions. |
REC013_3967 | 22 - Role of local Gvt | Each Shire Council shall divide the lands within their respective shires into suitable areas for the formation of Bush Fire Brigades as requested. |
REC013_3975 | 5 - Hazard reduction burns | To burn, where necessary, at least 33 feet where there is a risk of fire, on the outside of the railway fence, in conjunction with the railway employees. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |